7 N.W.2d 314 | Minn. | 1942
The complaint, so far as here material, alleged in substance that the parties made an oral contract by the terms of which plaintiff undertook to dig a well on defendant's farm and defendant promised to pay him for such work "after the completion of said job" at the rate of $1.65 per lineal foot and to furnish board and lodging to plaintiff and his crew while the work was being done; that plaintiff performed the contract by drilling a well 204 feet deep; and that he was entitled to recover the contract price, which defendant had not paid, and to a mechanic's lien for the amount of the recovery and foreclosure of the lien.
The answer admitted the contract and further alleged that the parties agreed that a 4-inch casing should be sunk; that plaintiff agreed that the well should furnish a sufficient supply of usable water; and that plaintiff should not be entitled to any pay until after the well was completed and was producing sufficient usable water.
Although no reply is necessary in actions to foreclose mechanic's liens (see Minn. St. 1941, §
While the pleadings allege that the contract was to "sink" a well, it is apparent from the methods employed and the testimony as a whole that the parties meant that the well should be drilled or bored.
At the trial plaintiff did not stand on the allegations in his pleadings, but claimed that when the well had been drilled to a depth of 204 feet the contract was modified so as to substitute 2 1/2-inch for 4-inch casing. It is not clear whether he also claimed that the contract did not bind him to drill a well that would produce an adequate supply of usable water.
We have examined the evidence with painstaking care. The testimony of defendant and his witnesses, of whom there were four, all related to him, supports the view that the contract was as claimed by him. Plaintiff's testimony and admissions in the pleadings and briefs amply support defendant's claims. In effect there was no substantial conflict that the contract as originally made was as defendant claims it was.
The real conflict was whether the contract was modified as claimed by plaintiff. Plaintiff's evidence is that when the well had been drilled to a depth of 204 feet the contract was modified so as to permit him to use 2 1/2-inch instead of 4-inch casing. As stated above, it is not clear from his testimony whether he also claimed that by the modification he was relieved from the requirement that the well should produce a sufficient supply of usable water.
Defendant's testimony, which is supported by that of his witnesses, was explicit that there was no agreement to modify the contract as originally made; that when plaintiff had sunk the well to a depth of 204 feet plaintiff obtained one Cichy to assist with the work, using the latter's equipment; that Cichy brought along some 2 1/2-inch casing; that plaintiff procured some casing of the same size; that, when plaintiff commenced to use the 2 1/2-inch *388 casing to drill the well below the 204 feet to which it was already bored with 4-inch casing, defendant protested and informed him that he would not pay for the well unless 4-inch casing were used; that plaintiff claimed that he had a legal right to reduce the size of the casing from 4 inches to 2 1/2 inches; that acting under such claim of right plaintiff continued to use the 2 1/2-inch casing; that meanwhile defendant consulted a lawyer, who advised him that he would not have to pay unless the contract was performed according to its terms; that by that time plaintiff had sunk the well to a depth of 283 feet, using 2 1/2-inch casing the last 79 feet; that he advised plaintiff that he had consulted counsel and of his insistence that 4-inch casing be used throughout and that he would not pay unless it was used; that some argument between the parties ensued; and that thereupon plaintiff discontinued the work, pulled up the 2 1/2-inch casing sunk by him, and removed his equipment from defendant's premises. The 204 feet of 4-inch casing was allowed to remain in the ground. There was no evidence that the casing which remained in the ground was of any benefit to defendant. It produced no water. It was not shown that it could be used for that purpose, and the inference is that it could not.
Below, plaintiff claimed the right to recover upon the ground that he performed the contract as originally made until it was modified, and that after the modification he performed it as modified until defendant's insistence on performance according to the terms of the contract as originally made and his warning not to pay if 2 1/2-inch instead of 4-inch casing were used below the depth of 204 feet, which plaintiff claims amounted to a wrongful interference by defendant, making further performance impossible.
The court below found that the contract was as claimed by defendant; that, although plaintiff asked defendant to modify the contract in the respects claimed, defendant refused to consent to the modification; that plaintiff had not performed the contract; and that thereafter plaintiff ceased work and removed his equipment from defendant's premises. The court concluded that plaintiff *389 was entitled to no relief, and judgment was entered accordingly. Plaintiff appeals.
On the appeal, while asserting the claims made below, plaintiff has shifted his ground somewhat by claiming that when he had drilled the well to a depth of 145 to 150 feet he considered abandoning the job, but continued to perform upon the advice of defendant's son, who told him that there was nothing else for him to do. This he contends amounts to an abandonment of the contract and the making of a new contract to continue with the work on a quantum meruit basis.
1. The contract was entire, because by its terms it was to be performed as a whole and the compensation for performance was to be paid as a whole. Uldrickson v. Samdahl,
2. The agreement that plaintiff should not be paid until after the well had been bored and was producing the stipulated quantity of usable water made plaintiff's performance, according to the terms of the contract, a condition precedent to any right to compensation. Gilloley v. Sampson,
3. The duty under a contract is full and complete performance. In the case of building and construction contracts, the rule has been generally adopted that such duty is satisfied by substantial *390
performance. It is not necessary to decide whether the reason for the rule is that the rules requiring exact and literal performance of contracts is relaxed in the case of such contracts (Hoglund v. Sortedahl,
We do not deem it necessary to define substantial performance at this time. For present purposes, it is sufficient to say that substantial performance means performance of all the essentials necessary to the full accomplishment of the purposes for which the thing contracted for has been constructed, except for some slight and unintentional defects which can be readily remedied or for which an allowance covering the cost of remedying the same can be made from the contract price. Deviations or lack of performance which are either intentional or so material that the owner does not get substantially that for which he bargained are not permissible. Elliott v. Caldwell,
Contrary to plaintiff's contention, the rules applicable to building and construction contracts apply to those for drilling or boring wells. Where a contractor by express stipulation agrees that he will dig, drill, or bore a well which will produce a certain quantity and quality of water, he cannot recover until he has not only dug, drilled, or bored the well, but also until it produces water of the quantity and quality stipulated in the contract. Blackburn v. Texarkana G. E. Co.
A stipulation in a contract to dig or bore a well using a casing of a certain size, being a legitimate matter of agreement, the contractor has no right to use a smaller size casing than that provided for in the contract. Gosson v. Witt,
4. In considering the appeal, we must take the facts as found by the court below. Where the evidence is in conflict, the terms of a contract and the question whether there was substantial performance of it are fact questions. Service
Security, Inc. v. St. Paul F. S. L. Assn.
In that view, it necessarily follows that plaintiff's notion that he had the right, after he drilled the well to a depth of 204 feet, to substitute 2 1/2-inch for 4-inch casing was entirely erroneous; that the substitution of 2 1/2-inch for 4-inch casing constituted an intentional violation of the contract; and that plaintiff failed to perform the contract because he failed to bore a well that would produce the quantity and quality of water for which the contract called. For failure to perform, plaintiff was not entitled to recover *393
under the contract. Elliott v. Caldwell,
5. Nor can there be a recovery upon a quantum meruit for part performance. The basis of such recovery is that the defendant has received a benefit from plaintiff which it is unjust for him to retain without paying for it. It was not shown that plaintiff's part performance was a benefit to defendant. He removed the 79 feet of 2 1/2-inch casing, So far as appears, the 204 feet of 4-inch casing still in the ground is useless. No water, much less water of usable quality, can be drawn through it. Benefits aside, it was not unjust for defendant to retain the work and materials performed and furnished without paying for them. Where a building and construction contract is entire and the contractor voluntarily and without excuse abandons it after part performance, he has no claim, equitable or otherwise, to any compensation whatever. Elliott v. Caldwell,
"The acceptance of the benefit of a partial performance, or of performance in a way different from that contracted for, where the party has the option of returning or rejecting the consideration performed, will usually be sufficient to imply a promise to pay a compensation commensurate with the benefit accepted. But the mere fact that a part-performance has been beneficial is not enough to render the party benefited liable to pay for the advantage. It must appear that he has taken the benefit under circumstances sufficient to raise an implied promise to pay for the work done, notwithstanding the non-performance of the special contract. Therefore, in a case of a building on land under a contract which *394 the builder fails to complete, or which he completes in a manner not conforming to the contract, so that the owner cannot be charged with the contract price, the mere fact of the building remaining on the land, and that the owner resumed possession and enjoys the fruits of the labor, is not such an acceptance as alone will imply a promise to pay for it; for the possession of the land necessarily involves possession of the buildings in their existing state, and the owner has no option of rejecting them."
6. The fact that defendant's son told plaintiff when the latter considered abandoning the contract that there was no alternative for him but to complete performance, so far from abandoning the contract and thereby authorizing performance on a quantum meruit basis, amounted only to advice that he was bound by his contract to perform it. See King v. D. M. N. Ry. Co.
Some other points have been raised, but they are so clearly without merit that we refrain from discussing them.
Our conclusion is that there should be an affirmance.
Affirmed. *395