- (a) The Arkansas Natural Resources Commission staff approval of the plans and specifications does not relieve the borrower of any liabilities or responsibilities with respect to the design, construction, operation, or performance of the project.
(b) The commission staff will approve the plans and specifications provided the documents:
- (1) Conform to the requirements of 15 CAR §§ 26-401 – 26-402;
- (2) Are consistent with all relevant statutes and program requirements;
- (3) Pass a biddability, operability, and constructability review by the commission staff;
- (4) Are consistent with the planning documents and environmental determinations required by 15 CAR § 26-305; and
- (5) Have been approved by each state and federal agency having jurisdiction over the project.