Alaska Admin. Code tit. 17, § 15.271
Right-of-way clearing and restoration
Effective Nov 15, 2024Alaska Register 252(Eff. 5/23/82, Register 82; am 11/15/2024, Register 252) | Authority: AS 02.15.020, AS 19.25.010, AS 35.05.020, AS 02.15.102, AS 19.25.200, AS 35.10.210, AS 02.15.106, AS 19.30.051, AS 35.10.230, AS 19.05.020, AS 19.30.121, AS 19.05.040, AS 19.40.065
- (a) Clearing for utility facility installations within department rights-of-way must be kept to the minimum that is necessary to accommodate the installation, construction, operation, and maintenance of the facility. Indiscriminate cutting of trees or the disfiguration of any feature of scenic value will not be permitted.
- (b) A utility may use chemical sprays only in compliance with applicable federal and state statutes and regulations.
- (c) Each utility shall dispose of trees, brush, debris, refuse or waste as specified in the utility permit.
- (d) The department may require the permittee to restore or replace, at the permittee's expense, trees or shrubbery damaged or disturbed during the construction. Any damage to private property must be remedied as directed by the department.
- (e) All excavated material in excess of the quantity required for backfill in a department right-of-way must be hauled by the permittee, at the permittee's cost and expense, and stockpiled as specified by the department. All unusable material must be disposed of at the permittee's expense and may not be placed within the limits of a department right-of-way unless approved by the department.
- (f) Each utility shall maintain temporary pavement patches to provide a smooth all-weather surface at all times. Permanent replacement of the temporary patches must be made as soon as practicable after all other work under the permit is completed.
- (g) The department may require seeding or sodding of the construction area to prevent soil erosion or to replace the natural vegetative cover. Seeding and sodding operations must comply with the department's Standard Specifications for Highway Construction, adopted by reference in 17 AAC 20.950(8), and with the special provisions of the utility permit. Any area of right-of-way that is adjacent to private property and that has a protective vegetative cover must be fully restored.
- (h) The department will notify the permittee of cleanup and restoration work that has not been satisfactorily performed in accordance with the provisions of the utility permit and will specify a date for completion of the corrective work. The department may perform the cleanup and restoration work that has not been completed to the satisfaction of the department by the specified date. The permittee shall reimburse the department for all work done by the department.
(Eff. 5/23/82, Register 82; am 11/15/2024, Register 252)
Authority: AS 02.15.020, AS 19.25.010, AS 35.05.020, AS 02.15.102, AS 19.25.200, AS 35.10.210, AS 02.15.106, AS 19.30.051, AS 35.10.230, AS 19.05.020, AS 19.30.121, AS 19.05.040, AS 19.40.065