(a)
- (1) For the activities listed in subsections (b) and (c) of this section, the owner or operator shall submit an NOI to the Division of Environmental Quality by either hand delivery, postmarked by United States Postal Service, or postmarked by commercial delivery service at least ten (10) working days before asbestos stripping, removal work, or any other activity begins, such as site preparation that would break up or dislodge or similarly disturb asbestos-containing material.
- (2) Such notice must be accompanied by the required fee which is described in Subpart 16 of this part.
(b) For any renovation project, including any nonscheduled renovation operation involving the following amounts of RACM:
- (1) At least eighty linear meters (80 m) (two hundred sixty linear feet [260’]) on pipes;
- (2) At least fifteen square meters (15 m2) (one hundred sixty square feet [160 ft2]) on other facility components; or
- (3) At least one cubic meter (1 m3) (thirty-five cubic feet [35 ft3]), where the length could not be measured previously.
- (c) For any renovation project, including any nonscheduled renovation operation involving the following amounts of resilient floor and/or associated mastic covering which contains ACM (even if no RACM is present) at least fifteen square meters (15 m2) (one hundred sixty square feet [160 ft2]).
Codification Notes: “NOI” means notice of intent. "RACM" means regulated asbestos-containing material.