144 P. 341 | Idaho | 1914
This is an original application for a writ of mandate to J. R. Strong, city clerk of the city of Moscow, for the purpose of requiring him to issue and countersign a warrant on the treasurer of said city for the sum of $5,500 which has been allowed by the city to the plaintiff upon his claim for material and labor in the construction of certain sewers in the said city of Moscow.
After the material had been furnished and the work done, the plaintiff filed with the city his verified claim therefor, which was audited and allowed by the city council and the defendant was directed to draw and countersign a warrant on the city therefor, and the clerk thereupon refused to draw said warrant and entered upon the minutes the following: “The city clerk at this time gave notice to the city council of his refusal to comply with the order of the council and hereby does refuse to draw such warrant for the reason that he is informed and believes that the said claim was and is illegal and void. ’ ’ • And said clerk has ever since refused to draw said warrant, and this proceeding was instituted for the purpose of procuring a mandate commanding the clerk to issue such warrant to the plaintiff.
If the city clerk may decide whether a warrant shall be drawn or not in payment of a claim against the city, then the act of council in allowing or disallowing the claim would be an idle act. The city under the provisions of the law has the right to construct sewers and to pay for the same out of the general fund or by special assessments. The record shows that the city contracted for said improvements; that they were constructed by the plaintiff; that the city accepted them; that it allowed the claim of plaintiff therefor, and ordered the warrant drawn for the payment of the same. Even if the law were not technically complied with in letting said contract and in doing the work, and the city thereafter accepted it and appropriated the work to its benefit, it certainly must pay for it, especially where there is no fraud charged in the letting of such contract. A contract because of some irregularity or informality in the time or manner of its execution may be illegal and incapable of enforcement, but where such contracts are within the usual exercise of the powers and duties of the city council and the work and materials are accepted by the city, it must pay for them.
Some question is raised by the answer, out of what funds this claim must be paid. It is conceded that there is sufficient in the general fund for that purpose and more than sufficient, and the question is mooted, as to levies made in 1913, when half of the taxes realized therefrom are paid in
For the reasons above stated, the peremptory writ as prayed for must be granted, and it is so ordered, with costs in favor of the plaintiff.