By a written contract 'dated August 16, 1929, Simon Saliba agreed to build a house for Saia F. Zarthar according to certain plans and specifications for $11,000. An auditor whose findings of fact are final found that “after the written contract had been executed the parties mutually orally agreed that the house should be constructed as Zarthar should direct, that in the absence of specific direction the plans and specifications should govern, that Saliba should be paid the reasonable and fair value of the labor and materials involved in any changes ordered by Zarthar, and that Zar
The provision of the written contract that "no charge for extra work will be honored and paid unless the owner shall order same by a writing directed to the contractor stating the nature of the work to be performed and the sum to be paid therefor” obviously could not prevent oral contracts for extra work, for the parties had power to waive or alter that provision orally at any time. Vitti v. Garabedian,
On the theory that the written contract as orally modified governs the rights of the parties, the auditor found that Saliba is entitled to recover in his action of contract an amount composed of the contract price less a deduction for work included in the contract but not performed (Walsh v. Cornwell,
The trial judge ruled correctly that Saliba could not recover on his first count, which was based on the written contract as orally modified, for the reason that he had not fully performed it. Allen v. Burns,
Zarthar contends that Saliba was guilty of intentional failure to perform the contract as orally modified, and consequently cannot recover under the second count for substantial though inexact performance within the rule of Hayward v. Leonard,
The nearest approach to intentional failure to perform related to the concrete front steps, which Saliba could not readily build during the cold weather, and did not build afterwards because he contended that Zarthar had failed to make payments when due. The auditor found that Zarthar was not in default, but that finding considered only the original contract price, whereas a considerable sum besides was due for extra work which was included in the contract as orally modified. The trial judge was right in drawing the inference from the auditor’s report, which was equivalent to a case stated (G. L. [Ter. Ed.] c. 231, § 126; Merrimac Chemical Co. v. Moore,
Exceptions overruled.
