272 F. 954 | 3rd Cir. | 1921
This case grows out of the bankruptcy of the Faber Engineering & Construction Company, and con
The case, therefore, in substance resolves itself into narrow limits, namely, what, under the law of Pennsylvania, would have been the rights of a levying execution creditor of the Eaber Engineering Company? No question of fraud or bad faith is involved. For a present and sufficient consideration, the Faber Company sold the personal property to the claimant, and while the latter did not take possession, this fact in no way affected the validity of the sale as between the two parties, and the buyer could therefore take possession thereof at any time. But by leaving the property in the hands of the seller, the buyer subjected them to levy and sale by an execution creditor of the seller. In that regard this court, in Re Komara, 251 Fed. 47, 163 C. C. A. 297, said:
“Undoubtedly the Pennsylvania decisions, from Clow v. Woods, 5 Serg. & R, 275, 9 Am. Dec. 346, with the intervening cases, to Barlow v. Fox, 203 Pa. 114, 52 Atl. 57, hold that retention of possession when actual delivery is practical is a fraud in law, and will not avail against creditors.”
On the other hand, the Pennsylvania law is equally clear that, if in the interim of possession by the buyer no execution creditor of the seller levies and the buyer thereafter takes possession, the sale takes effect as of its date, Christ v. Zehner, 212 Pa. 192, 61 Atl. 822, and consequently the potential right of an execution creditor to levy necessarily ends.
We are of opinion the court below rightly adjudged the trustee in bankruptcy showed no title to these goods. Its decree is therefore affirmed.
The receiver has procured a rule upon the Southern Surety Company to show cause why certain property, consisting of tools and equipment used in constructing highways, which had been in the possession of the bankrupt should not be delivered to the receiver. The bankrupt had a contract with the state of Pennsylvania for the construction of a state highway in the county of Mercer, under date of June 10, 1919, and for the performance of said contract by the bankrupt the Southern Surety Company became the surety to the commonwealth. At the time of entering into the contract of suretyship, the bankrupt assigned said property to the surety as collateral, for the faithful performance of the contract. The form of that contract was in prsesenti, .and not in futuro. In other words, it was not an agreement to transfer the property at a future date. The bankrupt proceeded with the construction of the highway until perhaps some time in January, 1920, and received from time to time the moneys earned for the work as it progressed. In January, 1920, the surety took possession of all of the said equipment and retained possession thereof, subject of course to such right as the commonwealth of Pennsylvania had under its contract. The contract with the commonwealth provided that the compensation to be paid thereunder should be not alone for the performance of the work, but “for furnishing all materials, labor, tools and equipment.” The contract with the commonwealth also provided that upon failure of performance of certain- terms, the engineer for the highway department should give notice to the contractor and its surety of such default, and that upon the contractor’s failure to comply with such notice the highway commissioner could take the work out of the contractor’s hands and appropriate or use any or all materials and equipment on the ground, and complete the work, and should the cost of completion exceed the amount to be paid under the contract, the contractor and the surety should be liable to pay such excess.
On the 3d of April the petition in bankruptcy was filed, and a receiver appointed. Shortly after, the receiver presents his petition to this court, praying for an order upon the surety to deliver to the receiver the said property. Thereupon the surety files its answer. From the petition and the answer, upon both of which the cause has been heard, the foregoing facts are found.
We believe the law is with the defendant, and that the petitioner is not •entitled to the possession of the property. While the record does not show that any action had been taken by the highway commissioner of Pennsylvania, yet it does show that the commonwealth of Pennsylvania has paid for the furnishing of the tools and equipment, and that under its contract it is entitled to retain such tools and equipment until the work is completed either by the original contractor and its surety or by some other contractor. This seems clear under the authorities in Duplan Silk Co. v. Spencer, 115 Fed. 689, 53 C. C. A. 321, in Re Shelley, 242 Fed. 251, 155 C. C. A. 91, and from the opinion filed by this court in Re Taylor, at 316 November Term, 1919, in equity. The claimant must rely upon the strength of his own title. It seems, however, that the rights of the commonwealth of Pennsylvania are superior to those of the claimant in this case.
Another view may be taken of tbis question. The claimant urges that the surety has procured a preference because it took possession of the property within four months of the filing of the petition in bankruptcy, and further that, because of the provision of the amendment to the Bankruptcy Law, passed June 25, 1910 (Comp. St. § 9586 et seq.), giving to a trustee the rights, remedies, and powers of a creditor holding a lien by legal or equitable proceedings, that the acquisition of the property in January could not avail the surety as against the trustee. We are satisfied that the law of Pennsylvania recognizes that contracts of pledge of personal property without delivery of
This decision of the Supreme Court of Pennsylvania was in 1912. In 1915 the Supreme Court of the United States had before- it the case of Bailey, Trustee, v. Baker Ice Machine Co., 239 U. S. 268-275, 36 Sup. Ct. 50, 60 L. Ed. 275, a case involving the construction of the amendment aforesaid, and reached the conclusion that a trustee could not assail a contract of conditional sale filed prior to but- within four months of the petition, on the ground that he has the status of a creditor, fastening a lien under the provision of state law, and this for the reason that the trustee acquires the status given to him by that amendment, only from the time of the filing of the petition.
We therefore must conclude that inasmuch as the property in question had passed into the hands of the surety in pursuance of a lawful contract made more than four months prior to the petition, in bankruptcy, by which the surety’s right to the property was fixed; and inasmuch as no creditor prior to that time had attempted to subject the same to levy or other process, and because after the delivery as aforesaid no such creditor could .do so under the law of Pennsylvania, the trustee, having no higher rights than the creditors, could not do so.
Viewed in either aspect, the petitioner is not entitled to have possession of the property, and therefore his petition will be refused.