YOUNG RADIATOR COMPANY, Plaintiff-Appellant,
v.
The CELOTEX CORPORATION, Defendant and Third-Party Plaintiff-Appellee,
v.
COOLEY AND BORRE & ASSOCIATES, INC., Korndoerfer
Construction Company, F.J.A. Christiansen Roofing,
Co., Inc., Third-Party Defendants-Appellees.
No. 88-2691.
United States Court of Appeals,
Seventh Circuit.
Argued April 20, 1989.
Decided Aug. 4, 1989.
Ronald F. Wallenfang, argued, Michael J. Dabertin, Angela Johnson Colbert, Quarles & Brady, Milwaukee, Wis., for Young Radiator Co.
John D. Bird, Jr., Churchill, Duback & Smith, Milwaukee, Wis., for Celotex Corp.
Edward A. Hannan, Godfrey, Trump & Hayes, Milwaukee, Wisc., for Cooley and Borre & Associates, Inc.
William W. Ehrke, Prosser, Wiedabach & Quale, Milwaukee, Wis., for F.J.A. Christiansen Roofing Co.
Joseph D. McDevitt, Borgelt, Powell, Peterson & Frauen, Milwaukee, Wis., for Korndoerfer Construction Co.
Before CUDAHY, FLAUM, and KANNE, Circuit Judges.
FLAUM, Circuit Judge.
This is a diversity action involving a leaky roof. Plaintiff Young Radiator Company ("Young") brought suit against the Celotex Corporation ("Celotex"), the manufacturer of the roofing system at issue, alleging negligent manufacture and defective design of the roof, breach of contract, and breach of warranty. The district court granted summary judgment in favor of Celotex, finding that Young's tort claims were time-barred under the applicable Wisconsin statute of limitations and that there had been no breach of contract or warranty. Young appeals the district court's ruling on the tort and contract claims but does not appeal the warranty ruling. For the reasons stated in this opinion, we reverse the grant of summary judgment on the tort claims, affirm the dismissal of the contract claim, and remand for further proceedings.
In addition, this appeal raises a jurisdictional issue under Fed.R.App.P. 4(a)(3). After being sued by Young, Celotex joined as third-party defendants the architect, the general contractor, and the roofing subcontractor, seeking contribution from each. These third-party defendants filed motions for summary judgment based on statute of limitations grounds. The district court, having found Young's tort claims against Celotex to be time-barred, granted summary judgment to the third-party defendants as well. Celotex did not file a notice of appeal from that portion of the judgment dismissing its third-party complaint, and, consequently, the third-party defendants have filed motions in this court seeking to be dismissed from the appeal. They assert that in the absence of a timely Rule 4(a)(3) notice of appeal, we lack competency to exercise appellate jurisdiction to reinstate the third-party action. For the reasons stated herein, we grant the motions to dismiss.
I.
The parties are in agreement as to the following facts. In 1972, Young undertook to construct a new plant at its facilities in Racine, Wisconsin. Cooley & Boore & Associates ("Cooley") served as the architect; Korndoerfer Construction Co., Inc. ("Korndoerfer") was hired as the general contractor; and F.J.A. Christiansen Roofing Co., Inc. ("Christiansen") was the roofing subcontractor. The parties selected for the plant a "Philip Carey" roofing system, manufactured by Celotex.1
Christiansen began construction of the roof in June 1973. During the first two years of construction, various problems occurred, such as leaks and "vapor pockets."2 The architect, general contractor, and roofer met several times to discuss the problems, and Christiansen was instructed to make repairs as needed. In October 1974, Cooley informed Young that the roof was "not acceptable in its present state due to vapor pockets and will be made acceptable by Korndoerfer's subcontractor in the late spring of 1975 as we need heat to detect the vapor pockets."
On July 29, 1975, Christiansen's president, Donald McNamara, inspected the roof and found that there were over a hundred openings in the roof where heating and cooling equipment was to be installed. On that day, McNamara wrote to Mr. Young (president of Young Radiator) and informed him that the equipment had not been inserted and flashed and that water was freely flowing into the building through the openings. He also advised Young that Korndoerfer had ignored Christiansen's quotations for roof flashing,3 curbs, and pitch pans. Mr. Young, upset at learning of these problems from the subcontractor, responded with reprimands to Cooley for failing to properly supervise construction and demands that the project be promptly completed.
The permanent roof flashing and curbing were completed by Carlson Roofing of Racine ("Carlson"), and, after some additional remedial work by Korndoerfer, the roof was accepted by Celotex and Young (through Cooley) on November 5, 1975. With the exception of some minor follow-up flashing and curbing work by Carlson in 1976 (invoiced at $27.56 and $426.40), the construction was essentially completed as of that date. On November 13, 1975, Young Radiator was issued the Philip Carey Inspection and Service Contract which was Celotex's repair service agreement.
In 1978, Carlson repaired minor leaks which were invoiced to Young at $88. In 1979, Carlson made repairs invoiced to Young at $745.00 and $145.00. After receiving the $745.00 bill, Young contacted Celotex about the leaks. By letters dated September 7, 1979, and September 14, 1979, Celotex agreed that the leakage problems were covered by the service contract, informed Young that Carlson would make the necessary repairs at Celotex's expense, and assured Young that the roof would be put "in watertight condition." The repairs were made in the spring of 1980, but the roof continued to leak.
Celotex authorized Carlson to make additional repairs in 1980 and 1981, and by letters dated January 16 and October 21, 1981, continued to assure Young that the roof could and would be made watertight. On November 17, 1981, Celotex informed Young by letter that before the repairs could be completed four additional roof drains were needed and that those installations would be at Young's expense as they were not covered by the service agreement. The letter also offered to provide Young with materials to overlay the roof of Young's separate office building. The letter stated that Celotex "must receive a signed release from claims prior to the shipment of materials." Young never responded to this letter.
From 1980 through July 2, 1984, Young spent more than $11,000 on repairs to the plant roof. Thereafter, in 1984, the entire roof was replaced. Young filed this action against Celotex on January 2, 1986, alleging that the roof was negligently manufactured and defectively designed and that Celotex had breached the service agreement.
II.
Tort Claims/Statute of Limitations
Wisconsin law provides a six-year limitation period for property injury claims. Wis.Stat. Sec. 893.52 (formerly Wis.Stat. Sec. 893.19(5)).4 Both the district court's opinion and the parties' briefs on appeal analyzed the statute of limitations question according to the following standard, first enunciated in Tallmadge v. Skyline Construction, Inc.,
We hold that a cause of action accrues and the statute of limitations (sec. 893.19(5), Stats.) begins to run when the evidence of injury to property, resulting from the negligent act upon which the action is based, is sufficiently significant to alert the injured party to the possibility of a defect. The injury need not, however, be of such magnitude as to identify the causal factor.
Id.
Our independent research revealed, however, that this standard is no longer applicable and has been replaced by the discovery rule announced in Hansen v. A.H. Robins, Inc.,
Prior to the Wisconsin Supreme Court's 1983 decision in Hansen, Wisconsin law held that a cause of action in tort accrued on the date of injury. See, e.g., Boehm v. Wheeler,
Although the court purported that the standard was not a discovery rule but merely a test for identifying an event as an injury,
On appeal, Celotex argues that under the Tallmadge standard the evidence of roof leakage both during construction (1973-75) and during the late 1970's was so great that Young's cause of action must have accrued prior to 1980. Celotex relies on Holy Family Catholic Congregation v. Stubenrauch Associates, Inc.,
We have taken the time to analyze the facts under Tallmadge because discovery of the nature of the injury is a component in the Hansen discovery rule. In Hansen, a personal injury action involving the Dalkon Shield intrauterine device, the Wisconsin Supreme Court overruled the "date of injury" standard and held that "tort claims shall accrue on the date the injury is discovered or with reasonable diligence should be discovered."
[U]nder Wisconsin law, a cause of action will not accrue until the plaintiff discovers, or in the exercise of reasonable diligence should have discovered, not only the fact of injury but also that the injury was probably caused by the defendant's conduct or product.
* * *
* * *
[D]iscovery does not occur until there is information available to the claimant of the nature of her injury, the cause of her injury, and the defendant's part in that cause.
Id.
Finally, we suspect that the discovery rule may have been overlooked because it was thought either that the rule did not apply to property injury claims or that Hansen could not be applied retroactively. If so, we wish to make clear that property as well as personal injury claims are subject to the discovery rule, see Hansen,
III.
Contract Claim
The contract question requires less discussion. Young premised its breach of contract claim on the November 17, 1981, letter, wherein Celotex: (1) conditioned the shipment of materials for the office building roof on Young's release of all claims against Celotex for past, present, and future problems with that roof; and (2) requested Young to install four roof drains on the plant roof before Celotex proceeded with repairs. Young alleged that those two points constituted an anticipatory breach of the service agreement on the plant roof, and asserts on appeal that whether there was a breach is a question of fact for a jury. Young's argument is without merit.
As to the first point, both the letter and the attached "General Release" clearly stated that the release of claims pertained only to the office building roof. The letter is divided into two captioned sections--"A. Plant Roof" and "B. Office Roof." The release of claims is mentioned only in the office roof section and refers only to the shipment of materials for that roof. Lest there be any doubt, the release itself states that Young will hold harmless Celotex for any claims "arising out of, or in connection with ... the roof of the Racine Facility Office Building," specifically, obligations arising under "Roofing Bond No. 22299." The service agreement on the plant roof was Roofing Bond No. PC 4077.
As to the second point, the contract states:
In the event leaks from any cause should occur, owner shall notify Celotex promptly, confirming such notice in writing. Celotex will inspect the roof, and if cause of leak is within the coverage as stated above, Celotex will arrange for repairs to be made at no cost to owner. If cause of leak is not covered, Celotex will not be responsible for cost of any repairs.
The record shows that it was not uncommon for Celotex to determine that certain items were not covered by the service agreement. For example, on September 14, 1979, Celotex informed Young that expansion joint repairs would have to be made at Young's expense. Apparently, Young made those repairs, and Celotex proceeded with the covered repairs. Young did not respond to the November 17, 1981, letter and did not challenge Celotex's determination that roof drains were not covered by the contract. Indeed, it appears from our reading of the contract that installation of additional roof drains would not be covered. In any event, however, Young never claimed that roof drains were covered. Young simply stopped calling Celotex and, four years later, filed a suit for anticipatory breach.
It is well settled under Wisconsin law that "in order to constitute an anticipatory breach of contract (repudiation), there must be a definite and unequivocal manifestation of intention on the part of the repudiator that he will not render the promised performance when the time fixed for it in the contract arrives." Wisconsin Dairy Fresh v. Steel & Tube Products Co.,
IV.
Rule 4(a)(3)
Because we have reversed the dismissal of Young's tort claims, we must determine whether, in the absence of a Rule 4(a)(3) notice of appeal, Celotex may challenge the judgment entered for the third-party defendants. Rule 4(a)(3) gives parties fourteen days within which to file a notice of cross appeal after an initial notice of appeal has been filed. The rule was created to address a problem exemplified in Whitehead v. American Security & Trust Co.,
Despite the holding in Whitehead, that absent a timely notice of appeal the court was without jurisdiction to review the challenged judgment, there has been a longstanding split in authority among the circuits on whether a Rule 4(a)(3) notice of appeal is a jurisdictional requirement or a rule of practice which can, in appropriate cases, be suspended. Authority for the rule of practice position has its source in the grants of jurisdiction found in Article III and 28 U.S.C. Sec. 1291, both of which speak in terms of whole cases. Rule 1(b) underscores the point by providing that "[t]hese rules shall not be construed to extend or limit the jurisdiction of the courts of appeals as established by law." Thus, the rules of appellate procedure do not, in a strict sense, affect the subject matter jurisdiction of the courts of appeals.
However, the rules of appellate procedure have the force of law, 28 U.S.C. Sec. 2072, and Rules 3 and 4 state conditions precedent for the exercise of the appellate jurisdiction granted by Article III and 28 U.S.C. Sec. 1291. Although these conditions precedent are spoken of as "mandatory and jurisdictional," see, e.g., Browder v. Director, Dept. of Corrections of Illinois,
Against this backdrop, several circuits have held that while a timely Rule 4(a)(1) initial notice of appeal is mandatory and jurisdictional, Rule 4(a)(3), which provides additional time for filing cross or other separate appeals, is a rule of practice which can be suspended. Although the reasoning in specific cases varies, the basic rationale is that the initial notice of appeal invokes jurisdiction over the whole case so that the appellate court has the power to overlook the absence of a 4(a)(3) notice and to reverse or otherwise modify a non-appealed judgment or ruling in order to fully adjudicate the appeal before it. The Third, Fourth, Fifth, Eighth, Ninth, and District of Columbia Circuits have followed or recognized this approach. See Scott v. University of Delaware,
On the other hand, the Second, Sixth, Seventh, and Tenth Circuits have, for the most part, adhered to the view that Rule 4(a)(3) is a mandatory, jurisdictional requirement. See Brotherhood of Maintenance of Way Employees v. St. Johnsbury & Lamoille County R.R.,
Last year, the Supreme Court addressed a related issue. In Torres v. Oakland Scavenger Co., --- U.S. ----,
We believe Torres controls the issue in this case. While one could argue that the case dealt only with the specificity requirement as applied to an initial notice of appeal, we find the broad language in Torres to encompass Rule 4(a)(3) as well. Indeed, it could have been argued in Torres that the notice of appeal naming fifteen of the sixteen plaintiffs invoked the jurisdiction of the court over the whole case, so that a separate appeal by the sixteenth plaintiff would not be jurisdictionally required. Yet the Court's holding made clear that the requirements of Rules 3 and 4 must be satisfied as to each party, and precludes the argument in this case that Celotex's noncompliance with Rule 4(a)(3) can be waived.
Finally, we wish to note that while the Torres rule is harsh, even under a rule of practice approach the circumstances in this case would not warrant a waiver of Rule 4(a)(3). This is not a case where the appealing party (Young) is aligned in interest with the non-appealing party (Celotex) so as to justify viewing Young's appeal as being taken on Celotex's behalf. See In re Barnett,
V.
Accordingly, the judgment of the district court is affirmed in part, reversed in part, and remanded for further proceedings consistent with this opinion. The third-party defendants' motions to dismiss are granted.
Notes
The Philip Carey Company is a subdivision of Celotex. The composition (and perhaps complexity) of the roofing system is illustrated by the following excerpt from Christiansen's proposal:
We propose to furnish a roofing system consisting of two one inch layers of Celotherm or Fesco perlite type rigid roof insulation together with a three ply built-up roofing system, in accordance with Philip Carey specification # 300. The first layer of roof insulation will be applied to the deck in ribbons of steep asphalt with mechanical fastening of the outside four foot perimeter. The second layer of insulation will be applied in solid moppings of steep asphalt. We will apply the base sheet and two # 30 organic felts in steep asphalt and flood coat with 60 pounds of dead level asphalt and embed therein gravel at the rate of 400 pounds per square.
A vapor pocket is a blister in which air or other chemical substances are contained
Flashing is sheet metal or other material used to cover and seal joints and angles in a roof, such as where a roof comes in contact with a wall
In its motion for summary judgment, Celotex asserted that the current Sec. 893.52 was the applicable statute. On appeal the parties have agreed that the former statute, Sec. 893.19(5), governs this case. Because the statutes are substantially identical, both prescribing a six-year limitation period, the question is academic. However, we note that whether the current or former statute applies is determined by the date on which the cause of action accrued, not, as the parties believed, the date on which construction was completed. See Wis.Stat. Secs. 990.06, 991.07
The Wisconsin Supreme Court subsequently held this statute to be unconstitutional on equal protection grounds finding that the statute irrationally protected architects and builders but denied protection to owners, occupants, and tenants. Funk v. Wollin Silo & Equipment, Inc.,
At oral-argument, the parties vigorously disputed the role of "cause" under the Tallmadge test. We note the relevant language: "evidence of injury to property, resulting from the negligent act upon which the action is based ... The injury need not, however, be of such magnitude as to identify the causal factor."
In Milwaukee Area Vo. Tech., the plaintiff alleged that the "Cor-Ten weathering steel" used in the construction of the roofs and exterior walls of its buildings became rusted and stained after construction. This court affirmed a summary judgment on statute of limitation grounds, stating that "[i]t does not take a specialist to conclude that, once the problem with the rusting of the CorTen steel was discovered, a significant possibility exists that the problem may be with the steel itself."
Celotex makes an ancillary argument in support of its failure to file a notice of appeal. Celotex asserts that the district court did not dismiss its action against the third-party defendants but merely dismissed its third-party complaint. Relying on Benjamin v. United States,
