Alaska Admin. Code tit. 3, § 52.630
Standards for nonfuel costs
Effective Sep 11, 2004Alaska Register 171(Eff. 10/28/89, Register 112; am 9/11/2004, Register 171) | Authority: AS 42.05.141, AS 42.45.110, AS 42.45.160, AS 42.05.151, AS 42.45.130, AS 42.45.170
Nonfuel costs used in the calculation of power cost equalization per kilowatt-hour are subject to the following standards:
- (1) depreciation rates must be in accordance with the guidelines established by the Rural Electrification Administration that were in effect as of January 1, 1988, or, if different, the standards established by the commission;
- (2) depreciation expense is not allowed on plant funded with grants, contributions in aid of construction, or other nonutility money; and
- (3) unless the commission authorizes a different method of cost recovery appropriate to the overhaul, costs for major overhauls on equipment must be amortized over an appropriate period approved by the commission.
(Eff. 10/28/89, Register 112; am 9/11/2004, Register 171)
Authority: AS 42.05.141, AS 42.45.110, AS 42.45.160, AS 42.05.151, AS 42.45.130, AS 42.45.170