Appellant brought this action alleging a temporary regulatory taking and denial of substantive due process. The circuit court granted respondents summary judgment. We affirm.
In 1986, appellant Worsley Companies (Worsley) built a Scotchman on a tract of land (Tract B) leased from Daniel and Mildred Hall (Halls). Worsley constructed a sewer line across an adjacent tract of land (Tract A), which the Halls also owned, and connected it to Town of Mount Pleasant’s (Town’s) sewer system. This sewer line was never dedicated or otherwise transferred to Town or Mount Pleasant Waterworks and Sewer Commission (Commission). In 1994, Worsley was also leasing part of Tract A(A-1) owned by the Halls and began construction of a propane facility. The Halls retained the remaining portion of Tract A (Tract A-2).
In June 1994, Worsley was issued a building permit for the propane facility on Tract A-l. On August 80, 1994, Worsley applied for a water and sewer permit from Commission. Commission informed Worsley that an easement was needed for the existing sewer lines prior to the issuance of a permit. Worsley signed the easement documents and sent them to Commission. Commission responded that the easement would have to be granted by the property owners, the Halls, and not Worsley. Town refused to issue a certifícate of occupancy until Worsley had water and sewer service. Worsley filed an action seeking an injunction and damages against both Town and Commission.
In January 1995, the Halls and Worsley executed an agreement which allowed Worsley access to the existing water and sewer lines which were located on Tract A-2. This agreement satisfied Commission and it granted service to Worsley. Thereafter, Town issued a certificate of occupancy. Worsley amended its complaint to dismiss the injunction cause of action but still sought damages for a temporary regulatory taking and denial of substantive due process.
ISSUE
Did the circuit court err in granting respondents summary judgment?
DISCUSSION
Worsley contends the circuit court erred in granting summary judgment because there were questions of fact surrounding the issues in this case. We disagree.
Worsley contends Commission’s and Town’s refusals to issue the permit and certificate of occupancy constituted a taking of its property. The circuit court held Worsley did not have any protected property interest and, furthermore, the denial of the permit because of the unmet requirement of an easement over the existing sewer lines was not a taking. We agree.
In
Board of Regents v. Roth,
Worsley was not entitled to a water and sewer permit because it did not comply with the conditions required by Commission. Commission has a policy of requiring an easement or some other agreement when a water and sewer line is to be connected to an existing line owned by a different party. This is to prevent one party from not allowing the other party access to the line for repairs or service and maintenance.
See
83 Am.Jur.2d
Zoning and Planning
§ 713 (1992) (“Where the responsible state agency has refused to grant a building permit based on the builder’s plans not meeting the required
The circuit court also did not err in granting summary judgment for Town. Worsley had no entitlement to the certificate of occupancy. Town’s refusal to issue the certificate of occupancy to Worsley was not a regulatory taking. There was no discretion in Town’s actions. Pursuant to S.C.Code Ann. § 6-10-50(h) (Supp.1998), a certificate of occupancy shall be issued only if a building is in accordance with the building permit and other applicable laws. Under Town’s building regulations, a building must be connected to water and sewer service prior to the issuance of the certificate of occupancy. See Building Reg. § 106.1.1; Standard Plumbing Code §§ 601.2.
Worsley also contends the circuit court erred in granting summary judgment on its 42 U.S.C. § 1983 cause of action. We disagree.
Substantive due process protects a person from being deprived of life, liberty or property for arbitrary reasons.
Anco, Inc. v. State Health and Human Services Finance Comm’n,
Worsley then argues in its brief whether Town was grossly negligent is an issue of fact for the jury and, therefore, the circuit court erroneously granted summary judgment on the ground that the Tort Claims Act, S.C.Code Ann. § 15-78-60 (Supp.1997), was applicable. Under § 15-78-60(12) a governmental entity is not liable for a loss resulting from “licensing powers or functions including, but not limited to, the issuance, denial, suspension, renewal, or revocation of or failure or
Worsley relies upon
Staubes v. City of Folly Beach,
AFFIRMED.
