HITOSHI YOSHIKAWA v. CITY AND COUNTY OF HONOLULU; TROY K. SEGUIRANT, Individually; GREG TALBOYS; AGT CONSTRUCTION, LLC; & JAMES A. SCHMIT
CIVIL NO. 18-00162 JAO-RT
IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF HAWAII
May 27, 2021
Case 1:18-cv-00162-JAO-RT Document 228
ORDER GRANTING IN PART AND DENYING IN PART (1) DEFENDANT CITY AND COUNTY OF HONOLULU‘S MOTION TO DISMISS PLAINTIFF‘S THIRD AMENDED COMPLAINT, AND (2) DEFENDANT TROY K. SEGUIRANT‘S MOTION TO DISMISS PLAINTIFF‘S THIRD AMENDED COMPLAINT
As explained in a prior order, this case concerns Plaintiff Hitoshi Yoshikawa‘s (“Plaintiff“) attempt to rebuild his house in Kaneohe, Hawaiʻi and the regulatory challenges he faced in doing so. In his Third Amended Complaint (“TAC“), ECF No. 204, Plaintiff alleges that the City and County of Honolulu (the “City“) and one of its building inspectors, Defendant Troy K. Seguirant (“Seguirant“), violated Plaintiff‘s civil rights through their enforcement of various municipal laws, which frustrated
I. BACKGROUND
A. Facts1
Plaintiff, a Japanese national, resides in the City and County of Honolulu and owns waterfront real property located in Kaneohe (the “Property“). ECF No. 204 ¶¶ 8-9, 23. At the time Plaintiff purchased the Property in 2014, it contained a “nonconforming structure” within the shoreline setback. See ECF No. 204 ¶¶ 23, 31-32;
1. The Permit and Inspections
In November 2014, Schmit submitted a building permit application for an “Addition and Alteration to existing Single Family Dwelling,” which required approval from various sources, including the Building and Zoning divisions within the City‘s Department of Planning and Permitting (“DPP“). Id. ¶¶ 37, 39.
Following extensive review and “[i]terative feedback” between Schmit and DPP officials, Schmit revised the plans and ultimately obtained a building permit from DPP in October 2015. Id. ¶¶ 42-49. After obtaining the building permit, Plaintiff began substantial work on the addition and alteration project (the “Project“), beginning with demolition work in areas outside the shoreline setback in November 2015. Id. ¶¶ 50-51.
Seguirant inspected the Project at least nine times between December 2015 and May 4, 2016, which, according to Plaintiff‘s contractors, was unusually frequent as building inspectors might visit comparable projects only two or three times. Id. ¶¶ 52, 54, 57. Seguirant did not raise any issues or concerns relating to the scope or execution of the Project to Plaintiff, any of Plaintiff‘s contractors and subcontractors, or Schmit during any of these inspections. Id. ¶ 54. Plaintiff‘s contractors noticed Seguirant “approach and converse cordially with the next-door neighbor” on multiple occasions. Id. ¶ 55. Plaintiff alleges that Seguirant owns and operates a construction business while working as a building inspector for the City, which Plaintiff alleges is a conflict of interest given Seguirant‘s role as a City building inspector. Id. ¶¶ 13, 217.a.
2. The May 6, 2016 Unappealable Notice of Violation
On May 6, 2016, Seguirant issued a Notice of Violation and Stop Work Order on the Project (the “May 2016 NOV“). Id. ¶ 58. The May 2016 NOV informed Plaintiff that a “new building permit is required for the removal of the walls of the existing non-conforming structure and the construction of the new walls within the shoreline setback area” and cited Plaintiff for the “reconstruction of the existing nonconforming structure within the shoreline
After receiving the May 2016 NOV, Plaintiff stopped work on the Project and requested an appeal or hearing regarding the May 2016 NOV; and Plaintiff‘s representatives, including Schmit and Talboys, tried to convince various DPP officials to rescind the May 2016 NOV in various written communications and in-person meetings. Id. ¶¶ 64-69. In response to Plaintiff‘s request for an appeal, DPP‘s then-Acting Director George Atta informed Plaintiff that his request was premature, as Notices of Violation are not appealable; only Notices of Order are. Id. ¶ 71. Plaintiff then continued to exchange information and revised plans with DPP officials, including its Director and Deputy Director. Id. ¶ 73.
3. The Challacombe Letter
In October 2016, then-Acting DPP Director Art Challacombe issued a written letter indicating that a revised proposal Schmit had sent him was consistent with ordinances regarding nonconforming structures in the shoreline setback area (the “Challacombe Letter“). Id. ¶ 74. The Challacombe Letter explained that the revised proposal did not “increase the nonconformity and is less than 50 percent of the replacement cost of the nonconforming structure,” and so complied with the City‘s ordinances regarding construction work within the shoreline setback area. Id. The Challacombe Letter further authorized Plaintiff to submit a building permit based on the revised plans. Id. Following receipt of the Challacombe Letter, Plaintiff expended substantial resources and time to revise the Project‘s plans and submitted revised plans in December 2016. Id. ¶¶ 76-77.
4. The March 14, 2017 Appealable Notice of Order
On February 2, 2017, while working in Plaintiff‘s yard, Plaintiff‘s contractors overheard Seguirant tell the next-door neighbor, ““I keep shutting them down but f--- [expletive] these Haoles2 don‘t listen, that‘s why I try keep it local.“” Id. ¶¶ 79-81.
On March 14, 2017, Seguirant issued a Notice of Order (the “March 2017 NOO“) regarding the May 2016 NOV, which Plaintiff alleges contradicted the Challacombe Letter. Id. ¶ 82. The March 2017 NOO stated that the “existing non-conforming structure within the shoreline setback area was reconstructed, which is not in accordance with the approved building permit” and that “a new building permit is required for removing the walls of the existing non-conforming structure and constructing new walls within the shoreline setback area.” ECF No. 204-10 at 1. Plaintiff believed that the Challacombe Letter voided the May 2016 NOV. ECF No. 204 ¶ 83. Plaintiff initiated an appeal of the
5. The Amended Building Permit
Despite the issuance of the March 2017 NOO, on March 29, 2017, DPP issued an amended building permit (the “Amended Building Permit“) for the Project that was consistent with the Challacombe Letter. Id. ¶ 84. Various DPP officials further verbally assured Plaintiff‘s representatives that the Project could proceed, so Plaintiff recommenced work on the Project. See id. ¶ 86.
6. The April 7, 2017 Unappealable Notice of Violation
On April 7, 2017, Seguirant issued a further Notice of Violation and Stop Work Order (the “April 2017 NOV“). Id. ¶ 88. The April 2017 NOV “concern[ed] the same alleged issues pertaining to the Project‘s scope of work in the setback,” but in fact covered additional violations as well. Id.; ECF No. 204-12. The April 2017 NOV stated that the information supplied to obtain the Amended Building Permit was inaccurate in violation of
7. The BBA Hearing and Order
On November 3, 2017, the BBA held a hearing on Plaintiff‘s appeal of the March 2017 NOO, attended by Seguirant and his supervisor. Id. ¶¶ 87, 99. The BBA ruled on Plaintiff‘s appeal in its Findings of Fact, Conclusions of Law, and Decision and Order (“the BBA Order“), which was issued sometime in 2018.3 See id. ¶¶ 103-04. While Plaintiff describes the BBA Order in vague terms and declined to attach it to the TAC despite attaching numerous other documents, it is apparent from the face of the TAC that Plaintiff did not prevail before the BBA. See id. ¶¶ 138-41 (alleging that Plaintiff‘s inability to appeal the BBA Order deprived Plaintiff of his vested rights under the Amended Building Permit).
Plaintiff alleges that five months after the hearing he still had not received the BBA Order, but learned through discovery that it was sent to outdated addresses for Schmit and Plaintiff‘s prior counsel. Id. ¶¶ 101, 103-06. Plaintiff alleges that it was the City‘s fault that the BBA Order was mailed to the wrong addresses, as Schmit‘s mailing was returned as undeliverable and Plaintiff‘s prior counsel had repeatedly notified DPP of his new address through his pleadings. Id. ¶¶ 105, 106, 133, 135. Plaintiff further alleges that the Stop Work Order contained in the April 2017 NOV is effectively non-appealable because it was not followed by a Notice of Order. Id. ¶ 102.
The BBA found that “Seguirant issued the [May 2016] NOV based on his observations
Plaintiff did not appeal the BBA Order to the state circuit court within the thirty-day appeal period outlined in
B. Procedural History
Plaintiff commenced this action on May 3, 2018 and filed the TAC on February 5, 2021, asserting the following claims: Count One –
The City and Seguirant each filed motions to dismiss on February 19, 2021. ECF Nos. 205 (the City‘s Motion), 206 (Seguirant‘s Motion). Plaintiff filed his oppositions to both motions on March 19, 2021.9 ECF Nos. 217, 218. The City Defendants filed their reply memoranda on March 25, 2021. ECF Nos. 220, 221. Oral argument was presented at a motions hearing on April 23, 2021. ECF No. 225.
II. LEGAL STANDARD
“To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.‘” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). Facial plausibility exists “when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Id. (citing Twombly, 550 U.S. at 556). The tenet that the court must accept as true all the allegations contained in the complaint does not apply to legal conclusions. See id. As such, “[t]hreadbare recitals of the elements of a cause of action, supported by mere conclusory statements, do not suffice.” Id. (citing Twombly, 550 U.S. at 555). “[W]here the well-pleaded facts do not permit the court to infer more than the mere possibility of misconduct, the complaint has alleged—but it has not ‘show[n]‘—‘that the pleader is entitled to relief.‘” Id. at 679 (quoting
III. DISCUSSION
A. 42 U.S.C. § 1981 (Count One)
Plaintiff alleges that the City and Seguirant violated
Section 1981 was “meant, by its broad terms, to proscribe discrimination in the making or enforcement of contracts against, or in favor of, any race.” Gratz v. Bollinger, 539 U.S. 244, 276 n.23 (2003) (internal quotation marks and citation omitted). “‘Race’ is interpreted broadly to mean classes of persons identifiable because of their ancestry or ethnic characteristics.” Gathenji v. Autozoners, LLC, 703 F. Supp. 2d 1017, 1029 (E.D. Cal. 2010) (quoting Saint Francis Coll. v. Al-Khazraji, 481 U.S. 604, 612-13 (1987)). The Supreme Court has explained that Section 1981 is “intended to protect from discrimination identifiable classes of persons who are subjected to intentional discrimination solely because of their ancestry or ethnic characteristics.” Saint Francis Coll., 481 U.S. at 613. In order to state a claim under Section 1981, it is essential that the plaintiff “initially identify an impaired contractual relationship . . . under which the plaintiff has rights.” Domino‘s Pizza, Inc. v. McDonald, 546 U.S. 470, 476 (2006) (internal quotation marks, citation, and footnote omitted).
Because Section 1981 claims typically arise in employment discrimination cases, the Court must evaluate such claims using the first three elements of the McDonnell Douglas10 test used in Title VII discrimination cases even though the claims here do not involve an employment relationship. See Lindsey v. SLT L.A., LLC, 447 F.3d 1138, 1145 (9th Cir. 2006). Accordingly, Plaintiff must plead that he (1) is a member of a protected class, (2) attempted to contract for certain services, and (3) was denied the right to contract for those services. See id.
In Lindsey, the Ninth Circuit explained that there was a circuit split as to whether a fourth element applies to Section 1981 claims that arise outside the employment context, which “requires that . . . services remained available to similarly-situated individuals who were not members of the plaintiff‘s protected class,” but declined to decide the issue. Id. Following Lindsey, the majority of courts within the Ninth Circuit apply this fourth element. See York v. JPMorgan Chase Bank, Nat‘l Ass‘n, No. CV-18-04039-PHX-SPL, 2019 WL 3802535, at *2 n.4 (D. Ariz. Aug. 13, 2019) (explaining that “the greater weight of Ninth Circuit authority” supports the use of the fourth element (collecting cases)).
Nonetheless, the Court is persuaded by the court‘s reasoning in Makhzoomi v. Southwest Airlines Co., 419 F. Supp. 3d 1136 (N.D. Cal. 2019), in which an Iraqi plaintiff alleged that an airline removed him from a flight for speaking Arabic in violation of Section 1981 after another passenger reported to airline employees that she heard him express, while he spoke on a cell phone, what she perceived to be threatening statements. See id. at 1147. The court declined to apply the fourth element, explaining that “in the context of the denial of services by a commercial establishment, ‘the task of producing similarly situated persons outside the protected group is much more difficult,’ given the itinerant nature of the clientele.” Id. at 1149 (citation omitted). The court explained that requiring the plaintiff to compare his treatment with the treatment of other “passengers who were reported to have been overheard on the airplane making potentially threatening comments” was an “overly narrow comparison [that] would completely foreclose [the plaintiff]‘s discrimination claim,” which reveals the drawbacks of the fourth element in cases arising outside of the employment context. Id. (internal quotation marks and citation omitted). Instead, the court followed Christian v. Wal-Mart Stores, Inc., 252 F.3d 862 (6th Cir. 2001), in clarifying the third element as follows:
“(3) plaintiff was denied the right to enter into or enjoy the benefits or privileges of the contractual relationship in
that (a) plaintiff was deprived of services while similarly situated persons outside the protected class were not and/or (b) plaintiff received services in a markedly hostile manner and in a manner which a reasonable person would find objectively discriminatory.”
Makhzoomi, 419 F. Supp. 3d 1136 (quoting Christian, 252 F.3d at 872).
The facts here are analogous to Makhzoomi. Just as the Makhzoomi court found it unreasonable to require the plaintiff to compare his treatment with a group passengers that did not appear to exist, forcing Plaintiff to compare his treatment with Seguirant‘s treatment of other homeowners who were engaged in construction in violation of municipal ordinances would be “overly narrow” as Plaintiff is not well positioned to be aware of Seguirant‘s conduct each time he inspects a non-compliant project (each of which may vary in the nature of their non-compliance). Id. at 1149.11
In contrast, the Ninth Circuit held in Lindsey that there was a genuine issue of material fact as to the fourth element — whether the plaintiff, a company that presents fashion shows largely staffed and attended by African-Americans, was provided inadequate accommodations for contracted expectations such as a room for up to 550 guests, when it was denied the use of a hotel‘s grand ballroom, while a bar mitzvah party was granted use of the grand ballroom despite having a smaller number of attendees. See Lindsey, 447 F.3d at 1142-43, 1147. Unlike the plaintiff in Lindsey, Plaintiff was not in a position to identify Seguirant‘s treatment of those similarly situated to him.
1. Prima Facie Section 1981 Claim against Seguirant
While the bulk of Count One focuses on Plaintiff‘s constitutional claims (some of which are repeated in Count Two), the Court concludes that the TAC contains sufficient factual allegations to state a Section 1981 claim against Seguirant. Plaintiff alleges that he contracted with a general contractor and architect, both of whom are “Haole,” and that Seguirant interfered with Plaintiff‘s right to contract with them due to racial animus against “Haoles.” See ECF No. 204 ¶¶ 120-27. The Court disagrees with Seguirant that Plaintiff failed to plausibly allege how Seguirant impaired Plaintiff‘s contractual rights. ECF No. 206-1 at 11-12. While Count One is certainly disorganized, the Court understands Plaintiff‘s argument to be that Seguirant, motived by racial animus, tried to prevent the Project from proceeding by engaging in multiple inspections and issuing multiple violations. Plaintiff has further pleaded allegations that satisfy the relaxed standard in Christian that Makhzoomi adopted: Plaintiff received hostile treatment that a reasonable person would find objectively discriminatory when Seguirant made the “Haoles” comment referenced in the TAC. See Makhzoomi, 419 F. Supp. 3d at 1149; ECF No. 204 ¶ 81.
Further, Plaintiff may maintain a Section 1981 claim against Seguirant even if Seguirant was discriminating only against Plaintiff‘s “Haole” contractor and architect, and not Plaintiff, a Japanese national. See McDonald v. Santa Fe Trail Transp. Co., 427 U.S. 273, 286-87 (1976) (“[Section] 1981 is applicable
2. Qualified Immunity
Seguirant argues that he is entitled to qualified immunity on Plaintiff‘s Section 1981 claim because of a circuit split as to whether Section 1981 provides a remedy against government officials and because whether to apply the fourth element described in Lindsey is not settled law within the Ninth Circuit. ECF No. 206-1 at 9-10. Qualified immunity protects government officials from suit in their individual capacity so long as “their conduct does not violate clearly established statutory or constitutional rights of which a reasonable person would have known.” Harlow v. Fitzgerald, 457 U.S. 800, 818 (1982) (citations and footnote omitted).
The existence of a circuit split regarding the viability of a claim does not entitle a government official to qualified immunity where the claim is recognized in the circuit in which the action is maintained. See Boyd v. Benton County, 374 F.3d 773, 781 (9th Cir. 2004) (“If the right is clearly established by decisional authority of the Supreme Court or this Circuit, our inquiry should come to an end.“). Thus, the fact that other circuits may not recognize a claim under Section 1981 against government officials does not entitle Seguirant to qualified immunity.
Moreover, Plaintiff‘s Section 1981 claim against Seguirant may proceed even though Lindsey left open the question as to whether the fourth element of McDonnell Douglas applies outside the employment context. Indeed, “[t]he constitutional right to be free from such invidious discrimination [racial or ethnic animus] is so well established and so essential to the preservation of our constitutional order that all public officials must be charged with knowledge of it.” Williams v. Alhambra Sch. Dist. No. 68, 234 F. Supp. 3d 971, 978-79 (D. Ariz. 2017) (quoting Flores v. Pierce, 617 F.2d 1386, 1392 (9th Cir. 1980)).
3. But-for Causation
Seguirant argues that Plaintiff‘s Section 1981 claim fails because Plaintiff did not allege but-for causation, and that Plaintiff would be unable to allege but-for causation without impeaching the BBA Order, which affirmed the violations Seguirant issued. ECF No. 206-1 at 10-11. The Supreme Court recently ruled that a Section 1981 plaintiff must prove but-for causation by showing that “but for the defendant‘s unlawful conduct, [the plaintiff‘s] alleged injury would not have occurred.” Comcast Corp. v. Nat‘l Ass‘n of Afr. Am.-Owned Media, 140 S. Ct. 1009, 1014 (2020).
The Court disagrees with Seguirant that the BBA Order prevents Plaintiff from establishing causation. It may be the case that the Project violated the City‘s ordinances and that Seguirant discriminated against Plaintiff in enforcing those ordinances because of racial animus. Thus, taking all the allegations in the TAC as true, it is possible that Seguirant would not have enforced the City‘s ordinances in the precise manner that he did if Plaintiff‘s contractor and architect were of a different race.
4. Municipal Custom or Policy
The City argues that Plaintiff‘s Section 1981 claim against the City fails because Plaintiff failed to allege that Plaintiff suffered a Section 1981 violation because of a municipal custom or policy. ECF No. 205-1 at 8-9. For the City to
be liable under
Plaintiff argues that the TAC contains sufficient allegations regarding a municipal policy or custom because he alleged that the City failed to implement non-discrimination or cultural sensitivity training and failed to implement a proper conflict of interest policy or conflict-check for its building inspectors. ECF No. 217 at 9. In other words, Plaintiff‘s theory is not that the City had a custom or policy of discriminating against “Haoles,” but that Seguirant was able to engage in such discrimination because the City failed to train him properly.
“To impose liability on a municipal employer for failure to adequately train its employees, a plaintiff must prove that the government‘s omission amounted to ‘deliberate indifference’ to the right at issue[.]” Raines v. Seattle Sch. Dist. No. 1, No. C09-203 TSZ, 2013 WL 221630, at *2 (W.D. Wash. Jan. 18, 2013) (citing Clouthier v. County of Contra Costa, 591 F.3d 1232, 1249 (9th Cir. 2010)). In Clouthier, the Ninth Circuit explained that this standard is satisfied “[o]nly where a failure to train reflects a deliberate or conscious choice by a municipality” in order to avoid “diluting the requirement that a local government can be held liable only for an action or inaction that amounts to an official policy[.]” Clouthier, 591 F.3d at 1250 (quoting City of Canton v. Harris, 489 U.S. 378, 389 (1989)) (internal quotation marks omitted). Even if the City failed to provide Seguirant with non-discrimination or diversity training, nothing in the TAC indicates that the City evinced “deliberate indifference” toward racial discrimination. Furthermore, nothing in the TAC suggests that such training would have prevented Seguirant from engaging in discrimination. See Lee v. City of Los Angeles, 250 F.3d 668, 681 (9th Cir. 2001) (“[T]he identified deficiency in a local governmental entity‘s training program must be closely related to the ultimate injury.” (internal quotation marks, brackets, and citation omitted)).
The Court also rejects Plaintiff‘s argument regarding the conflict of interest policy because there is no apparent connection between the City‘s lack of a conflict of interest policy, which may have prevented Seguirant from inspecting homes in the same market that he services as a general contractor, and Seguirant‘s racial animus against “Haoles.”
Because the Court concludes that Plaintiff failed to allege that his right to make and enforce contracts under
Regarding Plaintiff‘s
B. 42 U.S.C. § 1983 : Procedural Due Process (Counts One and Two)
In Counts One and Two, Plaintiff alleges that the City Defendants are each liable under
“To obtain relief on a procedural due process claim, the plaintiff must establish the existence of ‘(1) a liberty or property interest protected by the Constitution; (2) a deprivation of the interest by the government; [and] (3) lack of process.‘” Shanks v. Dressel, 540 F.3d 1082, 1090 (9th Cir. 2008) (alterations in original) (citation omitted). At its core, procedural due process requires notice and an opportunity to be heard. See Mathews v. Eldridge, 424 U.S. 319, 333 (1976).
1. Deprivation of a Property Interest Protected by the Constitution
The City argues that Plaintiff cannot state a procedural due process claim because Plaintiff failed to allege a liberty or property interest protected by the Constitution, arguing that there is no constitutional right to build a home in violation of municipal law and that the BBA‘s conclusion that the Project did indeed violate such law is subject to issue preclusion. ECF No. 205-1 at 11-13.
Plaintiff, however, does not argue that the outcome of the BBA proceeding, namely the BBA‘s conclusion that the Project could not proceed without modification, was a due process violation; instead, Plaintiff alleges that the process itself was procedurally defective. If the Court were to accept the City‘s argument that Plaintiff‘s failure on the merits before the BBA doomed any procedural due process claim, that would mean that the government need not ensure due process so long as it is correct on the merits, which offends basic notions of due process.13
The Ninth Circuit has in the context of a substantive due process claim “recognized a constitutionally ‘protected property interest’ in a landowner‘s right
Plaintiff alleged that “Plaintiff‘s normal avenue to challenge DPP‘s adverse decision was to present an appeal to the BBA, followed by an agency appeal to the state circuit court.” ECF No. 204 ¶ 168. Thus, at least at this stage of the proceeding, the Court concludes that Plaintiff‘s right to appellate review before the BBA was a “significant substantive restriction” on DPP‘s ability to enforce the City‘s ordinances by preventing landowners from proceeding with construction. Plaintiff had a constitutionally protected property interest when he appeared before the BBA to challenge the March 2017 NOO and was ultimately deprived of this interest when the BBA affirmed the order. Even if this deprivation was proper, Plaintiff was nonetheless entitled to due process.
2. Lack of Process
As explained above, Plaintiff argues that there was a lack of process when the BBA failed to issue the BBA Order within a reasonable amount of time and when it transmitted the BBA Order to the wrong address. ECF No. 217 at 14-15.
Plaintiff alleges that the BBA‘s proceedings were subject to the Hawai‘i Administrative Procedure Act, which in turn required that the BBA render its decision within a reasonable amount of time. ECF No. 204 ¶¶ 167, 170. Plaintiff relies on
For purposes of this section, “application for a business or development-related permit, license, or approval” means any state or county application, petition, permit, license, certificate, or any other form of a request for approval required by law to be obtained prior to the formation, operation, or expansion of a commercial or industrial enterprise, or for any permit, license, certificate, or any form of approval required under sections 46-4, 46-4.2, 46-4.5, 46-5, and chapters 183C, 205, 205A, 340A, 340B, 340E, 340F, 342B, 342C, 342D, 342E, 342F, 342G, 342H, 342I, 342J, 342L, and 342P.14
Plaintiff also alleges, however, that Plaintiff‘s prior counsel notified the BBA of a change in address several times; that the BBA Order was transmitted to Schmit‘s prior address and was returned as undeliverable; that he was unable to commence an agency appeal of the BBA Order because he did not receive notice of the BBA Order within the 30-day appeal window; and that the City is therefore at fault for Plaintiff‘s inability to commence an agency appeal. ECF No. 204 ¶¶ 154-63. The Court concludes that Plaintiff sufficiently alleged a lack of process by including factual allegations showing that the City made errors relating to the transmittal of the BBA Order that prevented Plaintiff from commencing an agency appeal relating to the BBA Order.
The City argues that there was no lack of process because there is no constitutional right to an appeal, relying on Jones v. Barnes, 463 U.S. 745 (1983), and because Plaintiff received ample process before the BBA. ECF No. 205-1 at 13. In Jones, the Court ruled that although states must provide counsel for indigent criminal defendants where appeals may be made as a matter of right despite the lack of a constitutional right to appeal, counsel for such defendants have no duty to raise every colorable claim suggested by their clients. See Jones, 463 U.S. at 750-51, 754. The Court is not convinced that Jones or the lack of a constitutional right to an appeal forecloses Plaintiff‘s procedural due process claim. Plaintiff does not argue that he was denied due process because there was no procedure for appellate review. Rather, Plaintiff contends that he was denied the right to commence an agency appeal that was available under
The City argues that Plaintiff was not denied a lack of process because he still could have filed an untimely agency appeal and relied on the doctrine of equitable estoppel or changed course with respect to the Project in order to proceed in a manner allowed by DPP. ECF No. 205-1 at 14-16. While Plaintiff may certainly have had these options, Plaintiff nonetheless could not commence a timely agency appeal, which he was entitled by statute to do. The availability of alternative courses of action do not obviate the fact that Plaintiff has sufficiently alleged that he received a lack of process.
Finally, the City argues that Plaintiff‘s procedural due process claim fails because Plaintiff failed to allege a cognizable injury that resulted from the lack of process. Id. at 14. The Court disagrees. Plaintiff has alleged that he was unable to commence an agency appeal because of the City‘s failure to transmit the BBA Order to the correct address. Even if an agency appeal would not have changed the ultimate outcome, a denial of procedural due process “can lead to the award of nominal damages, even where substantive injury cannot be proved.” Weinberg v. Whatcom County, 241 F.3d 746, 752 (9th Cir. 2001). The availability of nominal damages means that Plaintiff need not prove actual damages in order to have a viable procedural due process claim. See id.
The Court therefore concludes that the TAC adequately states a procedural due process claim against the City.
3. Plaintiff‘s Procedural Due Process Claim against Seguirant
Despite the fact that Plaintiff‘s procedural due process claim relates to the BBA‘s handling of the BBA Order, Plaintiff
The Court concludes that amendment of Plaintiff‘s procedural due process claim against Seguirant would be futile in light of Plaintiff‘s failure to state a claim against Seguirant despite previous opportunities to amend his complaint. See Chodos, 292 F.3d at 1003.
The Court therefore DENIES the City‘s Motion with respect to the procedural due process claims in Counts One and Two of the TAC and DISMISSES WITH PREJUDICE those same claims as to Seguirant.
C. 42 U.S.C. § 1983 : Equal Protection (Counts One and Two)
In Counts One and Two of the TAC, Plaintiff asserts that the City Defendants are liable under
“The Equal Protection Clause of the
Plaintiff argues that his allegation that Seguirant inspected the Project nine times, as opposed to the two-to-three times that a building inspector would inspect a comparable project, shows that Plaintiff was treated differently than similarly situated individuals. See ECF No. 218 at 19. Seguirant argues that the owners of similar residential construction projects are not similarly situated to Plaintiff because Plaintiff was constructing the Project in
Courts within the Ninth Circuit have “enforce[d] the similarly-situated requirement with particular strictness when the plaintiff invokes the class-of-one theory.” Leen v. Thomas, No. 2:12-cv-01627-TLN-DMC, 2020 WL 1433143, at *6 (E.D. Cal. Mar. 24, 2020) (quoting Warkentine v. Soria, 152 F. Supp. 3d 1269, 1294 (E.D. Cal. 2016)) (brackets in original) (other citations omitted). “Class-of-one plaintiffs must show an extremely high degree of similarity between themselves and the persons to whom they compare themselves.” Id. (quoting Warkentine, 152 F. Supp. 3d at 1294); see also Hood Canal Sand & Gravel, LLC v. Brady, 129 F. Supp. 3d 1118, 1125 (W.D. Wash. 2015) (“[Class of one plaintiffs] must demonstrate that they were treated differently than someone who is prima facie identical in all relevant respects.” (quoting Purze v. Village of Winthrop Harbor, 286 F.3d 452, 455 (7th Cir. 2002)) (brackets in original)).
The Court ruled in its January 6 Order that the doctrine of issue preclusion requires that it give preclusive effect to the BBA Order, which determined that the Project violated municipal law. ECF No. 179 at 44. Plaintiff must therefore compare his treatment with, at a minimum, other property owners who have engaged in construction that violates municipal law. In order for Plaintiff to state an equal protection claim, then, Plaintiff is required to show that Seguirant treated Plaintiff differently than property owners committing similar building code violations, not property owners constructing similar projects who are not breaking the law. Plaintiff has thus failed to allege that he was treated intentionally differently than similarly situated individuals as the TAC fails to identify any similarly situated individuals and/or articulate how Seguirant treated Plaintiff differently from those individuals.
Because of its conclusion that Plaintiff has failed to allege that he was treated intentionally differently than those similarly situated, the Court need not reach the issues of whether Seguirant had a rational basis for treating Plaintiff differently or whether the City has municipal liability for Seguirant‘s equal protection violation. The Court further concludes that amendment would be futile in light of Plaintiff‘s previous opportunities to amend his complaint. See Chodos, 292 F.3d at 1003. The Court therefore DISMISSES WITH PREJUDICE Plaintiff‘s equal protection claim against both defendants in Counts One and Two of the TAC.
D. 42 U.S.C. § 1983 : Claim for Ratification or Approval (Count Two)
In Count Two of the TAC, Plaintiff alleges that the City is liable under
“[A] municipality cannot be held liable solely because it employs a tortfeasor—or, in other words, a municipality cannot be held liable under
The Court dismissed Plaintiff‘s ratification or approval claim in its January 6 Order because Plaintiff failed to allege facts showing that the DPP Director ratified an unconstitutional act and the basis for it. ECF No. 179 at 28. Here, Plaintiff posits that Seguirant‘s April 2017 NOV was the unconstitutional act. But Plaintiff again fails to allege that the DPP ratified the alleged unconstitutional basis for this act, i.e., Seguirant‘s discriminatory motives. See ECF No. 204 ¶¶ 189-90. Just as was the case in the SAC, nothing in the TAC suggests that the DPP Director was aware of any statements Seguirant made, any biases Seguirant harbored, or that Seguirant maintained his own contracting business while working as a building inspector for the City. Instead, Plaintiff alleges that “ratification can . . . be inferred by the long procedural history of the dispute which was known or should have been known by the DPP Director.” ECF No. 204 ¶ 189. The DPP‘s awareness of the dispute does not mean the DPP Director knew, let alone ratified, the basis for Seguirant‘s actions. Thus, even if Seguirant‘s April 2017 NOV was a constitutional violation, Plaintiff has failed to allege facts showing that the City is liable for such violation under a theory of ratification or approval.
Despite being granted leave to amend to plead facts showing that the DPP Director ratified Seguirant‘s unconstitutional acts and the basis for such acts, Plaintiff has failed to do so. ECF No. 179 at 28. The Court therefore concludes that further leave to amend would be futile. See Chodos, 292 F.3d at 1003. Accordingly, Plaintiff‘s ratification or approval claim in Count Two is DISMISSED WITH PREJUDICE.
E. 42 U.S.C. § 1983 : Fourteenth Amendment Violations for Policy of Inaction or Delay (Count Two)
In Count Two of the TAC, Plaintiff alleges that the City is liable for its policy of inaction or delay that amounted to a failure to protect Plaintiff‘s constitutional rights. Specifically, Plaintiff alleges that the City‘s failure to set a defined time frame for the BBA to render decisions violates
Under Oviatt, the elements of a municipal liability claim under
Plaintiff failed to plead the Oviatt elements sufficiently. Even assuming arguendo that the City‘s failure to establish a timeframe for the BBA to issue orders amounts to a policy under Oviatt, Plaintiff failed to establish facts showing that the policy constitutes deliberate indifference. In order to properly plead deliberate indifference, Plaintiff must offer facts showing that “the need for more or different action ‘is so obvious, and the inadequacy [of the current procedure] so likely to result in the violation of constitutional rights, that the policymakers . . . can reasonably be said to have been deliberately indifferent to the need.‘” Oviatt, 954 F.2d at 1477-78 (alterations in original) (citation omitted). Although the TAC alleges that the City‘s failure to set a time frame for the BBA to issue orders “amounts to deliberate indifference,” ECF No. 204 ¶¶ 199-201, Plaintiff has not alleged any facts showing that the BBA‘s failure to establish a deadline for issuing orders prior to the BBA‘s handling of Plaintiff‘s appeal was likely to result in the violation of constitutional rights such that the City was deliberately indifferent to the violation of constitutional rights. See Bd. of Cty. Comm‘rs v. Brown, 520 U.S. 397, 410 (1997) (“[D]eliberate indifference’ is a stringent standard of fault, requiring proof that a municipal actor disregarded a known or obvious consequence of his action.“).
In light of these conclusions, the Court need not reach the remainder of Defendant‘s arguments relating to Plaintiff‘s inaction or delay claim. The Court dismissed Plaintiff‘s inaction or delay claim against the City in its January 6 Order due to Plaintiff‘s failure to plead deliberate indifference. ECF No. 179 at 29-30. The Court therefore concludes that further leave to amend would be futile. See Chodos, 292 F.3d at 1003. As such, Plaintiff‘s claim for inaction or delay in Count Two is DISMISSED WITH PREJUDICE.
F. Negligence/Negligent Retention and Negligent Hiring and/or Supervision (Count Four)
In Count Four of the TAC, Plaintiff appears to assert what he considers to be three separate state law claims against the City: negligence/negligent retention, negligent hiring, and negligent supervision. Plaintiff, however, disclosed at the parties’ Local Rule 7.8 conference that he is not pursuing a negligent hiring claim and included it in the TAC inadvertently, leaving only the negligence/negligent retention claim and the negligent supervision claim. ECF No. 209 at 2. Plaintiff‘s negligent hiring claim is therefore DISMISSED WITH PREJUDICE.
1. Negligence/Negligent Retention
Plaintiff alleges that the City is liable for negligence and negligent retention because it retained Seguirant as an employee after learning of his tortious conduct, specifically his discriminatory conduct toward Plaintiff and his maintenance of a contracting business while working as a building inspector. ECF No. 204 ¶ 208. “It is well-established that, in order for a plaintiff to prevail on a negligence claim, the plaintiff is required to prove all four of the necessary elements of negligence: (1) duty; (2) breach of duty; (3) causation; and
The Court dismissed Plaintiff‘s negligent retention claim in its January 6 Order on the basis that the City‘s retention of Seguirant could not have been the proximate cause of Plaintiff‘s injuries if Seguirant had already caused those injuries when the City received notice of the Seguirant‘s wrongful conduct. ECF No. 179 at 33-34. Plaintiff again has failed to plausibly allege that the City‘s negligent retention of Seguirant was the proximate cause of Plaintiff‘s injuries insofar as Plaintiff did not allege that the City knew or should have known that Seguirant had engaged in wrongful conduct before Seguirant caused injury to Plaintiff. ECF No. 205-1 at 24.
The Court has previously given Plaintiff leave to amend in order to allege that the City had knowledge of Seguirant‘s wrongful conduct at the time Seguirant injured Plaintiff. ECF No. 179 at 33-34. As Plaintiff has failed to do so, the Court concludes further leave to amend would be futile. See Chodos, 292 F.3d at 1003. Plaintiff‘s negligence/negligent retention claim in Count Four is therefore DISMISSED WITH PREJUDICE.
2. Negligent Supervision
Plaintiff alleges that the City engaged in negligent supervision by allowing Seguirant to maintain his general contracting business while working as a building inspector and by providing Seguirant with little to no training as a building inspector, enabling Seguirant to discriminate against Plaintiff. ECF No. 204 ¶ 217(a-b). The Hawai‘i Supreme Court analyzes negligent supervision claims using the standards set forth in the Restatement (Second) of Torts § 317. See Dairy Rd. Partners v. Island Ins. Co., 92 Hawai‘i 398, 426-27, 992 P.2d 93, 121-22 (2000). Section 317 states:
A master is under a duty to exercise reasonable care so to control his servant while acting outside the scope of his employment as to prevent him from intentionally harming others or from so conducting himself as to create an unreasonable risk of bodily harm to them, if
(a) the servant
(i) is upon the premises in possession of the master or upon which the servant is privileged to enter only as his servant, or
(ii) is using a chattel of the master, and
(b) the master
(i) knows or has reason to know that he has the ability to control his servant, and
(ii) knows or should know of the necessity and opportunity for exercising such control.
Restatement (Second) of Torts § 317 (Am. L. Inst. 1965) (current through 2020 Supp.) (emphasis added). Thus, there can only be a negligent supervision claim arising out of an employee‘s misconduct when the employee‘s misconduct occurred outside the scope of his or her employment. See Black v. Correa, CV. No. 07-00299 DAE-LEK, 2007 WL 3195122, at *10 (D. Haw. Oct. 30, 2007) (“[N]egligent supervision may be found only when the employee acts outside the scope of his or her employment.” (citing Pulawa v. GTE Hawaiian Tel, 112 Hawai‘i 3, 143 P.3d 1205 (2006); Dairy Road Partners, 92 Hawai‘i 398, 992 P.2d 93 (2000))); Carroll v. County of Maui, Civil No. 13-00066 DKW-KSC, 2015 WL 1470732, at *10 (D. Haw. Mar. 31, 2015) (“To state a claim for negligent supervision or failure to control under Hawai‘i law, a plaintiff must allege that the employees who committed the wrongful acts were acting outside the scope of their employment.” (citation omitted)).
The Court ruled in its January 6 Order that Plaintiff‘s negligent supervision claim is defective because Plaintiff believes he was injured by Seguirant‘s efforts to enforce the City‘s ordinances in relation to the Property, which constitute acts Seguirant took within the scope of his employment. ECF No. 179 at 35. Plaintiff has not included any allegations regarding tortious conduct that Seguirant engaged in outside the scope of his employment. See generally ECF No. 204. Plaintiff‘s negligent supervision claim therefore remains defective.
Despite the Court‘s prior ruling, Plaintiff cites Ryder for the proposition that “Hawaii law recognizes two types of claims alleging negligent supervision: one that seeks relief from acts occurring outside the scope of employment, and one that seeks relief from acts that happened in the scope of employment.” ECF No. 217 at 21 (quoting Ryder, 2016 WL 2745809, at *10). In support of this proposition, Ryder cites to Black v. Correa, 2007 WL 3195122, at *10-11, which explains that in situations where an employee-supervisor negligently supervises other employees, the employer can be held liable for the employee-supervisor‘s acts within the scope of employment based on respondeat superior liability. See Ryder, 2016 WL 2745809, at *10.
But regardless of whether recovery under such a respondeat superior theory is a second “type” of negligent supervision claim as termed in Ryder, it is clear that Seguirant is not a supervisor as Plaintiff alleges that Seguirant is a building inspector and makes no references to any employees under Seguirant‘s supervision. Thus, as the Court held in the January 6 Order, Seguirant must have committed a tortious act outside the scope of his employment in order for Plaintiff to have a negligent supervision claim against the City. ECF No. 179 at 34-35.
The Court previously granted Plaintiff leave to amend in order to allege tortious conduct that Seguirant engaged in outside the scope of his employment. ECF No. 179 at 34-35. Because Plaintiff has not done so, the Court concludes further leave to amend would be futile. See Chodos, 292 F.3d at 1003. Plaintiff‘s negligent supervision claim in Count Four is therefore DISMISSED WITH PREJUDICE.
IV. CONCLUSION
For the reasons set forth above, The City‘s Motion [ECF No. 205] is GRANTED IN PART AND DENIED IN PART as follows: (1) the Motion is denied with respect to the procedural due process claim against the City in Counts One and Two; and (2) the
Seguirant‘s Motion [ECF No. 206] is GRANTED IN PART AND DENIED IN PART as follows: (1) the Motion is DENIED with respect to the
IT IS SO ORDERED.
DATED: Honolulu, Hawai‘i, May 27, 2021.
Jill A. Otake
United States District Judge
Civil No. 18-00162 JAO-RT, Yoshikawa v. City and County of Honolulu, ORDER GRANTING IN PART AND DENYING IN PART (1) DEFENDANT CITY AND COUNTY OF HONOLULU‘S MOTION TO DISMISS PLAINTIFF‘S THIRD AMENDED COMPLAINT, AND (2) DEFENDANT TROY K. SEGUIRANT‘S MOTION TO DISMISS PLAINTIFF‘S THIRD AMENDED COMPLAINT
