This action is brought to recover a portion of the purchase money paid by the plaintiff to the defendant upon a contract between them for the sale and purchase of a parcel of real estate in the city of New York, and also the expenses incurred by the plaintiff in the examination of the title, on the ground that the defendant failed to tender a good title, free from all charges and incumbrances other than those which were specified in the contract. The time fixed for closing the sale was the 10th day of Hay, 1892. On that day, by agreement between the parties, the time for per
The defendant in this case has not set up any equitable defense or counterclaimed for the specific performance of the contract, but stands upon his strict legal right to retain the money which has been paid by the plaintiff, on the ground that at law no recovery can be had if the plaintiff was at fault in refusing to perform at the time fixed for the purpose. In this situation he cannot invoke the aid of any equitable principle in support of his position, but must submit to be bound to a full and exact performance of his part of the agreement at the time specified. He had agreed to deliver to the plaintiff a title to the premises in fee simple, free from all incumbrances except those mentioned in the contract, and the plaintiff had a right
In Smyth v. Sturges, 108 N. Y. 495,15 N. E. 544, which was a similar action, the court says (page 503, 108 N. Y., and page 544, 15 N. E.):
“The vendor, having two remedies,—one damages, and the other performance,—chose the former. This right, if any, to damages, he assigned to the plaintiff, and the plaintiff has sued. In such an action the vendor must be held strictly to the very terms of his engagement, and show the performance of all the conditions on his part necessary to be performed to put the other party in default.”
The rule so clearly laid down by the court is one founded upon an essential distinction between actions for damages and actions for specific performance. In the latter the action proceeds upon the ground of the continuance of the contract, and the court can, upon equitable principles, enforce performance with due regard to the equities of the parties. In the case of actions at law, the question is not one of performance, but of damages for nonperformance. The contract is deemed to be at an end, and the remedy afforded is satisfaction for its breach. The defendant was bound to relieve the property from the liens and clouds upon his title before he could expect or demand performance on the part of the plaintiff. He was well advised of the condition of his title, and, so far as the Gauld mortgage was concerned, he had been for several months in a position to secure a proper change of the record and the cancellation of the same by the register. He did nothing, however, to compel proper action by the latter, but seems to have rested under the refusal of the register until two months after this action was brought, when he succeeded in securing a discharge of the mortgage. If the register would have discharged the mortgage, as the defendant now claims, upon the exhibition of the original and the filing of the satisfaction piece, it was the duty of the defendant to have had this done when the contract came to be closed, but he has failed to show the slightest excuse for not having done so. If, however, the register still stood upon his original refusal, it was still more the duty of the defendant to have taken appropriate legal action to compel the discharge. He had no right to expect the plaintiff to assume any such burden. He did not even attempt to remedy his situation by causing the mortgage to be satisfied immediately upon plaintiff’s refusal to take, and again tendering his deed, but allowed two months of inactivity to pass by, apparently upon the assumption that he had been under no obligation to the plaintiff in the matter. The defendant was bound also to discharge the taxes and the Croton water rents. It was not sufficient for him to offer to allow the same to the plaintiff out of the purchase money and thus cast upon the latter the obligation of seeing to the payment and discharge of the same. Morange v. Morris, *42 N. Y. 48. In this case the court says (page 51):
“In the present case the vendor was unable to perform his agreement, for the reason that the premises were incumbered with the liens for taxes and assessments admitted in the answer. By his agreement, he was not only to convey a title in fee simple, but he was to convey and assure it free from
*773 all incumbrances except as therein specified, and the incumbrances referred to were not within the exception. The existence of the incumbrances at the time fixed in the agreement for the execution and delivery of a deed was a breach of the agreement on his part, which put it out of his power to perform, and excused the plaintiff from tendering payment. The averment in the answer that the defendant would have discharged the incumbrances =■■ * * if the plaintiff had been ready and willing to perform on his part is wholly immaterial. The act of conveying the premises free from all incumbrances was to be concurrent with that of the payment of the purchase money. The plaintiff was under no obligation to pay his money to the vendor, and trust to a remedy by action for damages in case the vendor failed to remove the incumbrances. It was the duty of the defendant to have caused them to be discharged before the time arrived at which he had stipulated to convey. ” (The italics are ours.)
It may also be said that, a fortiori, the defendant had no right to compel the plaintiff to assume his obligation to pay the taxes, although accompanied by an offer to allow the amount out of the purchase money. He had not entered into any such contract, and, however such an offer may be looked npon in a court of equity, the case is one at law resting upon strict legal right,' and is without equitable aspect. Oppenheimer v. Humphreys (Sup.) 9 N. Y. Supp. 840, affirmed 125 N. Y. 733, 26 N. E. 757. It is easy for vendors of real estate to secure the insertion of appropriate stipulations in contracts of sale which will relieve them from the harshness of the rule in cases where they rely upon the money they expect to receive from the purchaser for the discharge of liens. In most cases they can also find relief from the stress of the situation in actions for specific performance, but, where they assume the position of exacting a forfeiture of the money paid by the vendee upon the contract, they do so nnder claim of compliance with the conditions of the contract on their part, and they cannot justly complain of the demand which the law makes that such compliance shall be full, exact, and timely. The defendant cannot now claim that he had or was entitled to any additional time in which to remedy the defects complained of. Where the contract is treated as at an end, by reason of the failure to perform at the time fixed for the purpose, and the equitable power of the court is not invoked to compel specific performance, time is of the essence of the contract, and certainly may be made so by the acts of the parties. Schmidt v. Reed, 132 N. Y. 108, 30 N. E. 373. In this case (page 113, 132 N. Y., and page 373, 30 N. E.) the court says:
“While, at law, the stipulated time of performance of a contract of sale and conveyance of land is of the essence of the contract, it is not essentially so in equity, and there, where the situation of the parties and property remains unchanged, relief will not necessarily be defeated by delay.”
Also: “The parties to a contract may, by its terms, make the time of performance essentially important, and its observance in that respect requisite to relief. Benedict v. Lynch, 1 Johns. Ch. 370. And, when that is not so, either of the parties to the contract may, by a reasonable notice to the other party for that purpose, render the time of performance as of the essence of the contract, and avail himself of forfeiture on default. Myers v. De Mier, 52 N. Y. 647.”
The case shows that, several days prior to the adjourned day for closing the contract, the counsel for the plaintiff notified the defendant’s attorney that he would insist that the liens and charges upon