(a) Where a project size or complexity requires funding in stages and takes many years to complete, the department and design professional shall take the following steps to ensure project completion in a timely and prudent manner:
- (1) Be aware that future funding is subject to termination;
- (2) Work to the budget established in the funding for each phase or portion of the project;
- (3) Establish a building program for the established budget for each phase only;
(4)
- (A) Base all work in the schematic design and design development and construction bid documents for the funded portion of the project only.
- (B) Do not obligate the department for design services beyond the project funding limits.
- (C) Any authorization for design professional services beyond available funding must be approved in writing by both the Design Review Section and department officials;
- (5) Do not bid or obligate funding for partial construction, such as slab work only, for a project which will be unused and of no value until future funding is established for completion; and
- (6) Coordinate project requirements as to master planning, funding, and program review in the schematic design plan review submittal to the department.