Appellee-plaintiff, The Western Casualty and Surety Company, a compensated surety on a construction contract performance bond, brought this action for indemnity to recover its costs in completing the contract after default by its principal.
The United States, acting through the Bureau of Reclamation, Department of the Interior, contracted with S. J. Groves & Sons Company for the construction of the Big Sandy Dam and Dike in western Wyoming. Groves subcontracted the earth embankment and riprap on the dam to Forgey Construction Company which, in turn, subcontracted the riprap work to Wyoming Construction Company. Western was the surety on the performance bond given by Wyoming to Forgey. Wyoming failed to complete and performance was taken over by Western. During the period involved, Wyoming became a wholly-owned subsidiary of appellant Monolith Portland Midwest Company. The jury verdict, in favor of Western and against Wyoming and Monolith, was for $74,677.33 to which the court added $25,701.45 as interest and entered judgment for $100,378.78.
Wyoming contends that Western is not entitled to indemnity because an antecedent default of Forgey relieved Wyoming of its obligation to perform and such default and its effect were known to Western. All pertinent contracts required completion of performance by November 29, 1951. The riprap work of Wyoming had to follow the placing of embankment by Forgey but could advantageously proceed as the embankment rose in height. On the contract termination date Forgey had placed more than 90% of the embankment materials and Wyoming had placed less than 10% of the riprap. The breach by Forgey, upon which Wyoming relies, is the failure of Forgey to complete the embankment by November 29, 1951.
The issue as to whether Wyoming was excused from performance because of the alleged breach by Forgey was submitted to the jury under adequate instructions and the jury by its verdict adverse to Wyoming on all issues necessarily found that the conduct of Forgey did not excuse Wyoming. Substantial evidence in the record sustains such conclusion.
There were four principal stages in the riprap operation covered by the Forgey-Wyoming subcontract.
The testimony of Wheeler, the president of Wyoming until June 1952, was that in September 1951 he, as the responsible executive of that company, decided that it would be impossible to complete by the contract date and that it would be necessary to work through the winter. The record shows that no fail
Wyoming next urges that the extensions of the date for completion of performance were material alterations of the contract which discharged the surety. In support of this contention it points out that construction work in western Wyoming is more costly in winter periods because of severe weather conditions and that the contract contemplated the work would be completed before the winter season.
The contracts involved all provided for an extension of the performance date.
The failure to perform on time did not terminate the contract.
This is not an action by an obligee to collect from a surety. Rather, it is an action by a surety which has performed in the place of its principal and which seeks to collect from its principal under a written contract of indemnity. That contract authorized the surety “to consent, from time to time, to any extensions, modifications, changes or alterations of, or additions to, said contract, * * While no formal written consent was executed, the conduct of Western is consistent only with consent to the extensions.
The equities of the situation cry out against Wyoming. By starting late and using inadequate equipment it failed to keep abreast with the progress of Forgey. It led all parties to believe that by winter work it would catch up with Forgey and complete the riprap^ promptly after the completion of the embankment. It did not object to the extensions but instead aided in their procurement. It failed to do the job
The other claimed material alterations of the Forgey-Wyoming contract relate to the advance by Forgey to Wyoming of part of the purchase price of a crusher and numerous advances on a yardage basis to pay lease truckers. These advances were made by Forgey because of the financial condition of Wyoming. They were credited against payments to Wyoming when those payments became due. Granting that in some circumstances an advance payment may be a material alteration of a contract,
Wyoming further says that Western breached its duty to act in good faith. We have no doubt that a surety must act in good faith in its dealings with its principal.
Only one facet of the bad-faith charge merits comment. Wyoming says that Western acquiesced in Forgey’s notice of default and did not assert the antecedent breach and material alteration defenses which were available. A sufficient answer is that such defenses, for reasons heretofore stated, were not available to either the principal, Wyoming, or to the surety, Western. Each, by its actions, had lost its right to assert those defenses, if either or both ever had such right. Be that as it may, the conditions existing at the time of the Forgey default notice and demand show that if there was any bad faith it was on the part of Wyoming, not on the part of Western.
As of May 31, 1952, Forgey was 99% complete and Wyoming 34%. In mid-June, Wyoming stopped the placement of riprap, stacked its machinery and equipment, and laid off its employees other than supervisors. The work was at a standstill. By letter dated June 27, 1952, Forgey gave Wyoming a notice of default stating that it, Forgey, would take over the work on July 2, 1952. At the same time, Forgey notified Western to perform under its bond.
A meeting attended by all interested parties was held on July 14, 1952. Wyoming, then under the domination and control of Monolith, refused to finish the job and Western assumed the responsibility of completion. At the time no protest was made by either Wyoming or Monolith. The subsequent formal protest, which did not state any substantiating grounds, did not detract from the good faith of Western. Here again the equities are with Western, which performed, and against Wyoming, which defaulted.
Western relies upon the so-called instrumentality rule under which it says that Wyoming is to be regarded as a department or agent of Monolith with the result that Monolith is responsible for the defaults of Wyoming.
In Taylor v. Standard Gas & Electric Co., 10 Cir.,
In a recent case arising in Colorado, Fitzgerald v. Central Bank and Trust Company, 10 Cir.,
At the time of the execution of the Forgey-Wyoming contract the stock in Wyoming, with unimportant exceptions, was owned by Wheeler and his wife. Wyoming supplied gypsum to Monolith.
In the fall of 1952 Wyoming was having financial trouble. It applied to Monolith for help. On January 14, 1952, Monolith advanced $25,000 which Wheeler, the president of Wyoming, considered an advance on a $75,000 open line of credit. On the same date all of Wyoming’s stock was assigned to Monolith or its nominees with a repurchase option if the indebtedness was repaid.
As part of the January 14 transaction in which Monolith advanced the $25,000, Wyoming took appropriate corporate action to surrender completely its power to conduct its own business without the approval of Monolith.
Although Wheeler was continued as president of Wyoming until May 1952, his efforts to complete the Forgey contract were frustrated by the Monolith control. Monolith, which in January had advanced funds to Wyoming, refused additional financing. A Monolith employee, acting as an officer of Wyoming, shut
The assumption of ownership and control of Wyoming was to the advantage of Monolith because of the gypsum contract which Monolith had made “through desperation” when it lost its prior source of supply and which was profitable to Wyoming. The decision to proceed no further with the Forgey contract was a detriment to Western as it was obligated under its performance bond. The facts justify the conclusion that Monolith was using Western and its property to the sole advantage of Monolith. That advantage was served by the abandonment of the Forgey contract.
Monolith emphasizes that there was no evidence of fraud but it is enough if the disregard of the corporate entity is required to prevent^ Jnjustiee. The issue was submitted to the jury under instructions, which, when taken as a whole and considered in their entirety, fairly and adequately set out the controlling principles. There was substantial evidence from which the jury could find that Monolith controlled and dominated Wyoming in the interests of Monolith and with full knowledge of the situation caused Wyoming to default on the Forgey contract with resulting detriment to Western. The verdict of the jury is sustained. It would be inequitable and unjust to permit Monolith to escape the con sequences of its conduct.
Wyoming and Monolith say that the trial court erred in permitting the filing of the amended complaint which joined Monolith as a defendant. Amendments to pleadings are within the sound discretion of the trial court and should be granted freely as justice requires.
Wyoming contends that the amended complaint should not have been permitted because Western had violated an earlier order in aid of discovery. The situation is that the trial court ordered Western to make more specific answers to certain interrogatories. Supplemental answers were made and there was no objection of lack of specificity. The point is without merit.
Error is predicated on the submission of two interrogatories to the jury in accordance with Rule 49(b), F.R. Civ.P. The court advised the parties well in advance that it would submit these interrogatories. No objection was made. The verdict was consistent with the answers to the interrogatories. By failure to object the parties have waived the right to protest now. In any event the interrogatories were fair and pertinent and did not prejudice the rights of any parties.
Various complaints are made against the instructions. A careful reading of
To the jury verdict assessing Western’s damages at the sum of $74,677.33, the trial court added $25,701.45 as interest from January 23, 1953, the day when Western submitted to Wyoming an itemized statement of its expenses in completing the Big Sandy project. The award of interest is contested on the grounds that the amount due under the indemnity contract was unliquidated and that the court was without power to add interest to the verdict.
The contract was made and performed in Wyoming. This diversity action was brought in the United States District Court for the District of Wyoming. The law of that state controls to determine the right to interest.
The applicable Wyoming statute
The itemized statement submitted by Western to Wyoming on January 23, 1953, showed the amount due to be $82,228.81. This was later reduced to $74,677.33 by adjustments favorable to Wyoming and secured through the diligence of Western.
The attack by Wyoming on the necessity of certain expenses does not change the character of the claim. The fact that a claim is disputed does not preclude the recovery of interest.
In allowing interest the trial court acted on the authority of American Surety Co. of New York v. Carbon Tim
In Leet v. Joder,
This case does not come within either inhibition of the Leet decision. The jury was not instructed on the matter of interest.
Affirmed.
Notes
. Wyoming brought in as third-party defendants Forgey Construction Company and Orrin B. Forgey, Bussell Forgey, Chas. S. Chapin and W. J. McNamara, individually and as co-partners doing business as Forgey Brothers. The jury verdict was in favor of the third-party defendants. In this appeal the judgment in favor of the third-party defendants is not contested.
. The subcontract covered both “blanket materials and riprap." The operations are so connected that herein reference will be made only to riprap.
. In the Forgey-Wyoming contract it was provided that there might be no extension without the written consent of Forgey. The absence of such written consent may not be raised by Wyoming and it is not asserted by any other party. Neither Wyoming nor Forgey objected to the extensions and by their conduct acquiesced therein.
. Barnard-Curtiss Company v. United States, 10 Cir.,
. Restatement of the Law, Security, § 129(2), p. 346, states the rule to be that where the principal (Wyoming) and the creditor (Forgey) without the surety’s consent agree to an extension, a compensated surety is discharged only to the extent that it is harmed by the extension.
. Wettlin v. Jones,
. See 72 C.J.S. Principal and Surety §§ 133-134, pp. 622-627.
. Trinity Universal Insurance Company v. Gould, 10 Cir.,
. Ibid.
. Schoonover, the chief engineer of Monolith, testified: “* about .1950 or 1951, I don’t recall the exact year when the U. S. gypsum plant at Laramie shut down and we were immediately forced to go out and find a source of gypsum. At that time Mr. Wheeler located a gypsum quarry for himself with the thought in mind of selling gypsum, so through desperation we bought gypsum from the Wyoming Construction Company.” It was not until 1953 or 1954 that Monolith located its own gypsum deposit.
. At the time of the stock assignment, the Wyoming stock had a book value of $98,-000.
. Rule 15(a) F.R.Civ.P., 28 U.S.C.A.; Zeigler v. Akin, 10 Cir.,
. 1945 Wyo.Comp.Stat. § 3-506.
. Id. § 3-504.
. Id. § 3-505.
. Id. § 3-509.
. T. & M. Transp. Co. v. S. W. Shattuck Chemical Co., 10 Cir.,
. 1945 Wyo.Comp.Stat. § 39-1104.
. In re Johnson’s Estate and Guardianship,
. The most important credit resulted from the action of Western in securing remission of penalties by the Bureau.
. North Drive-in Theatre Corporation v. Park-In Theatres, Inc., supra,
. The pertinent instruction was: “Now^ there are some items that are raised here as to whether an airplane was necessary in the completion of a job. There is; other evidence that there was too much overtime paid, and I am sure that evidence is all clear in your mind. If you find for the Casualty Company then you shall take into consideration whether the $74,677 was the amount which they incurred in eomi>leting the job, less any expenses which you feel were unnecessary in the completion of the job.”
. The language of the Supreme Court of Wyoming in Wyoming R. Co. v. Leiter,
. Neither party requested such an instruction.
. There reliance was placed on the provision allowing interest “on money * * due, and withheld by unreasonable delay of payment.”
