Dr. John W. YARBRO, surviving spouse of decedent, Geraldine Yarbro, Petitioner-Appellant, v. HILTON HOTELS CORPORATION, Defendant and Third-Party Plaintiff, v. I.M. PEI, individually, and I.M. Pei & Partners, a partnership, formerly known as I.M. Pei and Associates, Third-Party Defendants-Appellees.
No. 80SA274.
Supreme Court of Colorado, En Banc.
Dec. 13, 1982.
Rehearing Denied Jan. 10, 1983.
655 P.2d 822
Ellison, Ward & McCrea, Margaret Bates Ellison, Bruce B. McCrea, Denver, for third-party defendants-appellees.
LEE, Justice.
This is an appeal from a summary judgment entered in favor of the third-party defendants, I.M. Pei and I.M. Pei & Partners (Pei). We affirm the judgment.
The appellant, Dr. John W. Yarbro (plaintiff), brought an action against the Hilton Hotels Corporation (Hilton) for the wrongful death of his wife, Dr. Geraldine Yarbro. The plaintiff‘s claim arose out of events occurring on May 17, 1977, while the Yarbros, who both were oncologists, were attending a medical convention at the Denver
The plaintiff sought to recover damages in the amount of $4,000,000, alleging that his wife‘s death was caused by her losing her balance or tripping over a radiator located at the base of the window, and falling through the window of the room. The windows were 78.25 inches tall and 21.5 inches wide, with a 1/4 inch pane of glass set in pre-cast concrete mullions. There were no guards, screens, or other protective devices attached to the window. The radiator protruded 15 inches into the room, and the bed was placed close to the window, leaving little room to walk between the two. The plaintiff claimed that his wife‘s foot or leg came in contact with the radiator so as to cause her to lose her balance and fall into the windowpane, which could not withstand the impact.
Hilton impleaded I.M. Pei and I.M. Pei & Partners, professional architects who had provided design services for the building prior to its completion in 1960. Plaintiff then filed a complaint against Pei, alleging that the death was a result of the “negligently designed room configuration, the inadequate thickness of the glass installed therein, and the lack of adequate safeguards.” Pei responded with a motion for summary judgment raising as a defense
The plaintiff asserts that
The principal question for our review is whether the statute granting immunity from suit to architects ten years following substantial completion of the building is constitutional. We note that the statute is presumed to be constitutional and the plaintiff bears the burden of proving
I.
The appellant first argues that this statute denies due process since it does not rationally further any legitimate state objective. See, e.g., Williamson v. Lee Optical of Okla., Inc., 348 U.S. 483, 75 S.Ct. 461, 99 L.Ed. 563 (1955). We do not agree. Limiting liability of an architect, and others similarly situated, by a reasonable means may indeed serve a public purpose. We agree with the statement of the Supreme Court of New Jersey speaking in Rosenberg v. Town of North Bergen, 61 N.J. 190, 293 A.2d 662 (1972), as follows:
“There comes a time when [the defendant] ought to be secure in his reasonable expectation that the slate has been wiped clean of ancient obligations, and he ought not to be called on to resist a claim when ‘evidence has been lost, memories have faded, and witnesses have disappeared.‘”
61 N.J. at 201, 293 A.2d at 667-668 (1972) quoting Developments in the Law: Statutes of Limitations, 63 Harv.L.Rev. 1177, 1185 (1950). This court has previously upheld similar statutes of repose such as
“The general rule is that a statute of limitations ... does not violate due process ‘unless the time fixed by the statute is manifestly so limited as to amount to a denial of justice .... The legislature is the primary judge of whether the time allowed ... is reasonable.’ Oberst v. Mays, 148 Colo. 285, 292, 365 P.2d 902, 905 (1961).” (citations omitted).
Similarly, a majority of the states have acted to create time limits on suits against architects for design problems.3 Such statutes of repose differ from other statutes of limitation since they may bar a cause of action before it accrues. The legislative judgment is that construction or design defects are likely to be discovered within a reasonable period after substantial completion of the building.4 Thus, after that time,
We hold that it was not unreasonable for the General Assembly to limit to ten years the period in which suits may be commenced against architects for design defects, in view of the legislative intent to avoid stale claims and the likelihood that most types of defects would reasonably be discovered within ten years of substantial completion. See Smith v. Allen-Bradley Co., 371 F.Supp. 698 (W.D.Va.1974). Since the statute is rationally related to a permissible state objective, it does not violate due process.
This statute was enacted in 1969, nine years after the substantial completion of construction and the issuance of the certificate of occupancy in 1960 in this case. Geraldine Yarbro died in 1977, eight years after the statute came into effect, and seventeen years after the substantial completion of the Hilton Hotel. The alleged design defect was not discovered until 1977, and by that time the architect had become statutorily immune from suit.5 The plaintiff had no claim and thus no vested right to sue at the time the immunity became effective and he therefore cannot assert that his property was taken without due process. Freezer Storage, Inc. v. Armstrong Cork Co., 234 Pa.Super. 441, 341 A.2d 184 (1975), aff‘d 476 Pa. 270, 382 A.2d 715 (1978); Joseph v. Burns, 260 Or. 493, 491 P.2d 203 (1971).
As stated in Joseph v. Burns, supra, 260 Or. at 503, 491 P.2d at 207-208:
“Assuming that the effect of [the statute] is to abolish causes of action in tort where the damage does not result within ten years after the negligent acts or omissions complained of, we see nothing unconstitutional in so doing....
“It has always been considered a proper function of legislatures to limit the availability of causes of action by the use of statutes of limitation so long as it is done for the purpose of protecting a recognized public interest. It is in the interest of the public that there be a definite end to the possibility of future litigation resulting from past actions. It is a permissible constitutional legislative function to balance the possibility of outlawing legitimate claims against the public need that at some definite time there must be an end to potential litigation.”
We hold that the statute enacted at
Closely related to the due process argument is the plaintiff‘s challenge to the statute based upon
II.
The plaintiff also claims the statute violates the equal protection clause and the constitutional prohibition against special legislation. See
Since no fundamental right or suspect class, such as race, sex, or national origin, is involved here, our scrutiny of the statute need go no further than determining whether the statutory classification is reasonably related to a legitimate state objective. Friedman v. Rogers, 440 U.S. 1, 17, 99 S.Ct. 887, 898, 59 L.Ed.2d 100 (1979); New Orleans v. Duke, 427 U.S. 297, 303-304, 96 S.Ct. 2513, 2516-2517, 49 L.Ed.2d 511 (1976); Cudahy Co. v. Ragnar Benson, Inc., 514 F.Supp. 1212, 1217 (D.Colo.1981). As we have stated hereinbefore, the statute bears a reasonable relationship to the legislative objective of limiting liability for architects, contractors, engineers, and inspectors whose work on an improvement to real estate generally ends at the time of substantial completion of a project. Among those groups who do not come within the language of the statute are materialmen, owners and occupiers of the improved property. In our view the distinction made between these groups is reasonable, and thus the statute does not violate equal protection, nor the prohibition against special legislation.
A landowner owes a duty of reasonable care to persons coming onto his property. Mile High Fence Co. v. Radovich, 175 Colo. 537, 489 P.2d 308 (1971); Rudolph v. Elder, 105 Colo. 105, 95 P.2d 827 (1939). Owners and occupiers of improved property have continuing control of the premises and are responsible for repairs and replacements of damaged or dangerous conditions. Architects, contractors, engineers, and inspectors, on the other hand, in most cases do not have continuing control over or involvement with the maintenance of the improvement after its initial construction. As the New Mexico Supreme Court stated in Howell v. Burk, supra, refuting a similar challenge to the New Mexico architect immunity statute:
Therefore, the General Assembly could have reasonably concluded that these roles are logically distinguishable. It may also have concluded that an architect should not be held liable indefinitely, based upon the assumption that most design defects would be discovered and most claims could be expected to be brought within ten years time after completion. See supra note 4.“Those covered by the statute have no control over the real estate improvement once it is completed and turned over to the owner. The owner or tenant may permit unsafe conditions to develop, or use the premises for a purpose for which it was not designed, or make defective alterations which may appear to be a part of the original construction. See Grissom v. North American Aviation, Inc., 326 F.Supp. 465 (D.C.Fla.1971).” 568 P.2d at 220.
In addition, materialmen are in a position distinct from the architect, contractor, engineer, or inspector in that the materialman provides manufactured goods and should be held accountable under the general tort rules governing liability for defects in those products. See
“Suppliers and manufacturers, who typically supply and produce components in large quantities, make standard goods and develop standard processes. They can thus maintain high quality control standards in the controlled environment of the factor. On the other hand, the architect or contractor can pre-test and standardize construction designs and plans only in a limited fashion. In addition, the inspection, supervision and observation of construction by architects and contractors involves individual expertise not susceptible to the quality control standards of the factory.”
Burmaster v. Gravity Drainage Dist. No. 2 of the Parish of St. Charles, 366 So.2d 1381, 1386 (La.1978); See Cudahy Co. v. Ragnar Benson, Inc., 514 F.Supp. 1212, 1217 (D.Colo.1981); Klein v. Catalano, 386 Mass. 701, 437 N.E.2d 514 (1982); Freezer Storage, Inc. v. Armstrong Cork Co., 476 Pa. 270, 276-277, 382 A.2d 715, 719 (1978).
Accordingly, the tort rationale for product liability does not easily extend to cover the providing of services.7
A similar analysis applies to the appellant‘s argument that the statute is “special legislation” prohibited by
As previously discussed, the classification made in this statute is reasonable and not arbitrary. The appellant has failed to prove that the statute is unconstitutional beyond a reasonable doubt.8
III.
The plaintiff next argues that even if the statute is not unconstitutional for the foregoing reasons, the architect, Pei, cannot come within the protections of the statute because Pei was not licensed to practice architecture in Colorado at the time the design services were first rendered in 1955-1958. However, Pei did become licensed in Colorado in 1959, before the substantial completion of the hotel and before the certificate of occupancy was issued.
When the work was done on the hotel, Pei and the other appellees were employees of the owner-developer of the hotel in New York, and licensed in that state. There Pei performed design services which were later incorporated in construction drawings signed and sealed by architects licensed in Colorado. Although issued drawings must bear the seal of a licensed architect, the appellees argue that in practice many qualified architects work under the aegis of licensed architects without being licensed themselves.
The language of
In conclusion, we hold that since more than ten years had elapsed after substantial completion of the building before this lawsuit was filed, the architects are immune from suit according to
The judgment of the trial court granting summary judgment is affirmed.
DUBOFSKY and QUINN, JJ., dissent.
DUBOFSKY, Justice, dissenting:
Because the ten year statute of limitations for actions against an architect under
At the time the plaintiff filed a cross-claim against I.M. Pei & Partners,
The appropriate statute of limitations was found in
I am authorized to say that Justice QUINN joins in this dissent.
QUINN, Justice, dissenting:
I join in Justice Dubofsky‘s dissent and add a few additional observations about
I believe the statutory language of
“Properly considered ... the Death Act is not a survival statute. This is true for the reason that the cause of action created by this statute is separate and distinct from the action which the deceased would have for personal injuries had he survived. The wife‘s action is rooted in the statute itself and the elements of her damage are essentially different from those proper for consideration in a personal injury action to which her injured husband would have been entitled if death had not ensued.”
Thus, in the instant case, the death of Dr. Yarbro‘s wife created a claim in Dr. Yarbro “which is essentially different from any liability chargeable to the tort-feasor prior to the death....” Fish v. Liley, 120 Colo. at 162, 208 P.2d at 933. We must presume that the legislature was aware of this construction of the wrongful death statute when it enacted
Excluding wrongful death actions from the 1969 version of
I would reverse the summary judgment and remand the case to the trial court for further proceedings on the plaintiff‘s claim against the architects.
I am authorized to say that Justice DUBOFSKY joins me in this dissent.
