Alaska Admin. Code tit. 3, § 50.970
(a) Not later than May 31, 2026, each electric utility required to provide a community energy program under 3 AAC 50.950 shall submit a community energy tariff under the procedures set out in 3 AAC 48.220 and 3 AAC 48.270 that includes
(3) requirements for the installation of an external disconnect switch, unless the utility determines additional disconnection capability is not necessary, and the option to
(5) the maximum aggregate nameplate capacity for all eligible community energy facilities; if the maximum nameplate capacity for all eligible community energy facilities identified in a utility's tariff is less than 5 MW, in addition to the information required by AS 42.05.727(a)(2), the utility shall provide: