Owners or operators of all facilities must design, construct and maintain:
- (1) A run-on control system to prevent flow onto the active and/or closed portions of the landfill during the peak discharge from a 25-year storm;
- (2) A run-off control system from the active and/or closed portions of the landfill to collect and control at least the water volume resulting from a 24-hour, 25-year storm.
- (3) On-site drainage structures to carry incident precipitation from the disposal site so as to minimize the generation of leachate, erosion and sedimentation. Run-off from the active and/or closed portions of the landfill unit must be handled in accordance with 335-13-4-.01(2)(a), and (b) and shall be routed to a settling basin or other sedimentation control structure to remove sediment prior to release onto adjacent properties or waters.
Author: Russell A. Kelly
Statutory Authority: Code of Ala. 1975, §§22-27-3, 22-27-7.
History: November 18, 1981; Amended: July 21, 1988. Amended: Filed September 28, 1993; effective November 2, 1993. Amended: Filed June 21, 1996; effective July 26, 1996.