Alaska Admin. Code tit. 3, § 46.260
Integrated resource plan notification, protest process, and returning orders
Effective Mar 11, 2022Alaska Register 241(Eff. 3/11/2022, Register 241) | Authority: AS 42.05.141, AS 42.05.762, AS 42.05.780, AS 42.05.151, AS 42.05.770
(a) Not later than 20 calendar days before filing an integrated resource plan with the commission, an electric reliability organization shall
- (1) make a good faith effort to electronically notify each registered entity of its intent to file an integrated resource plan and make available the integrated resource plan and all non-confidential work papers that support the integrated resource plan; and
- (2) publish on its website a notice of its intent to file an integrated resource plan.
- (b) Not later than five business days after the filing of a complete integrated resource plan, the commission will arrange for publication of a public notice with a newspaper of general circulation in the geographic area of the interconnected bulk-electric system. The commission will also publish the notice on the commission's website and post it on the Alaska Online Public Notice System (AS 44.62.175). The deadline for the public comment period is 14 calendar days from the date of the public notice.
(c) An interested person may file with the commission comments or a protest of the petition and integrated resource plan in accordance with the requirements of 3 AAC 48.100 before the close of the comment period. A protest must include
- (1) specific grounds for the protest;
- (2) the steps that the petitioner may take to mitigate the protest;
- (3) the conditions that the commission should consider applying to the integrated resource plan; and
- (4) a petition to intervene.
- (d) A petitioner wishing to file a response to the protest shall file that response with the commission not later than 10 calendar days after the close of the comment period.
(Eff. 3/11/2022, Register 241)
Authority: AS 42.05.141, AS 42.05.762, AS 42.05.780, AS 42.05.151, AS 42.05.770