278 Pa. 351 | Pa. | 1924
Opinion by
The York Manufacturing Company, plaintiff, brought this suit against the Chelten Ice Manufacturing Company, defendant, to recover $29,700, with interest, on six promissory notes given by defendant to plaintiff on divers days from April 24 to June 20, 1919, inclusive. Defendant interposed a counterclaim for a much larger sum and the trial resulted in a general verdict in its favor; from judgment entered thereon plaintiff brought this appeal.
The parties are corporations, plaintiff being located at York and defendant at Philadelphia, and, in April, 1915, plaintiff by written contract undertook to construct and equip for defendant a plant for the making of ice, which was to be completed on or about June 23d of that year. The contract says, inter alia: “The York Manufacturing Company guarantees that the above freezing system (Can System Nos. 1 and 2) under test will have an ice-making capacity of 75 tons of ice per day of 24 hours with the water entering the cans at 40° or less, when properly and continuously operated.” Plaintiff also therein guaranteed the workmanship and material for one year. The contract further stipulates that, “If for a period of thirty days after the machinery, apparatus or plant, furnished hereunder, is erected ready to charge,
During the years 1915 and 1916 certain disputes arose between the parties with reference to the plant, its operation, etc., to adjust which the parties, in September, 1916, entered into a new written contract, reciting that, “Whereas the party of the first part [the plaintiff] furnished and installed the said machinery and apparatus, but not within the time prescribed therefor, and the said machinery and apparatus has not come up to the requirements of the contract in all respects, and the responsibility for said failures as well as for divers other controversies is in dispute between the parties hereto,” and stipulating, inter alia, that, “The party of the first part agrees, during the coming fall, winter and spring, to make such repairs, changes and additions to the said machinery and apparatus as may be necessary and proper to make the said machinery and apparatus
Assuming, as we must, the truth of defendant’s evidence and all favorable inferences deducible therefrom (Mitchell v. City of New Castle, 275 Pa. 426), the case
Assuming, but not deciding, that the above-mentioned thirty-day clause of the old contract remained in force under the new contract, it cannot be held as matter of law that defendant was thereby precluded from interposing the counterclaim in question, for, as above stated, when told the machine was ready for use, it gave prompt written notice of certain defects. Furthermore, plaintiff made extensive repairs and alterations to the machinery, etc., at its own expense, from time to time until August, 1919, and thereby justified a finding that it had waived any claim of full performance prior to that date. In this respect the case differs from those cited on its behalf. Plaintiff urges that it made such changes and repairs because of its interest in the plant, as creditor and stockholder, but no such claim was made while the work was in progress, and that was at most a matter for the jury. Defendant never expressly accepted the plant, and, under the facts above stated, it cannot be held as matter of law that there was an implied acceptance. Hence, plaintiff’s request for binding instructions was properly refused.
It was competent for defendant to show what possession plaintiff had of the plant and the work it did thereon down to August, 1919, also that the machine was generally out of repair and failed to produce the guaranteed amount of ice. Such proof tended to support the counterclaim and could not be excluded. The assignment of error (No. 1) relating to its admission embraces seventy-four printed pages of testimony, including that of two witnesses, also certain correspondence and- numerous
Early in 1919 plaintiff placed a Mr. Keyser in charge of the work of making changes and repairs to the plant in question, and declarations made by him, in connection with this work, were properly admitted in evidence on part of defendant. In the language of Judge Shakswood, in Penna. Railroad v. Books, 57 Pa. 339, 343: “The rule is well settled, that what an agent says while acting within the scope of his authority, is admissible against the principal, as part of the res gestee, but not statements or representations made by him at any other time.” To like import are Matteson v. N. Y. Cent., etc., R. R. Co., 218 Pa. 527; Baker v. Gas Co., 157 Pa. 593; Oil City Fuel Supply Co. v. Boundy, 122 Pa. 449; Roth-well v. California Boro., 21 Pa. Superior Ct. 234; Mellick v. R. R. Co., 17 Pa. Superior Ct. 13 (reversed on other grounds in 203 Pa. 457) ; Henry’s Trial Evidence, sec. 76. Moreover, the declarations of the witness in the instant ease were as to the plant and did not involve the making or waiving of any contract.
Defendant still has the machinery placed upon its premises, hence, if entitled to damages, the proper measure thereof is the difference between the value of the machinery as contracted for and as actually furnished (Otis Elevator Co. v. Flanders Realty Co., 244 Pa. 186; Mack v. Slateman, 21 Fed. 109), and the trial judge so held.
Plaintiff’s six requests were properly refused, as each calls for binding instructions.
The rule, that one who gives a renewal note with knowledge of the failure of consideration for the original waives such defense, cannot be applied here, for when the notes in suit were given, plaintiff had machinists work
The assignments of error are overruled and the judgment is affirmed.