YAKIMA ASPHALT PAVING COMPANY, ET AL, Appellants,
v.
THE DEPARTMENT OF TRANSPORTATION, Respondent.
The Court of Appeals of Washington, Division Two.
Timothy J. Carlson and Halverson & Applegate, for appellants.
Kenneth O. Eikenberry, Attorney General, and Gregory F. Brunson, Assistant, for respondent.
WORSWICK, C.J.
Yаkima Asphalt Paving Company, a subcontractor on two highway projects, brought this action against the Washington State Department of Transportаtion, claiming that it was entitled to an "asphalt cement adjustment" pursuant to a price adjustment provision in *664 the prime contract between thе Department and Northwest Construction, Inc. On motion, the Superior Court dismissed because the action as to one project had not been brought within the 180-day limitation period set forth in RCW 47.28.120, and as to both projects because the prime contractor, Northwest, had executed full releasеs of all claims pursuant to another contract provision. Yakima Asphalt contends that RCW 47.28.120 is unconstitutional, and that the releases are invalid. We do not reach the constitutional question. We affirm, holding that a 180-day limitation period in the prime contract applies, and that the releases are valid.
Northwest and the Department entered into contract 1772 on December 19, 1979, for construction of an interchange on State Rоute 82 in Eastern Washington. On January 3, 1980, the parties signed contract 1759 for a different interchange along the same highway. Northwest then subcontracted with Yakima Asphalt for the asphalt work on both projects. In order to qualify for final payment, Northwest was required by the prime contracts to certify cоmpletion of the work and to release the State from any claims except those expressly identified. Each prime contract also included the following provision:
For the convenience of the parties ... it is mutually agreed ... that any claims or causes of action which the Cоntractor has against the State of Washington arising from this contract shall be brought within 180 calendar days from the date of final acceptancе of the contract by the State.... The parties understand and agree that the Contractor's failure to bring suit within the time period provided, shall be a complete bar to any such claims or causes of action.[[1]]
*665 Work on contract 1759 was completed and accepted by the Deрartment on November 15, 1982. Work on contract 1772 was completed and accepted on February 22, 1983. On each, Northwest certified completion as required, and released the State from all claims without exception.
Yakima Asphalt's action, begun in June 1983, was met by the Department's motiоn to dismiss.[2] The Department contended that Northwest's releases barred both claims, and that both the 180-day contract limitation and RCW 47.28.120 barred the claim on contract 1759.
The trial court agreed with the Department concerning the releases. It went on to note that the contract limitation and thе statutory limitation were identical. It did not apply the contract provision, but held that the statute as well as the release barred the claim оn contract 1759.
[1] Yakima Asphalt first contends that RCW 47.28.120 is unconstitutional. We decline to consider this contention. A court will not decide on constitutional grounds an issue that can be resolved on other grounds. Tommy P. v. Board of Cy. Comm'rs,
[2] Parties to a contract can agree to a shorter limitations period than that called for in a general statute. Order of United Comm'l Travelers of Am. v. Wolfe,
Northwest agreed that all claims would be barred unless brought within the 180-day contractual period. No statute prohibits the shorter limitations period. To the contrary, RCW 47.28.120 expresses a public policy congenial to such a limitation for public works contracts.
Yakima Asphalt contends that the provision is unenforceable because it is unreasonable. We disagree. Legislative appropriatiоns, budgetary constraints, federal funding concerns, the volume of public works contracts, and the entire highway funding scheme all make a shorter limitation period reasonable. We see no reason why a contractor or subcontractor would be unaware of a potential claim before a project is completed, and unable to assert it within this limitation period.
Yakima Asphalt next argues that the releases Northwest signed аre unenforceable. It contends that these releases were not supported by consideration because Northwest only receivеd payment to which it was already entitled. We disagree.
[3] Inland Empire Builders, Inc. v. United States,
Finally, Yakima Asphalt argues that even if the releases are valid, they are only enforceable against Northwest because it was a third рarty beneficiary. We disagree.
[4] Yakima Asphalt was not a third party beneficiary. A third party beneficiary contract is not created unless the parties intend that the promisor assume a direct obligation to the intended beneficiary at the time they enter into the contract. Burke & Thomas, Inc. v. International Org. of Masters, Mates & Pilots,
We have considered Yakima Asphalt's additional contentions and find them without merit.
Affirmed.
PETRICH and ALEXANDER, JJ., concur.
Reconsideration denied November 6, 1986.
Review denied by Supreme Court March 3, 1987.
NOTES
Notes
[1] RCW 47.28.120, containing the same limitation period, reads: "Actions for labor and materials Limitation of action. Any contracting person, firm, or corporation performing any labor or furnishing any materials upon their contract or otherwise for public work or improvement under the direction of the department or any person claiming any right of action upon any such contract with the state of Washington or whо claims a cause of action against the state of Washington arising out of any such contract must bring such suit in the proper court in Thurston county befоre the expiration of one hundred and eighty days from and after the final acceptance and the approval of the final estimate of such work by the department; otherwise the action is forever barred."
[2] Northwest also joined the action as a plaintiff, but assigned its claim to Yаkima Asphalt.
The details of the claim are irrelevant. It involved a contract provision designed to protect the parties from fluctuatiоns in the price of asphalt. Yakima Asphalt contended that the Department used the wrong data in utilizing this provision, thereby causing Yakima Asphalt to be underpaid.
