Vernon R. Young, Jr. and Michael D. Rembert, appellants, appeal from a judgment in favor of Richard M. DeGuerin and wife, appellees, awarding them damages for appellants’ breach of a townhouse construction contract pursuant to the Texas Deceptive Trade Practices-Consumer Protection Act, Tex.Bus. & Com.Code Ann. § 1741, (Vernon 1978) et seq. (TDTPA). The trial court found that the cost of remedying the defects and damage to appellee’s townhouse to be at least $15,000.00, trebled; that ap-pellees were entitled to $5,000.00 for mental anguish, not trebled and $5,000.00 for attorney fees. Appellants were awarded $1,992.20 on the counterclaim, not to bе offset against appellees’ recovery. We reform and affirm.
In February 1973, appellees and appellant entered into a contract for the construction of a townhouse. Appellees’ townhouse was one of six to be built by Young for several friends. Each of the friends purchased his own lot and subsequently conveyed the land to Young, as trustee, who then executed mechanic’s and materialmen’s lien contracts with each owner in order to obtain permanent financing. Cost of appellees’ townhouse was approximated to be $44,700.00 with a clause inserted in the contract allowing for necessary cost adjustments upwаrds or downwards. At closing, appellees were confronted with a promissory note reciting an additional $10,180.00 for construction costs. Appellees questioned this and inserted a clause in the note stating it was disputed and subject to negotiations and offset. Appellees then executed the note along with a deed of trust securing its payment. Settlement of the note could not be reached •and appellees refused to pay it. Thereaft *298 er, Rembert, trustee under the deed of trust, attempted to foreclose on the property and appellees instituted this suit for an injunction alleging non-negotiation of the note. The court granted a temporary in-, junction and appellant Young counterclaimed for the amount of the note. Appel-lees then filed an amended pleading alleging breach of an implied warranty of habitability due to defective workmanship in the townhouse and violation of the TDTPA on the part of appellant Young and praying fоr relief as provided in Sec. 17.50(b) of the Act.
In his appeal, appellant states 34 points of error. The record before this court includes the-transcript, statement and facts, and exhibits. Findings of fact and conclusions of law were requested and filed. (Ap-pellees bring a limited appeal from the trial court judgment claiming the damages for mental anguish must be trebled pursuant to the TDTPA).
Appellant Young’s first 12 points of error complain that the trial court erred in holding him personally liable for the improper construction of the townhouse, for failure to negotiate the disputed note, and for failing to correct any defects in the townhouse. Undisputed еvidence revealed that Young was a corporate officer in several construction companies at the time ap-pellees’ townhouse was built. However, the contract Young introduced into evidence, which is the one on which both parties rely, did not disclose any corporate entity or any representative capacity on his part. The contract was executed only by Young and appellees. Appellant confirms his personal liability by his pleadings on which this case went to trial. In his first amended-answer, paragraph II he alleges:
“That VERNON R. YOUNG, JR., and the plaintiff herein closed a building transaction on or about the 16th day of October, 1973, ...”
Again in his original counterclaim in paragraph II he states:
“Counter-Plaintiff would show that he entered into certain building specifications, a copy of which is an agreement with Counter-Defendant to build a two-bedroom two story townhouse for Counter-Defendants in early January or February, 1973, which townhouse was to be built in acсordance with certain building specifications, a copy of which is attached to Plaintiff’s Original Petition as Exhibit “A”. Counter-Plaintiff would further show that he did build or cause to be built said townhouse in accordance with the building specifications.”
Because of such admissions in appellants’ pleading, appellees were not required tо prove such facts, and thus the trial court correctly found appellant personally liable for all of appellees’ damages.
Kelso v. Hawkins,
In points of error 13 through 19, appellant argues that the trial court erred in finding that there were breaches of implied warranties in the construction of the townhouse and that such breaches constituted deceptive trade practices. Appellant also complains of the amount of damages awarded for such breaches.
To negate the existence of an implied warranty in this case, appellant сontends that there was no sale of real estate, but only the sale of construction services and that the sale of services alone would not give rise to any implied warranty. As authority for this contention
Humber v. Morton,
“The implied warranty of fitness arises from the sale and does not spring from the conveyance.”
*299
Cited in the
Humber
case is the case of
Moore v. Werner,
Many of the authorities cited involve personalty, but we see no reason for any distinction between the sale of a new house and the sale of personalty, especially in a.suit between the original parties to the contract, one of whom constructed the house in question. It was the seller’s duty to perform the work in a good and workmanlike manner and to furnish adequаte materials, and failing to do so, we believe the rule of implied warranty of fitness applies, (citations omitted)
In the recent case of
Richman v. Watel,
Appellant argues that since the appellees purchased only construction services from appellant and not goods, chattels, or real estate, no implied warranty arose. The evidence sustains the trial court’s conclusion that the acts of appellant made the basis of apрellees’ suit grew out of “promises to provide services in connection with the sale of real estate.” Actually there was a realty sale in the transaction. Appellees conveyed the land in trust to appellant to secure in the building of the townhouse. Thereafter, appellant conveyed the land with the townhouse thereon to appellees, receiving as payment one promissory note of $43,600 and another of $10,180 and retaining a lien on appellees’ realty on which the townhouse was built. However, we agree with appellees that whether or not real estate is involved in the sale should make no difference since it is the quality of the house which carries the implied warranty. It is sufficient for recovery under the TDTPA that appellees prove the implied warranty of suitability for human habitation and workmanlike construction, the breach thereof and that such breach is the proximate cause of appellees’ damages, Richman v. Watel, suprа. To hold otherwise would deny recovery to a consumer who proved faulty workmanship and materials if he owned his lot and hired a contractor to build it, and would allow recovery under the same fact situation to a consumer who bought his lot and house in a package deal from the contractor.
Appellant next сomplains that there is no competent evidence to sustain the award of damages. Evidence adduced at this trial showed that while the building was structurally sound, but contained numerous defects. The trial court correctly held that the measure of damages for “defects which can be remedied without impairing the building as a whole is thе reasonable cost of the remedying the defects.”
Rogowicz v. Taylor and Gray, Inc.,
In рoint of error 20, appellant complains of the award of damages for mental anguish. Although not prayed for, the trial court awarded $5,000 actual damages for mental anguish over appellant’s objection. The appellees file one point of error complaining of the trial court’s refusal to treble the $5000.
Several appellate cases have been decided holding that the actual damages under the TDTPA are common law damages only.
Cantrell v. First Nat. Bank of Euless,
Appellees cite
Woods
v.
Littleton,
Implied warranty of merchantability in a real estate transaction is not reached, neither is recovery of damages for mental anguish nor numerous other legal issues presented in the appeal.
A review of all authorities cited leads us to the conclusion that there is no provision under Sec. 17.50 of the Act for the recovery of damages for mental anguish. Clearly, the Act makes no mention of mental anguish. We are not inclined to create a new cause of action for tort under the Act and thus invade the legislative province. We hold that the trial court erred in awarding appellees damages for mental anguish.
There exists another ground for not allowing the award of damages for mental anguish to appellees. They have not proved that mental anguish was suffered. The following resume is all the evidence appel-lees offered in support of the award of mental anguish.
Mrs. DeGuerin stated that she was “trapped” in her home with the construe *301 tion workers there; the doors were open all the time; it was not very pleasant; water ruined the upstairs making it look really bad and that it was embarrassing. She further testified that water dripped on her sistеr’s head, and part of the ceiling fell down when her husband hit a light fixture with a broom while their families were visiting. Mrs. DeGuerin also stated that she was breastfeeding her child several times a day and she was forced to retreat to her bedroom and close the door each time to do so, as the house was full of workmen. When her attorney asked her if she were under any stress, she replied “a tremendous amount.”
At best the above summary of events reveals only inconveniences and unpleasantness attendant to any repair work upon occupied premises.
In points of error 21 through 24, appellant complains that the trial court erred in reducing the prоmissory note from $10,180.00 to $1,992.20. The disputed note was signed upon the condition that it would be further negotiated. DeGuerin testified he attempted to talk to Young about it asking for receipts, charges and credits to show he owed the claimed amount.
A list of items was tendered into evidence which appellee stated was the additionаl work he was being charged for. Appellee then proceeded to go through these items and state what should be paid, what was not done, and what he had paid for himself. At the end of his testimony appellee had credits in excess of $7,000. Appellee also stated he expected to pay about $2,000 in additional costs, but not $10,000. The trial court had ample evidence upon which to base its reduction of the note. On appeal there is a presumption that the trial court made such findings as were necessary to support the judgment.
Badeaux v. Cohen,
The reduction in the promissory note would not constitute a double recovery as appellant contends. The note and damages award are separate and distinct. The court found that some of the charges in amount of the note had been paid by appellees and the court reduced the note by this amount. The damages award was based on the testimony of an engineer, appellees and other рarties, as well as various exhibits and photographs offered to show the breach of the implied warranty of habitability and workmanship in the construction of the townhouse.
In points of error 31 and 32, appellant complains of the award of attorney’s fees. The trial court was correct in allowing counsel to reopen his case to prove his attorney’s fees, Rule 270 T.R.C.P.;
Zodiac Corp.
v.
General Elec. Credit Corp.,
We have examined appellants’ other points of error and find them to be without merit. They are overruled.
We reform the judgment of the trial court by denying any recovery for mental anguish and reduce the amount of the recovery by $5000. The remainder of the judgment is affirmed in every respect.
The judgment is reformed and affirmed.