(a) The period of time allocated for the substantial completion of the work shall be stated as a calendar date or as a specific number of calendar days.
(b) The department, with input from the design professional, shall decide on the liquidated damages for failure to meet the substantial completion deadline.
(c)
(1) The liquidated damages shall be included in the project specifications.