This consolidated appeal is the latest manifestation of the numerous contract disputes arising from the Government’s failure to accept and dispose of radioactive waste from the nation’s nuclear utilities. Specifically, the appeal flows from this court’s decision in
Yankee Atomic Electric Co. v. United States,
Yankee Atomic Electric Company (Yankee Atomic), Maine Yankee Atomic Power Company (Maine Yankee), and Connecticut Yankee Atomic Power Company (Connecticut Yankee) (collectively, the Yankees) originally brought this action seeking damages to compensate for the cost of storing spent nuclear fuel (SNF) and high-level radioactive waste (HLW) beyond the time that the Government promised by contract to begin storing that waste in a permanent and secure repository. On remand, the trial court correctly calculated damages for dry storage construction costs, deferred costs of loading waste to the Department of Energy (DOE), and reracking costs. However, the trial court erred in denying Yankee Atomic’s claim for a portion of its wet pool storage costs and Nuclear Regulatory Commission (NRC) fees. Unlike
Consolidated Edison Co. of N.Y. v. United States,
Therefore, this court affirms-in-part and reverses-in-part the trial court’s damages award as recited below.
I.
This court has ofteii addressed the Standard Contract between the Government and nuclear utilities, and the Government’s liability for a partial breach.
See Me. Yankee Atomic Power Co. v. United States,
Starting in August 2004, the trial court held a seven-week trial on damages.
Yankee I,
On appeal, this court accepted the trial court’s “findings on foreseeability, reasonable certainty and the use of the substantial causal factor standard” for causation purposes, as well as the determination that an award of Nuclear Waste Fund fees should be denied as premature.
Yankee Atomic Elec. Co. v. United States,
On remand, the trial court accepted the fuel exchange model presented by the Yankees’ expert, and concluded that the Yankees would not have built dry storage; Maine Yankee and Connecticut Yankee also, according to the trial court, would not have reracked their storage pools under the 1987 ACR rate.
Yankee Atomic Power Co. v. United States,
The trial court also addressed certain “matters beyond the remand and mandate.” Id. at 717-19. Each side claimed the other presented issues beyond the scope of the remand. Id. at 719-20. The Yankees claimed that the Government’s argument to include GTCC pickup in the 1987 ACR queue was “of new cloth” and beyond the scope of the mandate. Id. at 719, 721. The Government responded that the Yankees’ claims for the cost of transferring SNF from their wet pools to DOE (including crane upgrades) were beyond the scope of the mandate. Id. at 720, 726. The Government also objected to Yankee Atomic’s claim for the costs to operate and maintain (O & M) its wet pool for 2000 and 2001, as well as its NRC fees.
The trial court found that the Government’s argument to include GTCC into the 1987 ACR queue was not raised during the Yankee I trial and was thus barred. Id. at 722. However, the trial court noted that even if the issue was not barred, “removal of GTCC by the date of at least the last SNF removal” would likely have occurred. Id. at 723. Moreover “the GTCC generated from shut-down reactors was statistically insignificant and would not have had an appreciable affect [sic] on the SNF queue.” Id. at 724. Finally “costs associated with dry storage and reracking would not have been incurred due to the presence of GTCC.” Id. at 725.
Another remand issue involved the costs of future loading to DOE and crane upgrades. The Yankees had voluntarily deducted these costs from the damages in
Yankee I
under the belief these costs were avoided costs and thus not recoverable. On remand, the trial court concluded that intervening Federal Circuit precedent indicated these were actually deferred costs, not avoided costs, and thus should not be deducted from the Yankees’ damages.
Yankee III,
Lastly, the trial court rejected Yankee Atomic’s attempt to resurrect its claims for costs relating to wet storage and NRC fees for the years 2000 and 2001. Yankee Atomic unsuccessfully sought these costs during
Yankee I,
but did not appeal the costs in
Yankee II. Yankee III,
On appeal, the Government complains that the trial court erroneously based its damages calculations upon estimates and speculation. Specifically, the Government claims that the trial court errantly relied on an exchanges model which was not grounded in fact and did not account for DOE’s discretion to reject fuel exchange
*1359
requests. The Government likewise appeals the trial court’s interpretation of the
Yankee II
remand as allowing the Yankees to claim damages conceded in the original trial yet precluding the Government from asserting that the Yankees must establish how GTCC would impact the SNF acceptance queue. The Government also appealed this court’s prior rulings regarding the appropriate rate of SNF and HLW acceptance under the Standard Contract and the status of GTCC as HWL under the Standard Contract.
See Carolina Power & Light Co. v. United States,
II.
This court reviews the trial court’s legal conclusions without deference,
Yankee II,
III.
This court recently affirmed a trial court’s use of an exchanges model when calculating damages for the storage of SNF in
Dairyland Power Cooperative v. United States,
Similar deference must be given in this ease. The Government has recycled the arguments already rejected in
Dairyland.
In
Dairyland,
the Government asserted that the utility “did not identify the specific [other] utilities it would have obtained year-one delivery commitment schedules from,” that local communities might have opposed the exchanges, and that the DOE had discretion to reject proposed fuel exchanges.
The trial court previously determined that in the nonbreach world, DOE would not have adopted an oldest fuel first
*1360
(“OFF”) procedure. Rather, fuel exchanges would have occurred.
Yankee III,
Compelling financial incentives, coupled with contractual provision for exchanges, which under full government performance, must be assumed to be used, and the history of utilities creating vigorous markets in analogous circumstances, all lead the court to conclude that it is plausible, and more likely than not, the market [the damages expert] presented would have developed, and to the extent he opined.
Id. at 692. The trial court noted that “[t]he government did not suggest that [the damages expert] was selective in his data, that he failed to gather appropriate data, or that his analysis was other than robust.” Id. As such, the trial court “[c]redit[ed] preponderant evidence” and concluded that the Yankees would not have built dry fuel storage in the non-breach world. Id. at 693.
DOE’s discretion to approve exchanges does not alter this analysis. “While considerations such as DOE’s discretion to approve such transactions and worries about the presence of failed fuel are certainly relevant, they are not overriding concerns sufficient to make the court’s finding clearly erroneous.”
Dairyland, 645 F.3d
at 1371. The trial court dedicated over twenty pages of analysis to the exchanges model, including detailed review of the model, the damages expert, and other relevant testimony.
Yankee III,
IV.
This court next turns to the issue of whether the trial court erred in interpreting the remand ordered in
Yankee II.
As this court has previously stated, “[u]pon return of its mandate, the district court cannot give relief beyond the scope of that mandate, but it may act on matters left open by the mandate.”
Laitram Corp.,
With respect to the Yankees’ claims for future loading costs and the
*1361
costs of crane upgrades, the trial court correctly noted that the intervening precedent of
Carolina, Power, Indiana Michigan,
and
Yankee II
changed the legal landscape for the calculation of damages on these issues. When the
Yankee I
trial occurred, future loading costs or costs associated with the transfer of fuel to DOE were considered avoided costs, and thus not recoverable by SNF plaintiffs. The Yankees agreed to reduce their breach world ISFSI costs by the estimated future cost of transferring SNF from their wet pools to DOE in the nonbreach world, on the ground these expenses were avoided because of the breach.
Yankee I,
When the trial court received this consolidated appeal on remand, it correctly allowed the Yankees to retract their initial voluntary deductions for these costs and reinstate these amounts as damages. The Government should not be allowed the unwarranted benefit of the Yankees’ voluntary deductions when those deductions would not have been necessary under subsequent precedent. As such, this court affirms the trial court’s determination regarding the deferred costs for loading waste to DOE.
This court also affirms the trial court’s finding that the Government could not assert that GTCC must be included in the SNF acceptance queue calculations. In
Yankee II,
this court held that DOE’s obligations under the Standard Contract apply to SNF and HLW, and placed GTCC within the definition of HLW.
During the Yankee I trial, the Government’s only argument relating to GTCC was that it had no obligation to remove GTCC under the Standard Contract because GTCC was not HLW. During the Yankee I trial, the Government could have argued in the alternative that removal of GTCC, if required, would have changed DOE’s waste acceptance queue. Without this alternative argument, the trial court need not now rewind the clock to pursue a new litigation approach. Unlike the Yankees’ costs for loading to DOE discussed above, the Government has not identified an exception to the mandate rule such as a change in the law or manifest injustice which would justify the requested departure from the norm. As such, this court affirms the trial court’s determination on this point.
In holding that the Government could not raise its GTCC argument during the remand, this court does not address the trial court’s alternative finding that “the GTCC generated from shut-down reactors was statistically insignificant,” and that “costs associated with dry storage and rer-acking would not have been incurred due to the presence of GTCC.”
Yankee III,
V.
Lastly, this court considers whether the trial court erred by excluding some of the costs Yankee Atomic incurred to operate its wet storage pool. In
Pacific Gas & Electric Co. v. United States,
this court affirmed a trial court’s interpretation of a similar mandate to that ordered in
Yankee II:
reconsideration of the damages presented during the initial trial in view of the 1987 ACR.
In like fashion, Yankee Atomic claimed its wet storage pool costs initially during the
Yankee I
trial. The trial court denied these costs on the ground that Yankee Atomic’s wet pool would not have been emptied by the 1999 fuel-out date.
Yankee I,
The trial court erroneously stated that the scope of the remand in
Yankee II
was to reexamine the causation for “discrete costs previously awarded,” and not to open the door for to additional costs.
Id.
at 726. This interpretation is too narrow. The remand was ordered “[b]ecause the Court of Federal Claims did not assess damages according to the rate at which the Government was contractually obligated to accept the utilities’ waste.”
Yankee II,
Regardless of whether the trial court originally granted or denied Yankee Atomic’s damages claims, once the trial court determined on remand that all SNF would have been removed from Yankee Atomic’s wet storage pool by the end of 1999 under the 1987 ACR rates in the hypothetical world, the court was required to apply that finding to its prior damages calculations. Under the Yankee II remand, the trial court was free to “revisit and reconsider” issues raised at trial, particularly as its application of this court’s mandate changed the factual predicate for its prior decision to deny Yankee Atomic’s costs. Indeed this record demanded such attention to the implications of applying the 1987 ACR rates.
Unlike the Government’s argument regarding GTCC, Yankee Atomic’s claim for these costs was initially raised at trial. As such, this court reverses the trial court’s denial of Yankee Atomic’s wet storage pool costs and NRC fees. The trial court wisely foresaw that this court could reverse its refusal to consider these costs. For this reason, the Court of Federal Claims found that Yankee Atomic had established these costs with reasonable certainty. Thus, this court need not remand for further *1363 damages calculations, but only for entry of judgment in an additional amount of $17,021,742.
VI.
Yankee Atomic’s claims for wet storage pool costs and NRC fees were within this court’s mandate in Yankee II. As such, the trial court’s denial of these costs is reversed. The remainder of the trial court’s decision is affirmed. Judgment should be entered to award Yankee Atomic Electric Co. an additional $17,021,742.
AFFIRMED-IN-PART AND REVERSED-IN-PART
COSTS
Costs to Plaintiffs-Cross Appellants.
