Lead Opinion
John W. Ferguson ha,d a contract for the construction of a building for the Hamilton Trust Company of Paterson, H. J. Plans for the same were made by one H. Gf. Stephens, architect. The firm of D. S. Hess & Co., these defendants, were sub-contractors under Ferguson. The plaintiff, doing business as the Empire Brass and Metal Works, entered into a contract with the defendants on July 31, 1902, for the performance of certain work and the furnishing of certain materials in the construction of the metal work of iron, polished and electroplated, for the said Hamilton Trust Company’s building, -By tk§ temis of the original eontmol till? woyfc wai te
The original contract, after stipulating that the sub-contractor (the plaintiff) should “ weU and sufficiently perform and finish in a thoroughly workmanlike manner * * * all metal work' of iron,” etc., “ under the direction and to the satisfaction of the general contractors' (these defendants) and IT. Gr. Stephens, architect, -x- * -x- agreeably to the drawings and specifications made by the said architect,” provided in the 3d clause that “ should any alteration he required in the work shown or described by the drawings or specifications, a fair and reasonable valuation of the work added or omitted shall he made by the general contractors, and the sum herein agreed to he paid for the work according to the original specifications shall be increased' or diminished as the case may be.” ■ It was further provided that “ in case such valuation is not agreed to, the sub-contractor shall proceed with the alteration upon the written order of the general contractors, and the valuation of the work added or omitted shall be referred to three (3) arbitrators, * * * tlie decision of any two of whom shall be' final and binding, and each of the parties hereto shall pay one-half of the expense of such reference.”
It is clear that under the provisions of this clause the plaintiff could do no extra work for which he could make a charge except upon the written directions of the defendants. In case the defendants gave such directions and the extra work was done, then if. the parties could not agree upon the reasonable value of the same the arbitrators were to fix the same, and their decision should be'binding. The arbitrators are not given any authority, to determine tlie question of what was “ work, added or omitted.” That was left to the parties themselves. The only question which could be' submitted to • arbitration under the 3d clause of the contract was the valuation of the work added or omitted. This appears to be the construction placed upon the contract by the parties. Disputes at ones arose as to whether or not pertain work required by the
On the twenty-seventh day of Febrnary, two days later, the defendants wrote to the plaintiff: “We are agreeable to leaving undecided questions in relation to the above work to the decision of Mr. John W. Ferguson, but do not desire that work be proceeded with upon this building which might be construed as additional work without a written notice to that effect from you.” On the twenty-eighth day of February the plaintiff acquiesced in the suggestion that the extra work for which a claim was to be made should be stated in writing to the defendants, at the same time enumerating the items for which he would ask Mr. Ferguson to award “ an extra,” which embraced “ the iron work which goes above the frames which we made for the revolving doors, * * * register facings,” and “ the trouble and expense we have been put to, owing to the fault of some one in setting those revolving windows, without authority from us.” It was declared in this communication that “ this covers all the points which have not been settled between ourselves,” the defendants being requested if there was any of this work to be stopped to notify the plaintiff at once.
The practical result accomplished here is not a waiver of the
The principal item for extras for which the plaintiff recovered before the referee and upon this appeal seeks to sustain, was set forth in the eighth cause of action of the complaint. After alleging the formalities of performance the complaint continues, “ That upon the completion of the contract, as hereinbefore set forth, the plaintiff submitted the question as to the valuation of such additional work to John W. Ferguson. That the said John W. Fergu
We examine the record in vain for any evidence to show that John W. Ferguson refused to pass upon the matters submitted to Mm by the plaintiff, except upon condition that he should pass upon other matters pending between himself and the plaintiff. It is true that the plaintiff in his letter refuses to go on with the arbitration, and alleges that the arbitrator refused to consider matters except in connection with others in which he was interested, but this is not evidence of that fact. It clearly appears from the record that the only matters before Mr. Ferguson were such as the plaintiff voluntarily placed before him. There is no evidence which warrants the conclusion that Mr. Ferguson sought or undertook to pass upon any item or question which plaintiff did not voluntarily place before him. The evidence clearly discloses that the plaintiff knew neither more nor less of Mr. Ferguson at the time of the submission of his questions than he did at the time the contract was modified, and so far as we can discover there was no reason for his withdrawing from the arbitration. If there were good reasons why Mr. Ferguson was not a proper person to act, it was the duty of the plaintiff, under his contract, not to repudiate the arbitration absolutely but to point out the disqualifying circumstances and seek to have a different person chosen. But the plaintiff alleges that he did something of the kind; that he “ offered to refer to three arbitrators, as provided in said contract, the question of the kind, character and valuation of such additional work,” and that the defendants refused so to refer. It is true that the plaintiff did, November II, 1903, at the time of repudiating the arbitration under his modified contract, ask the defendants to name their man-under the provisions of clause
In this situation it' is by the plaintiff suggested, on the authority of Seward v. City of Rochester (109 N. Y. 164), that the determination of Mr. Ferguson as arbitrator was not a necessary condition precedent to the right of the plaintiff to recover. The propo-. sition is that the agreement to arbitrate was such as to oust the courts of jurisdiction, arid that it was void as against public policy. There can be no doubt of the rule that where parties undertake, by independent covenant or agreement, to provide for an adjustment and settlement of all disputes and differences by arbitration, to the exclusion' of the corirts, such agreement is void and does not. stand
In the case last above cited the court reiterates the rule that “ Where the .parties, in their contract, fix on a certain mode by which the amount to be paid shall be ascertained, as in the present ease, the party that seeks an enforcement of the agreement must show that he lias done everything on his part which could be done to carry it-into effect. He cannot compel the payment of the amount claimed unless he shall procure the kind of evidence required by the contract, or show that by time or accident he is unable to do so.” (See, also, Spink v. Co-operative Fire Ins. Co., 25. App. Div. 484.)
The provision under consideration in National Contracting Co. v. Hudson River W. P. Co. (170 N. Y. 439) was certainly far more open to the objection that it tended to oust the courts of jurisdiction than the contract here under consideration, yet the court on demurrer'refused to sustain the contention that it was void; and we believe the uniform i authority of- this country is in harmony with the views expressed.-
If we are correct in these conclusions it follows that the eighth cause of action must fail. The plaintiff fails to show an award on
We are equally clear that there is no valid foundation for the cause of action Mo. 7. There was no time limit in the modified contract. Mo notice was given at any time, by the plaintiff that he would hold the defendants responsible for damages resulting from delay because of their failure to perform. This was prerequisite to a right of recovery for damages resulting from such a cause as is here claimed. In fact the record does not disclose that the defendants were in default under the contract at any time, and that they are liable for delays such as are shown by the record.
The findings of the referee in respect to causes of action numbers 1, 2, 3, 4,-5 and 6 may be said to be supported (though meagre in instances) in the testimony, and the judgment to that extent should not be disturbed.
The judgment should, therefore, be modified by deducting $3,569.04 therefrom as of the. date of entry, and as so modified affirmed, without costs.
Ingraham and Laughlin, JJ., concurred; Patterson, P. J., and Houghton, J., dissented in part.
Dissenting Opinion
I concur in the reduction of the judgment recovered in this action by the sum of $576, which the referee has allowed for damage suf
I am compelled, however, to dissent from the further reduction ' of the judgment by the sum of $2,993.04, which amount was allowed by the referee for extra work as claimed by the plaintiff. While it is true that by the terms of the contract between the parties written orders were required to authorize the performance of extra work, yet the evidence shows satisfactorily to my mind that such requirement was waived. That the work was performed and that the defendants received and accepted it is indisputable. During its progress the defendants- agreed to submit the construction of the contract to arbitration. Pending that arbitratioh it was disclosed that Mr. Ferguson, one of the arbitrators, was personally interested in the determination .of ■ the question, for this work was evidently stich as would either come within a contract to be performed by him or within the plaintiff’s contract, and the latter, with good reason, objected to going on with the proceeding before one who was . virtually an adverse party to him. It was not incumbent upon the plaintiff, after refusing to proceed before a board of arbitrators. of which Ferguson was a member, to suggest a new arbitrator. While it appears that efforts were made to constitute anothér board of arbitration, which efforts failed, .there was no absolute legal obligation on the plaintiff’s part to submit his claim to another, arbitrator or other arbitrators. The referee has found, and upon abundant evidence, that the whole amount of $2,993.04 was actually-for extra work, and I am of the opinion that the plaintiff is justly entitled to recover that amount. . .
The judgment should be modified by deducting therefrom the amount of $576, and as thus modified affirmed, without costs in this court.
Houghton, J., concurred.
Judgment modified as directed in opinion, and as modified affirmed, without costs. Settle order on notice.