Alaska Admin. Code tit. 18, § 15.020
Permit applications
Effective Apr 10, 2010Alaska Register 194(Eff. 11/25/77, Register 64; am 1/7/87, Register 100; am 8/2/90, Register 115; am 2/15/98, Register 145; am 7/11/2002, Register 163; am 4/10/2010, Register 194) | Authority: AS 46.03.020, AS 46.03.320, AS 46.03.730, AS 46.03.100, AS 46.03.330, AS 46.03.110, AS 46.03.720
- (a) Except as provided in 18 AAC 15.130 - 18 AAC 15.140, an applicant for a permit or written approval subject to 18 AAC 15.020 - 18 AAC 15.100 must serve a complete application on the department.
(b) An applicant must serve a complete application under (a) of this section for the department's review at least
- (1) five days before the proposed commencement of the operation, for applications for surface oiling permits;
- (2) 30 days before the proposed commencement of construction, installation, modification, or improvement, for applications for plan approvals or permits for a sewerage system treatment works, or public water system;
- (3) 60 days before the proposed commencement of construction, installation, modification, or improvement, for applications for plan approvals or permits for a municipal sewerage system, treatment works, or public water system project that involves state or federal monetary assistance;
- (4) 60 days before the proposed commencement of the operation, for an application for a solid waste disposal permit, short-term variance form water quality standards, or wastewater disposal permit; and
- (5) 100 days before the proposed commencement of a pesticide use that requires a permit under 18 AAC 90.
(Eff. 11/25/77, Register 64; am 1/7/87, Register 100; am 8/2/90, Register 115; am 2/15/98, Register 145; am 7/11/2002, Register 163; am 4/10/2010, Register 194)
Authority: AS 46.03.020, AS 46.03.320, AS 46.03.730, AS 46.03.100, AS 46.03.330, AS 46.03.110, AS 46.03.720