111 Mich. 118 | Mich. | 1896
The plaintiff furnished to the defendants a machine called a “sander,” upon defendants’ promise to pay |350 in money and an old sander, which had been in use in their factory. In the action which was brought for the money consideration, the defense is made that plaintiff, as part of the contract, agreed to indemnify the defendants against litigation with another manufacturer, by a letter or bond which should be satisfactory to the defendants. The contract consisted of correspondence. The defendants wrote on June l?th, as follows, viz.:
“But the Berlin Machine Co., of Beloit, Wis., represented by Mr. Forbes, one of their company, informs us that you were infringing on their patents, and that it would only be a question of time before we would be liable, if we bought one of your machines. Now, if you can furnish us with satisfactory letter or bonds that yoü will protect us in any such case, we will give you the order for the sander, and would like to have you ship it as quickly as possible.”
Plaintiff replied as follows, viz.:
“If you can wait about two weeks, we will furnish you machine, and will indemnify you fully against all interference from Berlin Machine Co.”
To this the defendants answered, as follows, viz.:'
“Please rush the sander as quickly as possible, as per our former coi'respondence.”
The judge directed a verdict for the defendants, on the ground that, before the plaintiff could recover, it must prove that the bond was sufficient in amount, and the sureties good; and he did this notwithstanding the fact that counsel for the plaintiff offered to prove such facts, and also to prove other items of account against the defendants.
We are of the opinion that the court erred. If it be conceded that the defendants were entitled to demand a bond as a condition precedent to the acceptance of the machine, it is too late to insist upon such condition after taking and using the machine for several months, and they should be limited to the right to recoup such damages as they have sustained by reason of the failure of the plaintiff to perform that part of the contract. They
“But to permit a party under all circumstances to refuse to pay because dissatisfied, and at the same time to retain the fruits of the agreement, is an unwarrantable extension of the doctrine applied to machines or articles of manufacture which can be rejected. Therefore in all cases, if the party relies upon dissatisfaction as a defense, he must rescind the agreement and restore the status quo.” 1 Beach, Cont. ■§ 106.
Such cases were those cited by counsel for the defendants; i. e., cases where acceptance was refused.
But we do not find it necessary to go to the extent of saying that defendants should be deprived of the benefit, of their contract, as appears to have been held in the case of Campbell Printing-Press Co. v. Thorp, 36 Fed. 414, which was apparently a Michigan contract. It is sufficient to say that the contract has been performed in a substantial part by the plaintiff, and the defendants have accepted and had the benefit of part performance, and they should not be permitted to rely upon the performance of the residue as a condition precedent to liability. Upon this point the author says:
1 ‘ Conditions precedent must be performed in order to make the conditional promise absolute. But, after the one party has performed the contract in a substantial part, and the other party has accepted and had the benefit of the part performance, the latter may thereby be precluded from relying upon the performance of the residue as a condition precedent to his liability. In such case he must perform the contract on his part, and must rely upon his claim for damages in respect of the defective
And see cases cited in note. See, also, Clark, Cont. 676, and note.
The judgment of the circuit court is reversed, and a new trial ordered.
Ellen v. Topp, 6 Exch. 424.