Alaska Admin. Code tit. 3, § 48.070
Formal proceedings
Effective Mar 11, 2022Alaska Register 241(Eff. 1/13/73, Register 44; am 6/29/84, Register 90; am 3/11/2022, Register 241) | Authority: AS 42.05.141, AS 42.05.271, AS 42.06.290, AS 42.05.151, AS 42.05.281, AS 42.06.300, AS 42.05.171, AS 42.05.770, AS 42.06.340, AS 42.05.241, AS 42.06.140, AS 42.06.400, AS 42.05.261, AS 42.06.260
- (a) Except as otherwise provided by 3 AAC 48.030 and 3 AAC 48.650, an application for a certificate of public convenience and necessity or electric reliability organization certificate or for the revision, sale, lease, rental, or inheritance of a certificate; or for the authority to acquire a controlling interest in a certificated public utility, electric reliability organization, or pipeline carrier; or any other application required by AS 42.05 or AS 42.06, will be docketed and considered in a formal proceeding.
- (b) A tariff filing will not be docketed or considered in a formal proceeding unless it is suspended by order of the commission within the statutory notice period, or within the regulatory notice period set under 3 AAC 46.320 for an electric reliability organization.
- (c) The commission may institute a formal proceeding in regard to any jurisdictional matter, either on its own motion or on complaint.
- (d) An electric reliability organization rule or petition for a new or revised integrated resource plan under AS 42.05.780 will not be docketed or considered in a formal proceeding unless it is suspended by order of the commission within the regulatory notice period set under 3 AAC 46.260 for a new or revised integrated resource plan or 3 AAC 46.470 for an electric reliability organization rule.
(Eff. 1/13/73, Register 44; am 6/29/84, Register 90; am 3/11/2022, Register 241)
Authority: AS 42.05.141, AS 42.05.271, AS 42.06.290, AS 42.05.151, AS 42.05.281, AS 42.06.300, AS 42.05.171, AS 42.05.770, AS 42.06.340, AS 42.05.241, AS 42.06.140, AS 42.06.400, AS 42.05.261, AS 42.06.260