(a)
- (1) Bid date requests to the Construction Section may not be made until approval from the Design Review Section has been given.
- (2) If the design professional is responsible for coordinating the bid date, written approval must be secured from the department prior to bidding.
(3) The Construction Section must be contacted to coordinate a bid:
- (A) Date;
- (B) Time; and
- (C) Location.
- (4) Upon coordination with the Construction Section, the project may be advertised and bid documents released to bidders.
- (5) Refer to 22 CAR §§ 112-201 and 112-304.
- (b) For projects subject to Building Authority Division bidding and contract management, a separate submittal of the front end documents may be required to the Construction Section prior to the establishment of a bid date.
- (c) A department may not enter into a contract for a negotiated capital improvement project unless allowed by law and prior approval of plans and specifications has been provided by the Design Review Section.