Zac Smith & Co. v. Moonspinner Condo. Ass'n, Inc.Zac Smith & Co. v. Moonspinner Condo. Ass'n, Inc.
- Reporters:
- ,
- Before:
- Barfield
Bill R. Hutto of Hutto, Nabors & Bodiford, Panama City, for appellee.
BARFIELD, Judge.
Appellants, a construction contractor and its insurer, challenge the trial court‘s award of attorney fees and costs against them in an order confirming an arbitration award in favor of appellee, an association of condominium owners. We reverse the award of costs, affirm the award of attorney fees against Lumbermen‘s Mutual Casualty Company, and remand the case to the trial court for correction of the final judgment to delete the award of attorney fees against Zac Smith & Company, Inc., and for further proceedings on the issue of costs.
Appellee sued appellants and others for construction and design deficiencies in their condominium. Appellants moved to compel arbitration of the claims against them under
On August 14, 1987, a panel of three arbitrators issued an award of $92,650 in favor of appellee and against both appellants. The arbitration award indicated that this amount “includes any interest that may be due,” provided that the arbitrators’
On August 25, appellee moved the trial court to confirm the arbitration award and to assess attorney fees and costs against appellants. The trial court entered an order confirming the arbitration award and awarding appellee fees and costs, reserving jurisdiction to determine the amount of the fees and costs. In December, the trial court entered a $138,124.19 judgment for appellee which included $29,400 in attorney fees and $16,074.19 in costs. Appellants’ motion for rehearing was denied, the order recognized that the award of attorneys’ fees “should be only as against Lumbermens Mutual Casualty Company, and not against Zac Smith & Company.”
COSTS
Appellants assert that the arbitrators, having been informed that appellee sought costs, denied the claim for costs by entering a lump sum arbitration award in full settlement of all the claims presented to it. They contend that the trial court therefore did not have the authority to award costs, citing McDaniel v. Berhalter, 405 So. 2d 1027 (Fla. 4th DCA 1981).
Appellee asserts that the dialogue between its counsel and the arbitrators at the hearing supports the trial court‘s ruling that the costs incurred in the arbitration proceeding were not submitted to arbitration.2 Appellee argues that since the award was in full settlement only of the claims submitted to the arbitration, the trial court was correct in taxing the costs against appellants, and distinguishes McDaniel on the ground that it is unclear in that case whether costs were submitted to arbitration.
Under McDaniel, costs related to an arbitration are to be awarded, if at all, by an arbitration panel and not by a court. The arbitration hearing transcript is ambiguous as to why the arbitration panel did not accept the costs list at the time it was presented by appellee‘s counsel, but we find that the issue of costs was submitted to the arbitration panel. The arbitration award is ambiguous as to whether the arbitrators intended to include the costs in the $92,650 awarded, whether they intended to deny the claim for costs, whether they contemplated that the court would determine the issue, or whether the claim for costs was merely overlooked.
Under the circumstances of this case, and in the interest of justice, we are inclined to treat appellee‘s timely filed motion as one seeking partial vacation of the arbitration award on the ground that appellee was not allowed to present evidence material to the issue of the costs claim. We therefore remand the case to the trial court for further proceedings on this issue, which may include ordering a rehearing under
ATTORNEY FEES
Appellee concedes that attorney fees should have been assessed only against Lumbermens and not against Smith. It argues, however, that
We accept appellee‘s interpretation of
Attorney fees are authorized by
Although both are used to resolve disputes among the parties involved in construction projects, the mechanics lien law and the insurance code provisions concerning performance and payment bonds are “different animals“. The statutes which authorize attorney fees for parties utilizing one or the other of these remedies are also different, both in form and in their precedent conditions. In order to be entitled to an attorney fee under
In contrast, any insured seeking attorney fees under
The trial judge correctly observed that
Appellee‘s award of attorney fees against Lumbermen‘s Mutual Casualty Company is AFFIRMED. The award of costs against both appellants is REVERSED. The case is REMANDED for correction of the final judgment to assess attorney fees against Lumbermens only, and for further proceedings on the costs issue in conformance with this opinion.
JOANOS and WIGGINTON, JJ., concur.