(a)
- (1) The project priority list is an ordered listing, prepared according to the priority system, of projects anticipated to receive loans.
- (2) All projects eligible for loan assistance must be included on the state's project priority list.
- (3) Loan assistance may be provided whatever the rank on the state's project priority list based on readiness to proceed with construction.
(b)
- (1) The Arkansas Natural Resources Commission staff may revise the project priority list according to provisions in 15 CAR § 26-205 as necessary to manage the Construction Assistance Revolving Loan Fund efficiently.
- (2) The commission staff shall submit the priority list to the United States Environmental Protection Agency for approval.
(c)
- (1) If a community not in the priority list seeks funding or the factors for a community on the priority list change, the priority list will be amended to reflect these changes.
- (2) The result of these changes will not affect communities that have already submitted a preapplication.
- (d) Any amendment to the priority list made for these reasons will be considered minor and subject to the rules for that type of revision.
(e)
- (1) All projects will be ranked, and loans will be awarded from the priority list.
- (2) In any joint project, the combined entities must have problems in common, or both entities must be contributing to an existing water quality violation.
(f)
- (1) The project cost estimates shown in the priority list are updated from information provided by the entities listed.
- (2) These estimates will be adjusted based upon final eligibility determinations and changes in project situations at the time of the loan closing.