The plaintiff brought this action to recover damages for personal injuries alleged to have been sustained by him when a ditch in which he was working caved in on him. The jury returned a verdict for the plaintiff, and from the judgment rendered thereon the defendant has appealed.
The plaintiff claimed to have proved the following facts: On April 1, 1964, the plaintiff was an employee of Hirsch Brothers, Inc., hereinafter referred to as Hirsch, which had contracted with Wykeham Rise School for Girls to construct and repair buildings on the school property. Hirsch hired the plaintiff in September, 1963, and assigned him to the Wykeham Rise School job in October, 1963. His duties included helping with demolition, form work and footings, and assisting electricians and plumbers.
Hirsch subcontracted to the defendant the excavation work on the Wykeham Rise School job. The defendant commenced that work late in the fall of 1963, using its own equipment. The work included digging and backfilling a trench from the school’s *148 dormitory to the administration building, a distance of 200 to 300 feet, for the purpose of laying conduits and a water main between the two buildings. The defendant’s work did not include the actual laying of the conduits and water main. The agreement between Hirsch and the defendant was that, if in the opinion of the defendant supports or shoring was needed to brace the sides of the ditch in question, the defendant was to notify Hirsch of the need, and Hirsch would then have its carpenters instal the shoring and supports necessary.
On April 1,1964, Frank Rinaldi, a backhoe operator employed by the defendant, commenced digging the ditch. He dug a section approximately thirty feet long, seven feet wide at the top and four and one-half feet deep. After this section of the ditch was dug, the plaintiff and three other Hirsch employees placed conduits in it, fastened them together and pulled the necessary wires through the conduits. While they were so engaged, Rinaldi did not operate the backhoe. After the plaintiff and the other Hirsch employees completed their work, Rinaldi dug a second thirty-foot section, and the plaintiff and the other Hirsch employees performed the same work as they had done in the first section. After the Hirsch employees completed their work in the second section, Rinaldi dug a third thirty-foot section, which was about six feet deep. The surface of the ground adjacent to each side of the third section was damp, muddy and sloppy, water seeped into the ditch from its sides, and the floor of the ditch was muddy and contained water. Theodore J. Anderson, the defendant’s supervisor, saw the third section of the trench and directed Rinaldi to dig a lateral trench leading out of the third section in order to drain the water from it.
*149 The plaintiff and the other Hirsch employees finished their work in the third section at noontime and stopped for lnnch. They returned at 12:30 p.m. and entered a fourth section which had been excavated by Rinaldi. This section was approximately six feet deep, water was seeping through the sides, and the floor was wet and muddy. While the plaintiff was in this section of the ditch, a side of it caved in, causing him the injuries which are the basis of this action. At the time of the accident, Rinaldi was sitting on the backhoe, which was not in operation, about thirty to forty feet from the plaintiff.
The defendant has assigned as error the refusal of the court to include certain claims of proof in the finding. A finding in a case tried to the jury is merely a narrative of the facts claimed to have been proved by each side, made for the purpose of fairly presenting any claimed errors in the charge or rulings of the court.
Morgillo
v.
Evergreen Cemetery Assn.,
The finding as corrected discloses that the defendant claimed to have proved the following facts: The digging by the defendant was to be done under the supervision of Hirsch. The defendant was *150 expected to live up to the specifications in the contract between Hirsch and the trustees of Wykeham Rise School. The defendant had no authority to order Hirsch employees to do or not to do anything. Shoring was not included in the term “excavation work” as used by Hirsch. There was no arrangement with the defendant on shoring, and the defendant was not obligated to give notice of any need for shoring. If shoring had been ordered, Hirsch employees would have installed it. William L. Hirsch came to the ditch at different times during the day and inquired as to its progress. He was in the ditch ten minutes before the accident, and, although he noted it was muddy, he made no observations as to its safety. Rinaldi gave no orders or instructions to the plaintiff or to other Hirsch employees. Although the plaintiff knew before he entered the ditch that it was muddy and that water was seeping out of the ground, he never requested that the ditch be shored nor discussed shoring on April 1, 1964. During the morning, minor sections of the ditch walls had caved in. The cave-in which injured the plaintiff involved a section of earth four or five inches wide and three or four feet in length.
In addition to the assignment of error in the finding, the defendant assigns error in the refusal of the court to set aside the verdict, in rulings on evidence, in the refusal to charge as requested, in the charge as given, in granting the plaintiff’s motion to amend his complaint, and in denying the defendant’s motion to amend its answer by adding a third special defense.
The principal claim of the defendant is that it is not liable for the plaintiff’s injuries because at the time they occurred Hirsch, and not the defendant, was in control of the ditch where the cave-in took
*151
place. The established general rule is that where the owner of premises employs an independent contractor to perform work upon them, the contractor, and not the owner, is liable for any losses resulting from negligence in the performance of the work until such time as it has been completed, turned over to and accepted by the owner.
Trainor
v.
Frank Mercede & Sons, Inc.,
The court charged the jury on the issues involved in the case, and the defendant took two exceptions to the charge as given by the court. The defendant assigns error in other portions of the charge, but we will consider only the portions to which exceptions were taken. The defendant’s first exception was directed to the portion of the charge dealing with the foreseeability that harm may result if reasonable care is not exercised. In this respect the court charged the jury as follows: “The ultimate test of the existence of a duty to use care is found
*152
in the foreseeability that harm may result if it is not exercised. The test is: would the ordinary man, in the defendant’s position, knowing what it knew or should have known, anticipate that harm of the general nature of that suffered by the plaintiff was likely to result unless reasonable care was taken.” This is a correct statement of the law.
Petrizzo
v.
Commercial Contractors Corporation,
The defendant’s second exception to the charge was based on, and limited to, the claim that the court instructed the jury that as a matter of law the defendant was in charge of the ditch and thus in control of it. After the exception was taken, the court recalled the jury and instructed it that it was for the jury to determine whether the defendant was in fact in charge of the excavation of the ditch. The defendant’s attorney then stated that he had
*153
no exception to the charge then given by the court, but he preserved his other exception to the charge relative to duty and foreseeability. Under the circumstances, the defendant may not on this appeal claim error based on the correctness of the court’s charge on the question of control of the ditch. Practice Book §§ 249, 652;
Vivenzio
v. Heller,
The defendant assigns error in the refusal of the court to charge the jury in accordance with three requests to charge. Each of the first two requests was based on the assumption that all duties in regard to shoring were either on Hirsch or on the defendant. Neither request took into account the plaintiff’s claim that the duties as to shoring were divided between Hirsch and the defendant, so that, although Hirsch was responsible for the actual construction of shoring, the defendant was obligated to notify Hirsch whenever in its opinion shoring was needed. Thus, both requests were inadequate, and the court did not err in refusing to charge in accordance with them.
The defendant’s third request was that the court charge the jury that the defendant would not be liable for the absence of shoring unless the defendant, and not Hirsch, was in control of the ditch at the time of the accident. The request did not take into account the claim of the plaintiff that the agreement between the defendant and Hirsch was to the effect that if, in the defendant’s opinion, supports or shoring was needed to brace the sides of the ditch, the defendant was to notify Hirsch of the need, and Hirsch would then instal the shoring and supports. Furthermore, this request was based on the assumption that either Hirsch or the defendant was in con
*154
trol of the ditch to the exclusion of the other at the time of the accident. To be entitled to recover, it was not necessary for the plaintiff to prove that the defendant was in control of the ditch to the exclusion of Hirsch. The defendant is liable to the plaintiff for negligence if the trier finds either that the defendant alone was in control of the ditch or that the defendant and Hirsch were both in control of it.
Kaplan
v.
Merberg Wrecking Corporation,
The defendant assigns error in certain rulings on the admissibility of evidence. The defendant sought to introduce into evidence the contract between the school and Hirsch. The defendant claimed that the terms of that contract controlled the obligations between Hirsch and its subcontractors. The court excluded the contract. The controlling contract was the one entered into between Hirsch and the defendant. There was no dispute concerning the terms of this contract except as to whether the agreement between Hirsch and the defendant was to the effect that, if in the defendant’s opinion supports or shoring was needed to brace the sides of the trench, the defendant would notify Hirsch of this need, and Hirsch would then instal the necessary shoring and supports. Nor was there any dispute as to whether the defendant was doing the work in accordance with the specifications of the contract between *155 Hirsch and the school. The court did not err in excluding the contract.
The other assigned error in the admissibility of evidence was the court’s action in sustaining objections to questions asked of Howard Schiffres, a witness for the plaintiff, designed to elicit information as to shoring which was constructed in the trench after the accident. The defendant claimed that the evidence was admissible to establish who was in control of the ditch, under the rule of cases such as
Williams
v.
Milner Hotels Co.,
The defendant assigns error in the allowance of an amendment to the complaint by the plaintiff during the trial and in the refusal of the court to permit the defendant to amend its answer to allege a third special defense. Under the statutes and rules of practice, the court may in its discretion, in a proper case, allow the filing of amendments to pleadings before, during and after trial. General Statutes § 52-130; Practice Book §§ 132, 134;
Thibault
v.
Frechette,
Finally, we consider the defendant’s claim that the verdict is not supported by the evidence. This claim is tested by the evidence set forth in the appendices to the briefs.
Lucier
v.
Meriden-Wallingford Sand & Stone Co.,
There is no error.
In this opinion the other judges concurred.
