- (a) An applicant must pay the appropriate fee as listed in the following table for a permit issued under this chapter or 18 AAC 83.110, or for certification of a permit required by 33 U.S.C. 1341 (Clean Water Act, sec. 401): INDIVIDUAL PERMIT FEES1 Fee (in dollars) (1) Annual fee for a domestic wastewater system covered under a general permit, with a daily maximum permitted flow, in gallons per day (gpd), of (A) 0 - 100,000 655 (B) 100,001 and over 7,920(2) Annual fee for power generation cooling water discharge by a facility 6,520(3) Annual fee for seafood processing that is not covered under the general permit 7,040(4) One-time fee for seafood processor modifications within the same year 325(5) One-time application fee for certification under 33 U.S.C. 1341 of a "dredge-or-fill" permit issued under 33 U.S.C. 1344 (Clean Water Act, sec. 404), for2 (A) Airport project320 (B) Other projects or department activities as follows: (i) waiver of certification under 33 U.S.C. 1341130 (ii) project disturbing less than one acre600 (iii) project disturbing 1 - 5 acres 765 (iv) project disturbing 5.01 to 20 acres1,160 (v) project disturbing greater than 20 acres2,375(6) Annual fee for harbor dredge projects 1,080(7) Annual fee for individual permit for a municipal separate storm sewer system (MS4) 9,115(8) Annual fee for bulk fuel and small oil terminals with only a few low- volume discharges 6,490 Notes to table: 1 If the applicant is a business with fewer than 20 employees, the fee is reduced by a travel cost of $85. 2 Mine projects and pipelines eight inches or greater in diameter are subject to a fee as described in 18 AAC 72.959.
- (b) For one-time fees, an applicant for a permit shall pay the fee within 30 days after issuance of the billing.
- (c) For annual fees, fees are billed annually and must be paid within 30 days after issuance of the billing.
- (d) If a new permit application is received not earlier than October 1 and not later than December 31, the applicant shall pay one-half of the annual fee required under (a) of this section for that year.
- (e) For any annual fee received more than 30 days after issuance of the billing, a late fee of $20 is charged for each month that the payment is late.
- (f) A fee required under (a) of this section is not refundable.
- (g) If a permit is transferred from an existing owner or operator to a new owner or operator, the new owner or operator shall pay the applicable fees described in (a) of this section during the next annual billing cycle.
- (h) An owner or operator may request in writing to terminate an existing permit if a discharge is not occurring. If a permit is terminated at the request of the owner or operator, the owner or operator must file a new application and pay a new application fee for a new permit before resuming the wastewater discharge.
(Eff. 1/17/2002, Register 161; am 12/23/2009, Register 192; am 10/22/2016, Register 220; am 10/1/2023, Register 247)
Authority: AS 37.10.052, AS 46.03.020, AS 46.03.110, AS 44.46.020, AS 46.03.050, AS 46.03.710, AS 44.46.025, AS 46.03.100