(a) A well is considered to be completed 30 days after
- (1) drilling and testing operations have ceased and the well is capable of producing a geothermal resource;
- (2) the well has begun to produce geothermal resources, unless drilling operations are resumed before the end of the 30 day period; or
- (3) the well is plugged and abandoned.
- (b) All required logs, records and test results must be submitted to the commissioner within 60 days after completion of drilling operations.
(c) A completion report must be submitted to the commissioner within 60 days after completion of drilling operations. The completion report must provide the following information:
- (1) the actual depth of the well;
- (2) the actual depth to zone of completion;
- (3) the actual bottom-hole location for a directionally drilled well;
- (4) method of completion or abandonment; and
- (5) any information on drilling difficulties or unusual circumstances encountered which would be helpful in assuring future safety of operations or protection of the environment.
(Eff. 5/8/83, Register 86)
Authority: AS 41.06.020, AS 41.06.040