(a) The commissioner shall issue a permit if the commissioner finds that
- (1) rights of a prior appropriator will not be unduly affected;
- (2) the proposed means of diversion or construction are adequate;
- (3) the proposed use of water is beneficial; and
- (4) the proposed appropriation is in the public interest.
(b) In determining the public interest, the commissioner shall consider
- (1) the benefit to the applicant resulting from the proposed appropriation;
- (2) the effect of the economic activity resulting from the proposed appropriation;
- (3) the effect on fish and game resources and on public recreational opportunities;
- (4) the effect on public health;
- (5) the effect of loss of alternate uses of water that might be made within a reasonable time if not precluded or hindered by the proposed appropriation;
- (6) harm to other persons resulting from the proposed appropriation;
- (7) the intent and ability of the applicant to complete the appropriation; and
- (8) the effect upon access to navigable or public water.