(a)
- (1) The borrower shall provide the Arkansas Natural Resources Commission staff with notification that the project is complete and make a written request to the commission staff for final inspection.
- (2) The commission staff will conduct a final on-site inspection of the project and may perform a review of any financial assistance records.
(b) The commission staff will not approve the final project inspection until:
- (1) The borrower has obtained commission staff approval of the final operation and maintenance manual; and
- (2) Record drawings have been furnished to the borrower and the commission staff as provided in 15 CAR § 26-606.
(c)
- (1) The project will not be considered physically complete until the work as defined in the engineering report and the plans and specifications approved by the commission staff has been fully done and accepted by the borrower and commission staff.
- (2) Following an acceptable final inspection by the commission staff, the commission staff will provide written acceptance to the borrower and the final construction disbursement shall be requested.
- (3) Final acceptance of the project by the borrower will not be made without commission staff approval.