471 F.2d 618 | Ct. Cl. | 1973
Lead Opinion
delivered the opinion of the court:
Plaintiff Young Associates, Inc. contracted in June 1964 with the National Park Service of ¡the Department of the Interior to do some construction work, including lighting and
Young Associates appealed the imposition of liquidated damages to the Department of the Interior Board of Contract Appeals, which affirmed the contracting officer’s determination. I'BCA No. 557-4-66,67-2 BOA ¶ >6676; 69-1 BCA f 7419 (Dec. 1968). This action to review the administrative holding raises purely legal issues; the facts are not now disputed
Plaintiff’s major challenge is that the board erred in ruling that the contract should be construed as containing a liquidated-damages provision (under which the contracting officer thought he was acting). It is agreed that liquidated damages could not be imposed unless authorized by the contract, and it is also common ground that a liquidated-damage provision was not mandatory for this type of contract but was optional at the election of the contracting officer. The basic question is whether such a requirement became part of this undertaking.
The default-termination clause of the contract (article 5 of the 1961 edition of Standard Form 2S-A) provides that the Government can terminate the contractor’s right to proceed if he delays in performance, and also that “[w]hether or not the Contractor’s right to proceed with the work is terminated, he and his sureties shall be liable for any damages to the Government resulting from his refusal or failure to complete the work within the specified time.” This standard-form article then goes on to say:
(b) If fixed and agreed liquidated damages are provided in the contract and if the Government so terminates the Contractor’s right to proceed, the resulting damage will consist of such liquidated damages until such reasonable time as may be required for final com*441 pletion of the work, together with any increased costs occasioned the Government in completing the work.
(c) If fixed and agreed liquidated damages are provided in the contract and if the Government does not so terminate the Contractor’s right to proceed, the resulting damage will consist of such liquidated damages untü the work is completed or accepted.
Invoking subparagraph (c), defendant points to section 8.8 of Standard Specification FP-61
FAILURE TO COMPLETE WORK WITHIN CONTRACT TIME. Pursuant to the general provisions of the contract providing for liquidated damages for each calendar day of delay until the work is completed, the total amount of liquidated damages shall be as calculated from the daily charge given in table 8-1.
In turn, table 8-1 sets forth a graduated scale of “daily charge [s] for liquidated damages for each calendar day of delay”, rising from $30 to $300, depending on the original contract amount. For an agreement of the initial size of plaintiff’s ($312,712.40), the charge was $100 a day. This, says defendant, squarely authorizes the assessment made here.
Plaintiff’s point is that this ehain-of-contract-authority which the Government threads from article 5 (c) to section 8.8 to table 8-1 falls apart when examined closely. Article 5 (c), it is argued, does not itself authorize liquidated damages but is phrased hypothetically — “[¿]/ fixed and agreed liquidated damages are provided in the contract” (emphasis added). The next step in the challenge is that section 8.8 of FP-61 cannot be the contract provision providing for liquidated damages to which article 5(c) refers because, when 8.8 says “pursuant to the general provisions of the contract providing for liquidated damages”, it must be referring to some other part of the agreement, not to itself— and there is no other such provision. The last link in the contractor’s reasoning is that table 8.1 is merely a bare schedule,
This is far from a frivolous argument. In tying the standard construction form with FP-61, the contracting officer failed to bind up the loose ends of language. On one reading, article 6 (c) seems to refer to something in FP-61, and then FP-61 appears to hark back to the standard form — in a sort of contractual renvoi. It would have been much better practice to insert a clause affirmatively and unequivocally declaring that liquidated damages would be imposed for unexcused delay.
Nonetheless we are not persuaded to accept the contractor’s argument. Though they are not as clear as they should have been, the terms of this contract can be reasonably understood as granting authority for the assessment of liquidated damages. As the board observed, article 5(c) does not say, “If a clause directing that liquidated damages shall be imposed is provided in the contract”, but merely, “If fixed and agreed liquidated damages are provided in the contract.” Literally, section 8.8 and table 8-1 of FP-61 do in fact “provide” such “fixed and agreed liquidated damages”, and accordingly the single stated condition to the operability of article 5(c) is precisely fulfilled. The latter provision being thus triggered, under its terms “the resulting damage [from the contractor’s delay] will consist of such liquidated damages until the work is completed or .accepted.” This reading is certainly rational, fitting as it does with the literal language of article '5 (c) and the presence in the contract of both section 8.8 and table 8-1.
'If the contractor had shown that from the 'beginning it understood the agreement otherwise — not to provide at all for liquidated damages — we might well have upheld its position on the ground that such a reading, opposite to the
This being so, we have no choice but to reject plaintiff’s argument. The parties’ joint intent is, of course, dominant if it can be gathered (J. W. Bateson Co. v. United States, 196 Ct. Cl. 531, 542, 450 F. 2d 896, 902 (1971)), and here we have very strong evidence that during performance both sides concurred that the contract incorporated a liquidated-damages clause. See S. S. Silberblatt, Inc. v. United States, 193 Ct. Cl. 269, 278, 433 F. 2d 1314, 1318 (1970); Max Drill, Inc. v. United States, 192 Ct. Cl. 608, 620, 427 F. 2d 1233, 1240 (1970). Nor is it impossible to attach that common intent to the cloudy English of the contract. Though the language by itself is needlessly equivocal, the interpretation made and shared by the parties is reasonable and in literal harmony
Plaintiff’s secondary contention is that, in any event, this hquidated-damages clause is unenforceable as a penalty.
Plaintiff gives us nothing to show that these principles require the clause to be set aside in this instance. The Government’s damages stemming from delayed receipt of the supplies or construction it ordered are normally hard to measure, and it is usually reasonable to establish some fixed monetary substitute for calculation by trial. As the Department of Agriculture Board of Contract Appeals recently put it in Ford Constr. Co., AGBCA No. 241, 72-1 BCA ¶ 9275 at 42,980, liquidated-damages clauses in favor of the Government in road construction cases are ordinarily “intended to cover additional administrative and engineering expenses incurred by the Government when performance of the contract extended over a greater time than was originally contemplated, the loss to the Government of the use of the
Citing the liquidated damages policy section of the Federal Procurement Regulations, 41 C.F.R. § 1-1.315-2 (c) (1912),
The plaintiff is not entitled to recover. Its motion for summary judgment is denied, the defendant’s motion is granted, and the petition is dismissed.
In particular, there is no claim before the court th.at the unexcused delay was less than 144 days.
“The Standard Specifications for Construction of Roads and Bridges in Federal Highway Projects,” promulgated by the Commerce Department in 1961.
Plaintiff gives as an example this provision of a District of Columbia Government form contract:
“Liquidated damages will be imposed for each calendar day or major portion thereof that any wort shall remain uncompleted after time specified for completion and in the amount as set forth in the table below.”
We by-pass, without deciding, defendant’s point that plaintiff may not challenge the validity and enforceability of the liquidated-damages provisions for the first time in this court. (Plaintiff did not present this issue to the board.) It is not clear to what extent the boards of contract appeals are empowered to hold contract clauses invalid, and since we need not reach that somewhat difficult issue we let it rest where it is.
“Tie rate of liquidated damages stipulated must be reasonable in relation to anticipated damages, considered on a case-ly-case Itasis^ since liquidated damages fixed -without any reasonable reference to- probable damages may be held to be not compensation for anticipated damages caused by delay, but a penalty and therefore unenforceable” (emphasis added).
Dissenting Opinion
dissenting:
Because I believe that the subject contract cannot reasonably be construed as containing a liquidated damages provision, I am unable to agree with the decision of the court.
No statute or regulation imposed a liquidated damages provision on the plaintiff’s contract. Rather the applicable provision of the Federal Procurement Regulations, 41 C.F.R.
It is perhaps significant that in 1968 (well after the instant dispute arose) the Federal Procurement Regulations were amended
§ 1-18.110 Liquidated damages.
(a) A liquidated damages clause may, in the discretion of the contracting officer, be included in construction contracts. See § 1-1.315. Where such a provision is used, the invitation for bids or request for proposals shall include a clause reading substantially as follows:
Liquidated Damages
In case of failure on the part of the Contractor to complete the work within the time fixed in the contract or any extensions thereof, the Contractor shall pay to the Government as fixed, agreed and liquidated damages, pursuant to the clause of this contract entitled “Termination for Default-Damages for Delay-Time Extensions”, the sum of $— for each calendar day of delay.
One probable reason for the amendment was a recognition on the part of contracting officials that specific, positive language is required in contracts like the one before us to render applicable the hypothetical standard form provisions pertaining to liquidated damages.
For the reasons stated above, I do not think the subject contract can reasonably be construed as containing a liquidated damages clause. The contract is simply devoid of sufficient declaratory language to constitute such a provision.
That being so, I cannot accord the dispositive effect which the majority gives to the letters submitted by the plaintiff
A liquidated damages provision is necessarily a harsh contractual remedy, because it permits the Government to recover specified amomits upon an unexcused delay by the contractor without assuming the burden of establishing the actual amount of its loss, if any. Certainly the parties to a Government contract may agree, by appropriate language, to make such a provision a part of their bargain. The court should be reluctant, however, to imply such a clause in a contract when there is a lack of affirmative language to constitute a liquidated damages provision. Since I am persuaded that neither the contractual language nor the actions of the
All this does not mean that the defendant is without a remedy. Plaintiff no longer contends that the delays complained of were excusable. The Government should be entitled to establish, in further proceedings, the actual damages, if any, resulting from plaintiff’s delay of 144 days in completing performance of the contract. Therefore, I would grant plaintiff’s motion for summary judgment on the liquidated damages issue and hold that plaintiff is entitled to remission of the liquidated damages assessed ($14,400), subject to the right of the Government to set off against that sum the amount of actual damages sustained by the Government as established by it in further proceedings before our trial commissioner.
Plaintiff cites illustrative language taken from a District of Columbia standard form construction contract:
“Liquidated damages will be imposed for each calendar day or major fraction thereof that any work shall remain uncompleted after the time specified for completion, and in the amount as set forth in the table below. * * *”
Table 8.1 of FP-61 adds nothing; it merely states the daily amounts of liquidated damages to be charged, If applicable.
This Is particularly true considering that FP-61 Is a voluminous document providing standard specifications for a wide variety of federal highway projects, most of which are not applicable to plaintiff’s relatively limited tunnel-work project.
33 Fed. Reg. 14288, 14289 (1968).
E.g.,Max Drill, Inc. v. United States, 192 Ct. Cl. 608, 620, 427 F. 2d 1233, 1240 (1970) and other cases cited by the majority.