WSS Industrial Construction, Inc. v. Great West Contractors, Inc.WSS Industrial Construction, Inc. v. Great West Contractors, Inc.
Opinion
SUMMARY
A corporate subcontractor sued a general contractor to recover for work performed under a construction services agreement. At trial, the general contractor and its surety moved for nonsuit arguing the subcontractor was barred by the Contractors’ State License Law, Business and Professions Code section 7000 et seq. (the CSLL), from maintaining any action for recovery because the subcontractor was not properly licensed at all times during its performance of the contract. The trial court disagreed. It concluded the corporation’s president held a valid individual contractor’s license at all times and that, in any event, licensure was not required for tasks the corporation performed prior to obtaining its license. The court found “there was substantial compliance with the licensing [statute] during the contract and work was performed in good faith,” and denied the motions for nonsuit A jury found in favor of the subcontractor and awarded over $220,000 in damages, statutory penalties and interest.
We conclude the trial court erred in denying nonsuit. With one exception, the CSLL forbids a contractor from recovery—in law or at equity—on an otherwise valid claim for performance of any service for which a license is required if the contractor was unlicensed at any time during performance of the work. In this case, the subcontractor was unlicensed during a period in which it performed services that could only be performed by a licensed contractor. We further hold the subcontractor is unable to meet the threshold requirement to invoke the statutory exception of substantial compliance with the CSLL, because it was never licensed as a state contractor prior to beginning performance. Accordingly, we will reverse and remand the matter for entry of judgment in favor of the general contractor and its surety.
FACTUAL AND PROCEDURAL BACKGROUND 1
Plaintiff and respondent WSS Industrial Corporation, Inc. (WSS or, at times, the corporation), a steel subcontractor, sued general contractor appellant Great West Contractors, Inc. (Great West), to recover for work WSS performed under a subcontract with Great West for improvements on a public works project at the new Middle School for the Deaf, in Riverside, California (the project).
A jury trial was conducted in January 2006. After WSS rested, Great West and Fidelity moved for nonsuit, asserting WSS was statutorily barred by the CSLL from recovery under the subcontract because it was not duly licensed at all times during performance of the contract, and could not demonstrate substantial compliance with state licensing requirements because the corporation never held a California contractor’s license before it began work under the subcontract. (
DISCUSSION
Great West insists the trial court erred in denying nonsuit because there can be no question WSS, the corporate entity, was not licensed, as required by
1. The licensure requirements embody a legislative scheme aimed at protecting the public against unscrupulous and incompetent contractors.
Since its adoption in 1939, the CSLL “has declared that, except as expressly otherwise provided, a contractor may not sue to collect compensation for
The CSLL embodies a comprehensive legislative scheme governing the construction business in California. It reflects a strong public policy, which favors protecting the public from unscrupulous and incompetent contractors. According to our Supreme Court, “The purpose of the licensing law is to protect the public from incompetence and dishonesty in those who provide building and construction services. [Citation.] The licensing requirements provide minimal assurance that all persons offering such services in California have the requisite skill and character, understand applicable local laws and codes, and know the rudiments of administering a contracting business. [Citations.]”
(Hydrotech Systems, Ltd. v. Oasis Waterpark
(1991)
The trend in changes to
2.
Application of legal principles to this case—
a. WSS performed work before it was licensed.
In this action, WSS, the corporation, entered into a subcontract with Great West. WSS was thus the “person” engaging in the business or acting in the capacity of a contractor. Accordingly, once licensure was controverted, it was WSS’s obligation to prove the corporation was properly licensed at all times during performance
WSS was incorporated in April 1999. The corporation applied for a contractor’s license on August 20, 2001, and submitted its bid proposal to Great West on August 28, 2001. 6 On December 1, 2001, WSS executed the subcontract, which incorporated its bid proposal. WSS agreed to “obtain necessary licenses prior to starting work,” and to “comply with all laws, rules, ordinances, and regulations of all governing bodies having jurisdiction over the work.” WSS did not obtain its contractor’s license until December 21, 2001. WSS’s license expressly states it “did not exist before that date.” WSS inserted its contractor’s license number and returned the subcontract to Great West in early January 2001. Great West signed the document on January 2, 2002.
Meanwhile, on October 10, 2001, WSS notified the state (the owner of the project) it intended to begin work on the project within 20 days. That notice was required so the corporation could be paid for its work. On October 29, 2001, WSS sent Great West an invoice for $15,000 for initial preparation of “shop drawings.” Ramirez testified the invoice was for work to be completed by the corporation by October 31, 2001. WSS submitted a second invoice for $11,000 on December 19, 2001, “for work completed to date,” which included $9,000 for shop drawings and $2,000 for specialized anchor bolts WSS ordered and had delivered to the project. Ramirez testified that ordering materials—such as anchor bolts—was included in WSS’s subcontract. He also testified he knew licensure was required for preparation of shop drawings, and that he knew WSS did not have its contractor’s license when it submitted its first two invoices. WSS sent Great West a third invoice on December 25, 2001. That invoice sought payment for about $192,000 worth of materials, including 40 percent each of the Canopies/Steel and Tube Steel Columns/Steel, 80 percent of the Canopies/Galvanize and 100 percent of the Rolling Tube Steel. Each of these items was included in WSS’s bid proposal. The December 25 invoice included work WSS expected to complete and have inspected by December 31, 2001. 7
First, we address WSS’s contentions that licensure was not required for any of the work it did before December 21, 2001. WSS is mistaken.
(i) WSS may not segregate “acts” performed in furtherance of the contract.
First, WSS insists it is entitled to recovery because the discrete tasks of ordering anchor bolts and preparing shop drawings do not constitute performance and can be segregated from the subcontract.
A strikingly similar attempt by an unlicensed contractor to segregate certain tasks from an integrated contract to avoid the bar of
We also find no merit in WSS’s assertion that the ordering of bolts and preparation of shop drawings for which it had bid could not have been tasks done “in performance of’ the subcontract because the subcontract did not exist until it was executed by Great West in January 2002, by which time WSS was licensed.
(ii) Licensure required to prepare drawings and order materials.
WSS also argues, and the trial court agreed, the drafting of shop drawings and ordering of anchor bolts was not work performed under the contract, but prefatory tasks for which the corporation was not required to be licensed. WSS is mistaken.
WSS prepared shop drawings detailing the steel work it intended to perform on the project and specifying “how [it was] going to build the canopies,” and submitted those drawings to the project architects and engineers for approval. A contractor includes one who, like WSS, “offers to undertake ... or purports to have the capacity ... or submits a bid” to do specific acts defined by statute as work engaged in by a contractor, including the construction, alteration or repair of any part of any building, structure or project. (§ 7026.) Shop plans constitute such an offer or bid. Through them WSS purported to possess the capacity to undertake the steel work and construction it proposed to perform on the project within the meaning of section 7026, and thus was acting as a contractor. WSS was required to possess a contractor’s license when it submitted its shop plans specifying the scope of the structural steel construction it intended to perform on a public works project. (See §§ 6737.3 [exempting licensed contractors from requirements applicable to civil engineers for, among other things, designing structures for work the contractor is to perform and supervise, in accordance with construction industry standards and codes and within his or her license classification, and for the preparation of shop or field drawings for work he or she has contracted to perform], 6731 [defining scope of civil engineering].) The public has a right to expect the party designing such plans—the improper implementation of which could have serious consequences at a school for deaf children—will, at a minimum, have the qualifications required and to possess a valid contractor’s license.
The same logic negates WSS’s assertion it was not required to be licensed to order materials meant to be incorporated
Because WSS was unlicensed during a period in which it performed work under the contract for which a contractor’s license is required, it is barred from any recovery unless it can bring itself within the statutory exception for substantial compliance, an issue to which we now turn.
b. WSS has not made a sufficient showing of substantial compliance; it was not licensed before December 21, 2001, and may not rely on the license history of another individual or entity.
WSS contends it substantially complied with the licensing requirements because, as the corporation’s RMO, Ramirez previously qualified a WSS partnership for a contractor’s license and held various individual contractor licenses of his own at all times before and after the corporation obtained its license.
8
WSS has not made a sufficient showing of substantial compliance. The contract at issue was between Great West and WSS, the corporation, the entity which bid the project and the only entity to have performed work for which recovery was sought in this action, not WSS, the partnership or Ramirez as an individual. WSS was incorporated for
Nor is the fact that Ramirez was the qualifier for the partnership, an unrelated entity, relevant to the corporation’s license history. WSS’s reliance on
Asdourian
v.
Araj
(1985)
In
Asdourian,
a contractor failed to obtain a license in his own name. He had planned to conduct business as a sole proprietor under a fictitious name, and obtained a license in that name. Because he lacked a license, the plaintiff was out of compliance with the law. If strict compliance with
The court traced the judicial doctrine of substantial compliance back to its earlier decisions,
Gatti v. Highland Park Builders, Inc.
(1946)
However,
Asdourian, Gatti,
and
Latipac
are no longer the law. In 1989, the Legislature added subdivision (d) (now subdivision (e)) to
WSS, the corporate entity or “person” engaged in the business, which acted in the capacity of contractor, does not and cannot argue
it
was ever licensed as a contractor or held that status at a time that preceded its performance in this case. The substantial compliance doctrine is unavailable to a contractor who has not been duly licensed at some point before beginning performance of the contract.
(MW Erectors, supra,
We are cognizant of the harshness of this result. But the law is clear. If the bar of
3. Remaining issues not reached.
In view of the discussion above, it is unnecessary to address whether WSS acted in good faith, whether the court erred in permitting WSS’s expert to testify as to certain matters, whether the damages award was excessive, or any other issues.
DISPOSITION
The judgment is reversed. The matter is remanded with instructions to the trial court to vacate the judgment and enter judgment in favor of Great West and Fidelity. Great West and Fidelity shall recover their costs in this proceeding. (
Rubin, J., and Flier, J., concurred.
Notes
Our factual recitation and discussion are limited to the dispositive issue of licensure.
The interests of Great West and Fidelity are aligned on appeal. Thus, for the sake of brevity, we will refer to appellants collectively as Great West.
Initially, this litigation involved Great West and its sureties on four separate construction projects. Settlements were reached as to all projects except the Middle School for the Deaf.
A portion of Great West’s motion to vacate the judgment was granted on grounds not relevant here.
We decline WSS’s invitation to ignore the licensure argument because the issue was not raised until the middle of trial. As required by statute, the issue was fully vetted at a special evidentiary hearing. Moreover, the defense of illegality under
In its bid, WSS proposed to perform the following services:
“1. Fabricate and Install Canopies 1, 2, 3, 4, 5, 6, 7;
“2. Qty. 7 Canopies to be Galvanized;
“3. Anchor Bolts with Templates F.O.B.;
“4. 4x4x3/16 T.S. Columns with Grey Primer;
“5. Qty. 3 Roof Access Ladders;
“6. 4"x6"xl5 lbs per ft. Galv. Chain;
“7. Shop Drawings.”
Great West argues convincingly that it was not possible for all the work WSS invoiced on December 25, 2001, to have been done between the date WSS received its license and year end. That is because, according to Ramirez, it can take five days to several weeks to galvanize steel, depending on the time of year. Galvanization and fabrication of steel are independent processes. WSS does not do the galvanization; it hires a third party vendor to perform that process, which must be done before WSS can fabricate the steel. WSS was closed for business on December 25, 2001. There were only four business days between the time the license was issued on December 21 and December 31, 2001, during which time WSS claimed it purchased these materials and had them galvanized. Great West asserts that, if WSS actually waited until its license issued to order and have the steel galvanized, there was insufficient time for it to have completed the work invoiced on December 25, and logic dictates some tasks invoiced that date were performed prior to licensure. WSS insists the tasks for which Great West was billed on December 25 were performed after it received its license. This dispute is immaterial; if WSS was not licensed at all relevant times, it may not recover for any work it performed under the contract if the work required licensure, unless it can avail itself of the statutory substantial compliance exception. Leaving the third invoice aside, there is no dispute WSS performed work (prepared shop drawings and ordered materials) prior to December 21, 2001. The only question is whether a license was required to perform those tasks.
Ramirez was the qualifier for licenses issued to a WSS Partnership and its predecessor partnership, RAM Welding. When WSS, the corporation, was formed in 1999, Ramirez was informed by the Board he was not eligible to qualify for a license for the corporation without first disassociating from WSS partnership, which he did. Ramirez also held valid individual licenses. Ramirez’s individual licenses and the WSS partnership’s license were in effect when the corporation bid the project in August 2001. Ramirez submitted a notice of disassociation to the Board in mid-November 2001, with an effective date of December 1, 2001. WSS contends it acted in good faith and substantially complied with
A license number may be reissued or reassigned to a corporation under limited circumstances, none of which obtain here. (See § 7075.1, subd. (c)(1), (3) & (4).)