The operator shall submit a report to the commissioner within 60 days after completion of geothermal exploration and include the following information:
- (1) final hole designation and location;
- (2) a drilling log noting any water table, aquifers, and sale and mineral deposits encountered;
- (3) methods of cementing and completion, and types of casing and tubing used;
- (4) complete details of abandonment procedures;
- (5) any information on drilling difficulties or unusual circumstances encountered which may be helpful in assuring future safety of operations or protection of the environment in the area concerned; and
- (6) temperature data and logs for each hole surveyed.
(Eff. 5/8/83, Register 86)
Authority: AS 38.05.020, AS 41.06.020, AS 41.06.050, AS 38.05.181, AS 41.06.040