(a)
- (1) It is understood and agreed that any changes to the original application must be submitted to the Arkansas Development Finance Authority in writing for review and approval.
- (2) A processing fee of five hundred dollars ($500) must be submitted with each change request per project.
- (3) The type of change will require different documentation and time frames for submission.
- (4) The authority has categorized the changes that require additional time and additional documentation below.
- (5) A general change request will require a written explanation explaining the reason for the change and accompanied with any required documentation as outlined in I.R.C. § 42 as it relates to the change.
(b)
- (1) Change requests must be submitted to the authority prior to implementing the change.
- (2) If the change has already been completed prior to the authority’s approval an additional five hundred dollars ($500) will be required for late submission and not obtaining the authority’s prior approval to implement the changes.
(3)
- (A) If the changes were implemented prior to the authority’s approval due to circumstances that required immediate action, the authority will consider a waiver of the five hundred-dollar late submission fee.
- (B) An example would be replacement of a management company that did not provide advance notice that they were removing themselves as the managing agent or any immediate project changes due to illegal activities.