Zlydasdyk v. Lucas

185 N.W.2d 838 | Mich. Ct. App. | 1971

29 Mich. App. 584 (1971)
185 N.W.2d 838

ZLYDASDYK
v.
LUCAS

Docket No. 8354.

Michigan Court of Appeals.

Decided January 20, 1971.
Leave to appeal denied March 25, 1971.

Paul L. Greer (Theodore A. Caris, of counsel), for plaintiffs.

Shepherd & Shepherd, for defendants.

Before: FITZGERALD, P.J., and QUINN and McINTYRE,[*] JJ.

Leave to appeal denied March 25, 1971. 384 Mich. 821.

FITZGERALD, P.J.

Thomas and Olive Lucas, defendants in the present case, are owners of certain lakeside property in Newaygo County. The particular land in question was purchased in 1955 and consists of three lots adjacent to Pettit Lake and an island separated from these lots by a short expanse of water. From 1955 until 1960, the Lucas' only means of access to the island was by small boat.

During the summer of 1960, plans were formulated for the construction of a bridge which would eventually connect their mainland property with the island. In February 1961, muck was dredged from the site to facilitate construction. The necessary materials were delivered and remained in open view until early spring when actual construction began. *586 The bridge was to span causeways which had been constructed on fill extending approximately 160 feet from the island in toward the mainland and about 75 feet from the mainland out toward the island. The project was substantially under way during the month of March and in July of 1961 it was completed. Following completion of the bridge, defendants expended considerable amounts in constructing a home on the island.

Plaintiffs, who are neighboring lakefront landowners, knew of the bridge, but took no action until May 11, 1967, when an action was brought alleging conduct by defendants which interfered with their respective littoral rights. The trial began in June 1968 with additional testimony taken in August and September. On October 15, 1969, a judgment was entered, the court ruling that the area of the bridge and land fill was navigable water and the bridge was unlawfully constructed. Defendants' claim of laches was rejected and an injunction issued ordering removal of the bridge, 100 feet of westerly fill, and 30 feet of easterly fill adjacent to the bridge. Defendants appeal as of right from the decision of the trial court.

Defendants now contend that the trial court erred in rejecting their argument that plaintiffs should be denied the relief sought on the basis of laches. In addressing itself to the question of laches, the trial court stated:

"It is true that the plaintiffs have been tardy in exercising their rights, however, the mere passage of time is not a sufficient basis for laches. This is especially true where plaintiffs are seeking protection of a vested legal right. Taylor v. S.S. Kresge Co. (1950), 326 Mich. 580. The defendants constructed the bridge in a relatively short time during the winter season, and the plaintiffs were faced *587 with an accomplished fact except that defendant thereafter proceeded to erect a home on the island after completion of the bridge."

While we readily concur with the trial court in its belief that the mere passage of time is not in itself a sufficient basis for laches, careful consideration must be accorded the respective interests of the parties in application of this doctrine. This equitable doctrine is set forth and explained in our previous decision in Sloan v. Silberstein (1966), 2 Mich. App. 660, 676, where it was stated:

"Laches differs from limitations in that limitations are concerned with the fact of delay, laches with the effect of delay. Laches is concerned principally with the question of the inequity of permitting a claim to be enforced and depends on whether plaintiff has been wanting in due diligence. Limitations are statutory, while laches is not."

In applying the principles set forth above, we find that plaintiffs, although cognizant of the altered physical condition of defendants' property, made no effort to enforce or protect their own rights from the time the bridge was completed in 1961 until the summer of 1967, six years later. During this six-year period, defendants invested considerable time, effort, and money in constructing a permanent residence upon the island. In addition to the lack of due diligence in pursuing their claim, plaintiffs now seek the removal of the bridge itself, which would result not only in great physical hardship for defendants, but undoubtedly would render the island and home much less valuable.

The opinion of the trial court as well as the plaintiffs' brief reflects considerable emphasis on Taylor v. S.S. Kresge Co. (1950), 326 Mich. 580, stressing that the equitable doctrine of laches has *588 little basis where the parties are seeking in equity to protect a vested right. This case is easily distinguished, for in Taylor the legal right which the plaintiff sought to protect was that of record title to land, and though the action was equitable in nature, the balance of equities, in contrast to the present case, were with the plaintiff. In Michner Plating Company v. Davis Drilling Co., Inc. (1968), 10 Mich. App. 358, this Court held that a strict legal right, if incompatible with the equities of the case, does not necessarily entitle one to equitable redress. In addition, the record contains sufficient evidence of the fact that during the interval between completion of the bridge and commencing of the original action, defendants' position has materially changed and granting the equitable relief sought by plaintiffs would cause considerable hardship.

Therefore, upon consideration of the lack of due diligence of plaintiffs in pursuing their claim and the effect upon the equities of the situation, we must conclude that the trial court improperly rejected a clear showing of laches.

The judgment of the trial court is reversed and the injunction vacated. Costs to appellants.

All concurred.

NOTES

[*] Circuit judge, sitting on the Court of Appeals by assignment.

midpage