Wright v. Coe & Anderson, Inc.Wright v. Coe & Anderson, Inc.
- Reporters:
- , ,
- Before:
- Covello
The plaintiff brought this action to recover damages for personal injuries alleged to have been sustained by him when a ditch in which he was working caved in on him. The jury returned a verdict for the plaintiff, and from the judgment rendered thereon the defendant has appealed.
The plaintiff claimed to have proved the following facts: On April 1, 1964, the plaintiff was an employee of Hirsch Brothers, Inc., hereinafter referred to as Hirsch, which had contracted with Wykeham Rise School for Girls to construct and repair buildings on the school property. Hirsch hired the plaintiff in September, 1963, and assigned him to the Wykeham Rise School job in October, 1963. His duties included helping with demolition, form work and footings, and assisting electricians and plumbers.
Hirsch subcontracted to the defendant the excavation work on the Wykeham Rise School job. The defendant commenced that work late in the fall of 1963, using its own equipment. The work included digging and backfilling a trench from the school’s
On April 1,1964, Frank Rinaldi, a backhoe operator employed by the defendant, commenced digging the ditch. He dug a section approximately thirty feet long, seven feet wide at the top and four and one-half feet deep. After this section of the ditch was dug, the plaintiff and three other Hirsch employees placed conduits in it, fastened them together and pulled the necessary wires through the conduits. While they were so engaged, Rinaldi did not operate the backhoe. After the plaintiff and the other Hirsch employees completed their work, Rinaldi dug a second thirty-foot section, and the plaintiff and the other Hirsch employees performed the same work as they had done in the first section. After the Hirsch employees completed their work in the second section, Rinaldi dug a third thirty-foot section, which was about six feet deep. The surface of the ground adjacent to each side of the third section was damp, muddy and sloppy, water seeped into the ditch from its sides, and the floor of the ditch was muddy and contained water. Theodore J. Anderson, the defendant’s supervisor, saw the third section of the trench and directed Rinaldi to dig a lateral trench leading out of the third section in order to drain the water from it.
The defendant has assigned as error the refusal of the court to include certain claims of proof in the finding. A finding in a case tried to the jury is merely a narrative of the facts claimed to have been proved by each side, made for the purpose of fairly presenting any claimed errors in the charge or rulings of the court. Morgillo v. Evergreen Cemetery Assn., 152 Conn. 169, 172, 205 A.2d 368; State v. Whiteside, 148 Conn. 208, 214, 169 A.2d 260, cert. denied, 368 U.S. 830, 82 S. Ct. 52, 7 L. Ed. 2d 33. Where a party seeks additions to its own claims of proof in a case tried to the jury, the additions should he made if they are material and are supported by the evidence. Phoenix Mutual Life Ins. Co. v. Brenckman, 148 Conn. 391, 394, 171 A.2d 194. The finding is accordingly corrected by adding to it certain facts from the defendant’s draft finding which we have included in our following statement of the defendant’s claims of proof.
The finding as corrected discloses that the defendant claimed to have proved the following facts: The digging by the defendant was to be done under the supervision of Hirsch. The defendant was
In addition to the assignment of error in the finding, the defendant assigns error in the refusal of the court to set aside the verdict, in rulings on evidence, in the refusal to charge as requested, in the charge as given, in granting the plaintiff’s motion to amend his complaint, and in denying the defendant’s motion to amend its answer by adding a third special defense.
The principal claim of the defendant is that it is not liable for the plaintiff’s injuries because at the time they occurred Hirsch, and not the defendant, was in control of the ditch where the cave-in took
The court charged the jury on the issues involved in the case, and the defendant took two exceptions to the charge as given by the court. The defendant assigns error in other portions of the charge, but we will consider only the portions to which exceptions were taken. The defendant’s first exception was directed to the portion of the charge dealing with the foreseeability that harm may result if reasonable care is not exercised. In this respect the court charged the jury as follows: “The ultimate test of the existence of a duty to use care is found
The defendant’s second exception to the charge was based on, and limited to, the claim that the court instructed the jury that as a matter of law the defendant was in charge of the ditch and thus in control of it. After the exception was taken, the court recalled the jury and instructed it that it was for the jury to determine whether the defendant was in fact in charge of the excavation of the ditch. The defendant’s attorney then stated that he had
The defendant assigns error in the refusal of the court to charge the jury in accordance with three requests to charge. Each of the first two requests was based on the assumption that all duties in regard to shoring were either on Hirsch or on the defendant. Neither request took into account the plaintiff’s claim that the duties as to shoring were divided between Hirsch and the defendant, so that, although Hirsch was responsible for the actual construction of shoring, the defendant was obligated to notify Hirsch whenever in its opinion shoring was needed. Thus, both requests were inadequate, and the court did not err in refusing to charge in accordance with them.
The defendant’s third request was that the court charge the jury that the defendant would not be liable for the absence of shoring unless the defendant, and not Hirsch, was in control of the ditch at the time of the accident. The request did not take into account the claim of the plaintiff that the agreement between the defendant and Hirsch was to the effect that if, in the defendant’s opinion, supports or shoring was needed to brace the sides of the ditch, the defendant was to notify Hirsch of the need, and Hirsch would then instal the shoring and supports. Furthermore, this request was based on the assumption that either Hirsch or the defendant was in con
The defendant assigns error in certain rulings on the admissibility of evidence. The defendant sought to introduce into evidence the contract between the school and Hirsch. The defendant claimed that the terms of that contract controlled the obligations between Hirsch and its subcontractors. The court excluded the contract. The controlling contract was the one entered into between Hirsch and the defendant. There was no dispute concerning the terms of this contract except as to whether the agreement between Hirsch and the defendant was to the effect that, if in the defendant’s opinion supports or shoring was needed to brace the sides of the trench, the defendant would notify Hirsch of this need, and Hirsch would then instal the necessary shoring and supports. Nor was there any dispute as to whether the defendant was doing the work in accordance with the specifications of the contract between
The other assigned error in the admissibility of evidence was the court’s action in sustaining objections to questions asked of Howard Schiffres, a witness for the plaintiff, designed to elicit information as to shoring which was constructed in the trench after the accident. The defendant claimed that the evidence was admissible to establish who was in control of the ditch, under the rule of cases such as Williams v. Milner Hotels Co., 130 Conn. 507, 510, 36 A.2d 20, which hold that evidence of repairs is admissible for the purpose of proving control. In the present case, the question is who was in control of the ditch at the time of the cave-in. The plaintiff and the defendant both agree that Hirsch was obligated to instal shoring whenever it was needed. Consequently, the fact that Hirsch installed shoring after the accident would have no probative value on the question of control of the ditch at the time of the cave-in, as Hirsch did what both the plaintiff and the defendant concede Hirsch was required to do in the execution of the contract with the defendant. The court properly sustained the objections to the questions.
The defendant assigns error in the allowance of an amendment to the complaint by the plaintiff during the trial and in the refusal of the court to permit the defendant to amend its answer to allege a third special defense. Under the statutes and rules of practice, the court may in its discretion, in a proper case, allow the filing of amendments to pleadings before, during and after trial.
Finally, we consider the defendant’s claim that the verdict is not supported by the evidence. This claim is tested by the evidence set forth in the appendices to the briefs.
Lucier
v.
Meriden-Wallingford Sand & Stone Co.,
153 Conn. 422, 427, 216 A.2d 818. There was evidence from which the jury could have found the following facts: The defendant was employed as a subcontractor to dig
There is no error.
In this opinion the other judges concurred.