- (a) An owner or operator shall submit each sampling and analytical testing report required under AS 46.03.460 - 46.03.490 to the department not later than 21 days after completion of the analytical testing for each sampling event.
(b) The sampling and analytical testing report must include
- (1) the date, time, and on board location where each sample was collected;
- (2) the sampling technique and analytical testing method used for each sample;
- (3) the quality assurance and quality control analysis of the sampling, analytical testing, and analytical data;
- (4) the analytical results;
- (5) any deviation from the approved plan submitted under 18 AAC 69.025;
- (6) any deviation from the approved plan submitted under 18 AAC 69.030;
- (7) the type of wastewater sampled; and
- (8) if necessary, a notification that resampling under 18 AAC 69.070 is occurring.
(Eff. 11/15/2002, Register 164; am 12/16/2013, Register 208)
Authority: AS 46.03.460, AS 46.03.465