Alaska Admin. Code tit. 18, § 60.213
Research, development, and demonstration permit
Effective Oct 27, 2017Alaska Register 224(Eff. 9/5/2010, Register 195; am 10/27/2017, Register 224) | Authority: AS 44.46.020, AS 46.03.100, AS 46.03.810, AS 46.03.010, AS 46.03.110, AS 46.06.010, AS 46.03.020, AS 46.03.800, AS 46.06.080
(a) The owner or operator of a permitted Class I MSWLF with a liner approved under 18 AAC 60.330 and a leachate collection system designed and constructed to maintain less than a 12-inch depth of leachate on the liner may apply for a research, development, and demonstration permit if the owner or operator proposes to utilize innovative and new methods that vary from one or more of the following requirements:
- (1) the requirement to construct and maintain a run-on control system in accordance with 18 AAC 60.225(c);
- (2) the restriction under 18 AAC 60.360(a)(1)(B) on the placing of bulk or noncontainerized liquid waste in the MSWLF.
(b) The application for a research, development, and demonstration permit must be submitted to the department using a form provided by the department. The application must include
(1) a cover letter that contains
- (A) a statement that the applicant seeks a research, development, and demonstration permit;
- (B) a statement that identifies the requirement listed in (a) of this section from which the applicant requests a variance; and
- (C) a brief general description of the site topography, geology, climate, surface hydrology, and groundwater hydrology;
- (2) documentation demonstrating that the leachate collection system is designed and constructed to maintain a leachate depth of less than 12 inches;
- (3) a research plan that includes a detailed description of the proposed research project and a detailed statement of project goals;
- (4) waste types and quantities that will be managed as part of the research, development, and demonstration project;
- (5) an operation and contingency plan specific to the proposed research, development, and demonstration project;
- (6) drawings that show changes to the facility based on the proposed research, development, and demonstration project;
- (7) a monitoring plan that includes monitoring specific to the proposed research, development, and demonstration project;
- (8) a corrective action plan that describes procedures that will be taken if the proposed research, development, and demonstration project results in landfill damage, environmental damage, or improper waste disposal; and
- (9) other information that the department requests and that the department considers relevant to compliance by the applicant with this chapter.
- (c) The department will assess a fee in accordance with Table E-1 in 18 AAC 60.700(a) for a research, development, and demonstration permit.
(d) In addition to applying the criteria in 18 AAC 60.215(a)(1) - (9), the department will issue a research, development, and demonstration permit only if the applicant demonstrates, to the department's satisfaction, that
- (1) the proposed project includes a defined project goal and quantitative methods to measure progress toward that goal; and
- (2) the criteria and innovative and new methods proposed for the project are at least as protective of human health and the environment as the criteria for a Class I MSWLF permit issued under this chapter.
(e) In a research, development, and demonstration permit, the department will include conditions that
- (1) only allow the MSWLF to accept waste types and quantities relevant to the research proposal and approved by the department; and
(2) require, during the life of the permit, the submission of progress reports every six months; each progress report must include
- (A) a description of progress towards the stated project goals;
- (B) a summary of all monitoring and testing results;
- (C) operating information related to permit conditions required by the department; and
- (D) any problems encountered during the reporting period.
(f) The department will not issue a research, development, and demonstration permit for a term longer than three years. The department will not renew a permit
- (1) more than three times; and
(2) unless the applicant submits a request for renewal in writing, using a form provided by the department; the request must include
- (A) a detailed assessment of the project, showing the status with respect to achieving project goals, and a list of problems and progress towards resolution of those problems; and
- (B) other information that the department requests and that the department considers relevant to compliance by the applicant with this chapter.
(Eff. 9/5/2010, Register 195; am 10/27/2017, Register 224)
Authority: AS 44.46.020, AS 46.03.100, AS 46.03.810, AS 46.03.010, AS 46.03.110, AS 46.06.010, AS 46.03.020, AS 46.03.800, AS 46.06.080