(1) Extension by the state agency.
(a) The state agency may extend the project review period for a period not to exceed thirty (30) days with or without the consent of the applicant under the following conditions:
- 1. to allow time for competing or comparable applications to be heard in the same review cycle;
- 2. to allow additional time for review of difficult and complicated projects;
- 3. to allow the project to be reviewed at the next meeting of the Certificate of Need Review Board.
- (b) The state agency may extend the review period without limitation with the written consent of the applicant.
- (2) Extension by the applicant. The review period may be extended upon written request of the applicant for a period not to exceed thirty (30) days on a one-time basis.
Statutory Authority: Code of Ala. 1975, §22-21-275(3).