15 CAR § 94-112
Preconstruction meeting
Arkansas Code § 15-5-207
(a) All recipients must participate in a preconstruction meeting with the Arkansas Development Finance Authority staff prior to beginning any work on the development.
(b) A final set of plans must be submitted to the authority’s staff for review at least two (2) weeks prior to the scheduled preconstruction meeting.
(c) No recipient may begin construction or rehabilitation prior to the authority issuing a Notice to Proceed, which cannot be issued any earlier than the date of the preconstruction meeting.
(d) The recipient’s developer, architect, general contractor, job superintendent, and the person that will be preparing draw requests must be present at the preconstruction meeting.