- (a) Refer to 22 CAR § 111-410 for basic schedule requirements.
(b)
- (1) For projects utilizing a fast track methodology, the design professional shall assist the agency in developing a request for proposals package to be utilized in the selection process for the contractor or construction manager.
- (2) The RFP shall be submitted to the Design Review Section and Construction Section for review and approval prior to issuing to potential contractors.
- (3) The requirements of the RFP shall closely match the requirements of a schematic design plan review submittal.
- (4) Include appropriate specifications for the desired building materials and equipment.
(c)
(1) The department shall submit a schedule of activities listing the proposed milestone submittal dates to the Building Authority Division including but not limited to the following:
- (A) Submittal of request to begin selection of the design professional;
- (B) Submittal of request to select commissioning agent, if applicable;
- (C) Submittal of contractor selection RFQ document for review and approval;
- (D) Submittal of design professional services contract for approval;
- (E) Submittal of commissioning agent services contract, if applicable;
- (F) Submittal of contractor contract;
- (G) Submittal of first plan review; and
- (H) Beginning date of construction phase and expected duration of construction.
- (2) Refer to 22 CAR § 111-1707(e) for submittal schedule requirements using fast track construction.
Codification Notes: "RFP" means request for proposals. "RFQ" means request for qualifications.