For regulatory cost charges for geothermal wells on a supplemental appropriation for a fiscal year,
- (1) the commission will determine regulatory cost charges using the commission's determinations of geothermal resources and well operatorship previously made in connection with the regular appropriation for the fiscal year;
- (2) in applying the formula set out in 20 AAC 25.720(a), the commission will set the variable "Lg" equal to zero;
(3) the commission will use the procedures set out in 20 AAC 25.730, except that the period
- (A) for submitting comments or requesting a revision under 20 AAC 25.730(b) is 10 days instead of 30 days;
- (B) within which a public hearing will be held under 20 AAC 25.730(c) is 20 days instead of 60 days; the commission will provide notice of that hearing at least 10 days before the date of that hearing; the 30-day notice requirement under 20 AAC 25.540 does not apply to a hearing held under this paragraph; and
- (C) within which the commission will issue an order determining regulatory cost charges under 20 AAC 25.730(d) is 30 days instead of 90 days;
- (4) 20 AAC 25.735 does not apply; and
- (5) the commission will set the payment date for regulatory cost charges to be at least 10 days after the date the commission provides notice under 20 AAC 25.730(d).
(Eff. 9/30/2010, Register 195)
Authority: AS 41.06.005, AS 41.06.040, AS 41.06.055, AS 41.06.035, AS 41.06.050