Opinion
Appellants Ronald I. Cooper and Ellen M. Cooper challenge summary judgment in favor of respondent WRI Opportunity Loans II, LLC (WRIO), in its action for payment of a loan guaranteed by appellants. We reverse.
FACTUAL AND PROCEDURAL BACKGROUND
There are no material disputes about the following facts: In 1999, the Coopers were the sole principals in Cooper Commons, LLC (CC), which planned to build residential townhouses and condominiums on a property in West Hollywood. 1 According to the budget for the project, the property was purchased for $5,979,066, and CC expected that the units, when completed, would sell for a total of $25,762,005. The senior and junior secured lenders on the project were, respectively, Comerica Bank—California (Comerica) and WRIO.
In November 1999, WRIO loaned $2,490,000 to CC. Under the loan documents, the loan matured in March 2002, and interest on the principal balance accruеd at a rate equal to 2.0 percent above a reference rate set by the Bank of America (reference rate). The loan documents also contained provisions that accorded WRIO “additional interest.” These provisions entitled WRIO to 4.0 percent of the gross sales price of each unit when it was sold to third parties not affiliated with CC; in addition, they awarded WRIO sums calculated according to a fixed schedule if other contingencies were to occur. By a written agreement, the Coopers personally guaranteed the performance of CC’s obligations under the loan documents.
In June and December 2001, WRIO and CC amended the loan documents. The amendments increased the principal loan amount to $3,178,000, raised the interest rate to the greater of (i) 2.0 percent above the reference rate or (ii) 10.0 percent, and sеt the maturity date of the loan as June 12, 2002. In addition, the amendments increased the additional interest owed to WRIO upon sale of the units to nonaffiliated parties: WRIO’s share of the gross sales price of the first 15 units to be sold was raised to 5.0 percent, and its share of the gross sales price of the remaining units was raised to 4.5 percent. The Coopers expressly approved these amendments,
On February 22, 2002, CC filed for bankruptcy under chapter 11, and subsequently stated in that proceeding that WRIO held a secured claim for $3,178,000. No payment on WRIO’s loan was made after the maturity date of June 12, 2002. In September 2002, the bankruptcy court authorized CC to obtain additional funding from Comerica to complete the construction of the project. The units in the project were completed and sold for a total of approximately $31.8 million. On March 2, 2005, WRIO demanded that the Coopers, аs CC’s guarantors, pay the amounts owed under the loan, but they did not respond.
On March 14, 2005, WRIO filed a complaint for breach of a written guaranty against the Coopers, and subsequently sought summary judgment, asserting that the Coopers were obliged to pay the principal and interest— including the so-called additional interest—that CC owed under the loan. When the Coopers opposed summary judgment on the ground that the loan was usurious, WRIO contended in its reply that the Coopers had waived a usury defense, and that the loan otherwise fell within an exemption to California usury law for shared appreciation loans (Civ. Code, § 1917 et seq.). 2 After file parties submitted additional briefing on the issues raised in WRIO’s reply, the trial court granted summary judgment. On March 29, 2006, a judgment was entered awarding WRIO $6,634,300.82 plus additional accrued interest and costs.
DISCUSSION
The Coopers contend the trial court erred in granting summary judgment. We agree.
A. Standard of Review
“On appeal after a motion for summary judgment has been granted, we review the record de novo, considering all the evidence set forth in the moving and opposition papers except that to which objections have been made and sustained. [Citation.]”
(Guz
v.
Bechtel National, Inc.
(2000)
“[Sjummary judgment law in this state no longer requires a plaintiff moving for summary judgment to disprove any defense asserted by the
defendant as well as prove each element of his own cause of action. . . . All that the plaintiff need do is to ‘prove[] each element of the cаuse of action.’ [Citation.]”
(Aguilar v. Atlantic Richfield Co.
(2001)
Aside from challenging one item of interest valued at $19,014.45, the Coopers do not contend on appeal that WRIO failed to carry its initial burden on summary judgment. Their central contention is that there are triable issues as to their usury defense. Before the trial court, they pointed to WRIO’s investment analysis for
In view of the Coopers’ factual showing regarding usury, we conclude they raised triable issues regarding the existence of a usury defense unless—as the trial court determined—the defense fails as a matter of law. Because neither party submitted extrinsic evidence bearing on the meaning of the loan documents and the pertinent historical facts regarding the loan are undisputed, the interpretation of the loan’s provisions and its status as a shared appreciation loan are questions of law that we resolve de novo.
(Parsons v. Bristol Development Co.
(1965)
B. Usury
1. Elements
Generally, “[t]he California Constitution sets a maximum annual interest rate of seven percent on loans and forbearances, but allows parties by written contract to set the interest rate at up to 10 percent, or at the level of the Federal Reserve’s discount rate plus 5 percent, on loans or forebearances involving real property. (Cal. Const., art. XV, § 1, subds. (l)-(2).)”
4
(Jones
v.
Wells Fargo Bank
(2003)
As our Supreme Court has explained, “[t]he element of intent is narrow. ‘[T]he intent sufficient to support the judgment [of usury] does not require a conscious attempt, with knowledge of the law, to evade it. The conscious and voluntary taking of more than the legal rate of interest constitutes usury and the only intent necessary on the part of the lender is to take the amount of interest which he receives; if that amount is more than the law allows, the offense is complete.’ [Citation.] Intent is relevant, however, in determining the true purpose of the transaction in question because ‘. . . the trier of fact must look to the substance of the transaction rather than to its form. . . . “[I]t is for the trier of the fact to determine whether the intent of the contracting parties was that disclosed by the form adopted, or whether such form was a mere sham and subterfuge to cover up a usurious transaction.” ’ [Citation.]”
(Ghirardo v. Antonioli, supra,
2. Interest Contingency Rule
The usury law is subject to numerous exceptions аnd statutory exemptions.
(Southwest Concrete Products
v.
Gosh Construction Corp.
(1990)
According to this rule, a loan that will “ ‘give the creditor a greater profit than the highest permissible rate of interest upon the occurrence of a condition ... is not usurious if the repayment promised on failure of the condition to occur is materially less than the amount of the loan . . . with the highest permissible interest, unless a transaction is given this form as a colorable device to obtain a greater profit than is permissible.”
(Thomassen, supra,
Instructive applications of the rule are found in
Schiff v. Pruitt
(1956)
In Thomassen, the lender agreed to loan $18,500 for an 18-month period to a developer to enable him to build an office building. (Thomassen, supra, 250 Cal.App.2d at pp. 343-344.) In lieu of a fixed rate of interest on the principal, the developer agreed to pay the lender 30 percent of the net profit from the sale of the building and 30 percent of the building’s gross income from rentals prior to its sale. (Id. at p. 344.) The Court of Appeal concluded that the loan was not usurious, pointing to the risks undertaken by the lender in connection with its profits under the loan. (Id. at pp. 346-349.)
Under the interest contingency rule, courts “look to the substancе rather than to the form” of the transaction to determine whether the lender’s profits are exposed to the requisite risk.
(Thomassen, supra,
Moreover, courts have looked beyond the face of the agreement to assess whether the lender’s profits are subject to risk. In
Teichner
v.
Klassman
(1966)
Closely relatеd to the interest contingency rule is the statutory exemption to the usury law for shared appreciation loans. (See
Jones, supra,
In
Jones,
this court discussed the relationship between the exemption for shared appreciation loans and the interest contingency rule. There, a partnership obtained a loan for $1.7 million to purchase real property.
(Jones, supra,
In so concluding, we rejected the partner’s contention that the transaction constituted a “ ‘sham’ ” shared appreciation loan because the property’s rapid appreciation ensured that “the lender’s profits were never at risk.”
(Jones, supra,
C. Additional Interest Provisions
In view of
Jones,
the focus of our inquiry is whether WRIO’s loan meets the statutory requirements for a shared appreciation loan. We therefore
examine its terms to determine the circumstances under which they accorded additional interest
The loan agreement obliged CC to pay additional interest in connection with each proposed unit, payable upon the sale of the unit, “or in any event upon the Maturity Date.” 5 The additional interest for each unit was calculated according to a schedule that contained provisions covering various contingencies. The schedule (as amended by the parties) assigned each unit a “Budgeted Gross Sales Price” falling in a range from $420,000 to $555,895, and addressed three key contingencies: (1) the unit, whether completed or under construction, was sold to a third party not affiliated with CC; (2) the unit, whether completed or under construction, was sold to an affiliate of CC or released due to payment of the loan; and (3) no construction of the unit had been undertaken when the loan matured or the underlying property was sold. 6
In the case of the first cоntingency, WRIO was entitled to 5.0 percent of the gross sales price if the unit was among the first 15 sold, and 4.5 percent of the gross sales price otherwise. In the case of the second contingency, WRIO was entitled to the greater of (i) 4.5 percent of the actual gross sales price or (ii) 4.5 percent of the unit’s budgeted gross sales price.
7
Finally, in
the case of the third contingency, WRIO was entitled to the difference between $1,376,290 and the sum of the additional interest WRIO received under the provisions for the other contingencies.
8
In effect, the provision regarding
The schedule thus ensured WRIO a significant amount of additional interest in a wide range of circumstances, regardless of the success of the project. If CC undertook no construction on the project, the prоvision for the third contingency entitled WRIO to $1,376,290 in additional interest upon the loan’s maturity date; if CC began construction but failed to complete the project, the provisions for the first and second contingencies entitled WRIO to at least 4.5 percent of the actual or budgeted gross sales price, depending upon whether the buyers of the partially completed units were affiliated with CC; finally, if CC completed the project as planned, the provision for the first contingency entitled WRIO to at least 4.5 percent of the total gross income from the sales of the units. It appears that the schedule denied additional interest to WRIO in only one circumstance of any consequence, namely, that CC began construction on the units and thereafter failed to sell them to anyone.
The remaining question is whether the schedule accords WRIO “contingent deferred interest” within the meaning of the statutory scheme governing shared appreciation loans. In resolving this issue of statutory interpretation, our objective “is to ascertain and effectuate legislative intent. To accomplish that objective, courts must look first to the words of the statute, giving effect to their plain meaning. If those words are clear, we may not alter them to accomplish a purpose that does not appear on the face of the statute or from its legislative history. [Citation.]”
(In re Jerry R.
(1994)
In our view, the schedule cannot be construed as entitling WRIO to “contingent deferred interest,” that is, “a share of (1) the appreciation in the value of the security property (2) rents and profits attributable to the subject property, or (3) both.” (§ 1917, subd. (a).) The provisions in the schedule, on their face, guaranteed WRIO additional interest regardless of whether the underlying property aрpreciated in value, or whether the project generated rents or profits. If the property did not appreciate in value from its original purchase price of approximately $6,000,000—for example, because the project collapsed during a downturn in the real estate market, or resulted in defective or otherwise unmarketable units that required demolition—the schedule accorded WRIO additional interest ranging from 4.5 percent of the gross sales price of the property to $1,376,290. For the same reasons, if the property’s appreciation was modest, the additional interest to which WRIO was entitled under the schedule could exceed the appreciation. Moreover, the schedule awarded WRIO $1,376,290 in additional interest even if no construction was undertaken on the project.
WRIO contends that additional interest pursuant to the schedule constitutes contingent deferred interest under the statutory scheme, even though the schedule
As interpreted by WRIO, the statutory definition of a shared appreciation loan encompasses any loan secured by real property—including a loan that guarantees the lender an otherwise usurious rate of interest—as long as the loan also contains a provision entitling the lender to a share of appreciation arising from the property. WRIO’s interpretation would effectively abrogate the usury law with respect to loans secured by real property by sanctioning usurious rates of interest that were guaranteed, even in the absence of appreciation or risk.
WRIO’s construction cannot be reconciled with the language of the statutory scheme and the Legislature’s evident purpose in enacting it. The provision exempting shared appreciation loans from the usury law states that the exemption “is declaratory of existing law.” (§ 1917.005.) In view of this statement, the Legislature’s apparent intent in creating the exemption was to clarify the application of the interest contingency rule in a defined set of circumstances, rather than to abrogate the rule. 9 Under the rule, a lender may obtain payments on a loan that exceed the maximum interest rate set by the usury law, provided that these payments are subject to risk. (Thomassen, supra, 250 Cal.App.2d at pp. 346-349.) Accordingly, the statutory definition of a shared appreciation loan must be understood to permit a lender to obtain guaranteed interest payments up to the maximum rate permitted under the usury law, and additionally, payments of contingent deferred interest that are subject to risk.
As indicated above (see pt. B.2.,
ante),
the interest contingency rule permits courts to look beyond the face of a transaction to determine whether the underlying transaction exposed the lender’s ostensibly contingent profits to genuine risk; as we explained in
Jones,
the function of statutory exemptions generally is to curtail this kind of inquiry into the underlying transaction
(Jones, supra,
We also reject WRIO’s contention that the loan terms awarding additional interest based up the actual gross sales price of the units are provisions for the sharing of appreciation under the statutory scheme. WRIO argues that the project, realistically viewed, was likely to cause substantial appreciation in the property’s value, and the appreciation was likely to exceed the payments to WRIO under the terms in question. WRIO thus contends that the terms effectively allocated WRIO a share of the appreciation.
We find this argument to be at odds with the legislative intent underlying the exemption. As we have explained, the statutory scheme authorizes an exception to the usury law founded on the interest contingency rule. Generally, exceptions to a statute are construed narrowly to cover only situations that are “within the words and reason of the exception.”
(Hayter Trucking, Inc.
v.
Shell Western E&P, Inc.
(1993)
D. Waiver
WRIO contends that summary judgment in its favor is properly affirmed on an alternative ground, namely, that the Coopers expressly waived their entitlement to assert a usury defense.
12
Pertinent to this contention are sections 2809 and 2810, which fall within title XIII of the Civil Code (§§ 2787-2856), which abolishes the distinction between sureties and guarantors (§ 2787), and otherwise defines
Here, the written guaranty executed by the Coopers states: “Guarantor . . . waives any rights, claims, defense, abatements, or rights of setoff or recoupment based on or arising based on or arising out of: (1) any legal disability, discharge, or limitation of the liability of Borrower to Lender, whether consensual or arising by operation of law or any proceeding . . . .” Moreover, it states: “Guarantor affirms its intention to waive all benefits that might otherwise be available to Guarantor or Borrower under . . . Civil Code Sections 2809, 2810 ..., among others.” The Coopers do not dispute that the guaranty contains these provisions.
The issue thus presented is whether the Coopers’ waiver encompassed their usury defense. In
Rochester Capital Leasing Corp. v. K & L Litho Corp.
(1970)
The usurious provisions of a loan are void on the grounds of illegality or unlawfulness because they violate express provisions of law.
(Martin
v.
Ajax Construction Co., supra,
Thus, in
Hollywood State Bk.
v.
Wilde
(1945)
In
Wells v. Comstock
(1956)
The court in
Wells
further held that “[s]ince the principal obligation of the contract is unenforceable because of illegality, the guaranty too is unenforceable.”
(Wells v. Comstock, supra,
In view of
Wells
and the other authority regarding rule against the enforcement of unlawful transactions, we conclude that the Coopers’ waiver of their defenses arising under sections 2809 and 2810 or “by operation of law” was ineffective regarding their usury defense. WRIO nonetheless contends that the Legislature has authorized guarantors to waive a usury defense by enacting subdivision (a)(1) of section 2856 (subdivision (a)(1)), which provides: “(a) Any guarantor or other surety, including a guarantor of a note or other obligation secured by real property or an estate for years, may waive any or all of the following: [f] (1) The guarantor or other surety’s rights of subrogation, reimbursement, indemnification, and contribution and
any other rights and defenses that are or may become available to the guarantor or other surety by reason of Sections 2787 to 2855,
inclusive,”
15
(Italics added.)
Pointing to the italicized portion of subdivision (a)(1), WRIO argues that the Coopers’ usury defense is “available to [them] by reason of’ sections 2809 and 2810, and thus their waiver was effective rеgarding this defense. We disagree. As we have explained, the usury defense rests on the rule against the enforcement of illegal transactions, which is founded on considerations of public policy that are independent of sections 2809 and 2810. Furthermore, an examination of the history of section 2856 discloses that the Legislature did not intend subdivision (a)(1) to displace or modify this rule, insofar as it applies to the waiver of defenses by guarantors.
As originally enacted in 1995, Civil Code section 2856 was the Legislature’s response to
Cathay Bank v. Lee
(1993)
Subdivision (a) of the 1995 statute provided in pertinent part: “Any guarantor, including a guarantor of an obligation secured by real property or any interest therein, may waive the guarantor’s rights of subrogation and reimbursement and any other rights and defenses available to the guarantor by reason of Sections 2787 to 2855, inclusive . . . .” (Former Civ. Code, § 2856, added by Stats. 1994, ch. 1204, § 1, p. 7424, repealed by Stats. 1996, ch. 1013, § 2, pp. 5985-5987, italics added.) The remainder of the 1995 statute addressed the requirements for waivers, including waivers of rights and defenses arising from the antideficiency statutes. (Ibid.) In enacting the 1995 statute, the Legislature stated that subdivision (a) was “merely declarative of . . . existing law.” (Stats. 1994, ch. 1204, § 2, p. 7424.) In 1996, the Legislature enacted the current version of section 2856, which amended the 1995 statute, but preserved the italicized language upon which WRIO relies. (Stats. 1996, ch. 1013, § 2, pp. 5985-5987.)
As the court explained in
River Bank America v. Diller, supra,
E. Conclusion
Because WRIO’s challenges to the Coopers’ usury defense fail as a matter of law on the facts that were undisputed for the purpose of WRIO’s motion for summary judgment, we cannot say there are no triable issues regarding that defense. Accordingly, summary judgment was improper. 17
DISPOSITION
The judgment is reversed. Appellants are awarded their costs.
Epstein, R J., and Willhite, J., concurred.
Notes
CC initially intended to build 63 units, but later decided to build 62 units.
All further statutory citations are to the Civil Code, unless otherwise indicated.
In response to the trial court’s request for supplemental briefing, the Coopers and WRIO submitted declarations from experts who offered conflicting opinions on the undisputed facts as to whether the loan is a shared appreciation loan. These declarations do not raise triable issues as to the proper characterization of the loan. Generally, Evidence Code section 805 permits expert testimony on the ultimate issue to be decided by the fact finder. However, this rule “does not . . . authorize an ‘expert’ to testify to legal conclusions in the guise of expert opinion. Such legal conclusions do not constitute substantial evidence. [Citation.]”
(Downer v. Bramet
(1984)
California’s prohibition on usury is also set forth in an uncodified statute added by an initiative. (Stats. 1919, p. 1xxxiii, reprinted at Deering’s Ann. Uncod. Initiative Measures 1919-1 (1973 ed.) p. 35.)
Paragraph 1.6.4 of the loan agreement provides: “In addition to interest at the applicable rate, Borrower shall pay Lender additional interest (the ‘Additional Interest’) in connection with the release of Lender’s security interest in each Unit comprising the Project. Borrower shall not take any action or make any omission that will result in a reduction of the number of Units to be constructed. The Additional Interest payable with respect to each Unit shall become due upon and shall be paid from the escrow established for the closing of the sale of such Unit, or in any event upon the Maturity Date, a full prepayment of the Loan, or a partial prepayment with respect to which a release of such Unit from the Deed of Trust is requested. Such Additional Interest shall be calculated in accordance with the Unit Schedule . . . .”
The schedule also contains a provision concerning additional interest in connection with the sale of parking stalls and garage units.
Regarding the first two contingencies, the schedule provides: “A.l Units Completed or Under Construction. In the case of individual Units with respect to which construction has been commenced (whether or not the improvements are complete), Borrower shall pay Additional Interest in the following amounts: ffl (a) For the first 15 Units being released in connection with the closing of a sale of such Units to bona fide third parties who are not an Affiliate of Borrower, 5.0% of the gross sales price of each Unit, including any and all lot premiums and buyer-choice options and upgrades; and H] (b) For the remaining Units, after 15 Units have сlosed, being released in connection with the closing of a sale of such Unit to a bona fide third party who is not an Affiliate of Borrower, 4.5% of the gross sales price of the Unit, including any and all lot premiums and buyer-choice options and upgrades; and [f| (c) For any Unit being released in connection with a Loan prepayment, payment of the Loan at maturity or upon acceleration, or sale to an Affiliate of Borrower with Lender’s consent, the greater of (i) 4.5% of the gross sales price of the Unit if such Unit is subject to a ‘Qualifying Sales Contract’ ... on the date of such prepayment, maturity, or acceleration, or (ii) 4.5% of the ‘Budgeted Gross Sales Price’ for such Unit based upon the plan type of the Unit as identified in the Plans, as follows . . . .”
Regarding the third contingency, the schedule provides: “Property other than Condominium or Townhouse Units or Parking Units. Additional interest shall be due with respect to any portion of the Land that is not constructed as a condominium or townhouse Unit upon the sale of such Land or upon the Maturity Date in an amount equal to the difference between $1,376,290 and the sum of (i) the cumulative amount of Additional Interest that Lender has received prior to such time under [the other provisions for Additional Interest], plus (ii) the further amount of the Additional Interest that Lender expects to receive from closings of completed condominium or townhouse Units based on the budgeted sales prices shown in Section A. 1 above.”
The provision containing this statement (§ 1917.005) is derived, in part, from an earlier statutory exemption for a narrowly defined class of shared appreciation loans (see former section 1917.167, added by Stats. 1982, ch. 466, § 12, pp. 1998-2006, repealed by Stats. 1987, ch. 652, § 1, pp. 2061-2062). The prior statutory scheme concerned loans to supply funds for the construction of “owner-occupied dwelling units,” and permitted lenders to obtain up to 50 percent of the “Net appreciate[ion] value” of the units (that is, their “fair market value less the sum of the borrower’s cost of the property and the value of capital improvements”). (Former §§ 1917.120, subds. (c), (f), (j), 1917.130, added by Stats. 1982, ch. 466, § 12, pp. 1998-2006, repealed by Stats. 1987, ch. 652, § 1, pp. 2061-2062). In view of the broad reach of the current exemption, we conclude the Legislature’s statement that it “is declaratory of existing law” manifests an intent to refer beyond the prior statutory exemption to the common law interest contingency rule.
We recognize that to the extent the statutory exemption obviates the need to look beyond the face of the transaction, it may be in tension with the Legislature’s statement that the exemption “is declaratory of existing law” (§ 1917.005). However, such statements by the Lеgislature are properly assessed in light of other evidence bearing on the statute’s meaning.
(Western Security Bank v. Superior Court
(1997)
In view of this conclusion, it is unnecessary to address the Coopers’ contention that the trust deed provided insufficient notice that it secured a shared appreciation loan.
Although WRIO raised this contention in its reply to the Coopers’ opposition to summary judgment and the parties addressed it in their supplementary briefing, the trial court did not rule on it in granting summary judgment. Nonetheless, absent a triable issue of material fact, we may affirm the grant of summary judgment “if it is correct on any theory of law applicable to the case, including but not limited to the theory adopted by the trial court. [Citations.]”
(Western Mutual Ins. Co.
v.
Yamamoto
(1994)
Section 2809 provides in full: “The obligation of a surеty must be neither larger in amount nor in other respects more burdensome than that of the principal; and if in its terms it exceeds it, it is reducible in proportion to the principal obligation.”
Section 2810 provides in full: “A surety is liable, notwithstanding any mere personal disability of the principal, though the disability be such as to make the contract void against the principal; but he is not liable if for any other reason there is no liability upon the part of the principal at the time of the execution of the contract, or the liability of the principal thereafter ceases, unless the surety has assumed liability with knowledge of the existence of the defense. Where the principal is not liable because of mere personal disability, recovery back by the creditor of any res which formed all or part of the consideration for the contract shall have the effеct upon the liability of the surety which is attributed to the recovery back of such a res under' the law of sales generally.”
Subdivision (a) of section 2856 provides in full: “(a) Any guarantor or other surety, including a guarantor of a note or other obligation secured by real property or an estate for years, may waive any or all of the following: [$ (1) The guarantor or other surety’s rights of subrogation, reimbursement, indemnification, and contribution and any other rights and defenses that are or may become available to the guarantor or other surety by reason of Sections 2787 to 2855, inclusive. Q] (2) Any rights or defenses the guarantor or other surety may have in respect of his or her obligations as a guarantor or other surety by reason of any election of remedies by the creditor. ['jQ (3) Any rights or defenses the guarantor or other surety may have because the principal’s note or other obligatiоn is secured by real property or an estate for years. These rights or defenses include, but are not limited to, any rights or defenses that are based upon, directly or indirectly, the application of Section 580a, 580b, 580d, or 726 of the Code of Civil Procedure to the principal’s note or other obligation.”
We recognize that in enacting the current version of section 2856, the Legislature stated: “It is the intent of the Legislature that the types of waivers described in Section 2856 ... do not violate the public policy of this state.” (Stats. 1996, ch. 1013, § 3, p. 5987.) Because section 2856 does not describe the waiver of defenses based on the rule against the enforcement of unlawful transactions, and the history of the section manifests the Legislature’s intent to preserve pre-Cathay Bank law, this statement cannot reasonably be viewed as evidence that the Legislature intended to abolish or limit the rule.
In so concluding, we do not address the Coopers’ contention that there are triable issues of fact regarding the item of interest valued at $19,014.45.
