Alaska Admin. Code tit. 17, § 15.031
Application for utility permit on section-line rights-of-way
Effective May 23, 1982Alaska Register 82(Eff. 5/23/82, Register 82) | Authority: AS 19.05.020, AS 19.25.200, AS 19.40.065, AS 19.05.040, AS 19.30.051, AS 19.25.010, AS 19.30.121
- (a) Utility permits are required only for section-line rights-of-way presently used or proposed for use by the department. A person seeking to install a utility facility within a section-line right-of-way shall check with the department to determine whether the department presently uses or proposes to use the affected portion of the section-line right-of-way.
- (b) Before issuing a permit for the installation of a utility facility within a section-line right-of-way, the department must be satisfied that a section-line right-of-way exists at the location where the facility is proposed to be installed by the permit applicant. The permit applicant shall furnish proof of the existence of the section-line right-of-way.
- (c) An applicant that is granted a permit for the installation of a utility facility within a department section-line right-of-way shall coordinate the installation of the facility with any proposed department project using the section-line right-of-way.
- (d) The permittee shall provide one copy of each permit for the installation of any utility facility within a department-controlled section-line right-of-way to the Department of Natural Resources.
- (e) The department will immediately submit written notice to the Department of Natural Resources if a section-line permit application is denied.
(Eff. 5/23/82, Register 82)
Authority: AS 19.05.020, AS 19.25.200, AS 19.40.065, AS 19.05.040, AS 19.30.051, AS 19.25.010, AS 19.30.121