- (1) Corrections shall be completed within the specified period of time, normally twenty (20) days after receipt, or written justification must be provided to the Commission nolater than the specified completion date. The Administrator may approve a writtenrequest for an extension of time.
- (2) When corrections or repairs of defects are completed, the responsible member of theindustry shall forward to the Commission a signed letter or memorandum along withdocumentation certifying corrections have been made.
- (3) Once the Commission receives documentation indicating corrections have beencompleted, the homeowner will be contacted for verification. If there is still aconflict, the Commission will schedule an on-site inspection to resolve the dispute;then the file may be closed. The responsible party may be required to pay theCommission’s expenses for the inspection.
Author: Jim Sloan
Statutory Authority: Code of Ala. 1975, §24-6-4.
History: New Rule: Filed December 6, 2002; effective January 10, 2003.