(a) The excavator for an excavation project that qualifies for a complex or large project shall provide the underground facility operator, via the one-call notification system, with notice of the planned complex or large project not less than five working days prior to the planned complex or large project pre-excavation planning meeting. The notice shall follow the guidelines established for complex or large projects which shall include, but not be limited to, all of the following: